ASX:G1A

Abra Development Works Ramping Up, Major Contracts Finalised

GALENA MINING LTD. ("Galena" or the "Company") (ASX: G1A) announces that Abra Mining Pty Limited ("AMPL"), the joint-venture company for the Abra Base Metals Project ("Abra" or the "Project") has finalised significant contracts in relation to the development of the Abra lead-silver Project. Figure 1 shows Galena, Byrnecut and GRES executives inspecting the new Abra underground Jumbo supplied by Sandvik.


HIGHLIGHTS:

  • Underground mining contract finalised with Byrnecut with mobilisation in the second half of September 2021
  • Plant construction contract with GR Engineering Services Limited (ASX: GNG) in full implementation, with key long lead items ordered, FEED completed and the final detailed engineering at 15%
  • Red Dust Holdings have commenced site bulk earthworks associated with aerodrome, TSF and plant and infrastructure pads

Managing Director, Tony James commented, "A major milestone has been achieved at Abra with the finalisation of the underground mining contract with Byrnecut and the implementation of the process plant EPC with GR Engineering Services. Both companies have been very strong supporters of the project over a long period of time and its very rewarding for everyone to see the work starting on the ground.

The Byrnecut mining contract is for 4 years, with the remainder of this year and the majority of next year focussed on gaining access to the orebody, 230m below surface. During this time the mine is effectively a "single heading" decline and the manning requirements for that period are far lower than when the mine reaches commercial ore production in 2023. The actual mining work is expected to commence in the coming weeks. Equipment and labour have been sourced and are ready for mobilisation in the second half of September.


Click here for the full ASX release

G1A:AU
The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Gavel and legal books.

Silver Elephant to Appeal Pulacayo Contract Cancelation by Comibol

Silver Elephant Mining (TSX:ELEF,OTCQB:SILEF) has announced plans to appeal the termination of its Pulacayo mining production contract (MPC) by Bolivia’s state-owned mining authority.

The company received a notice of cancelation on Tuesday (December 31) from Corporacion Minera de Bolivia (Comibol), which says the MPC was revoked due to alleged illegal mining activities within the contract area.

Silver Elephant maintains that its operations have been fully compliant with Bolivian regulations and that all required authorizations for mining activities in the Pulacayo area were properly secured.

Keep reading...Show less
Boab Metals

Boab Metals Secures Funding for Sorby Hills Project: A Promising Investment Opportunity

Description

In a game-changing move, Boab Metals (ASX:BML) has locked in crucial funding for its Sorby Hills Project, a significant lead-silver resource nestled in Australia. This financial boost not only fortifies the company's position but also lessens its dependence on equity markets. It's a pivotal stride towards the project's Final Investment Decision (FID), which is on the horizon for late 2025.

Keep reading...Show less
Silver bars, silver bull and stock chart.

Silver Price Forecast: Top Trends for Silver in 2025

The silver price reached highs not seen since 2012 this past year, supported by an ongoing deficit and increasing interest from investors as geopolitical concerns prompted safe-haven buying.

The white metal reached its highest point for the year in October, breaking through US$34 per ounce on the back of a shifting post-pandemic landscape and geopolitical tensions. However, Donald Trump's victory in the US presidential election just a few weeks later buoyed bond yields and the US dollar while weighing on silver and gold.

What will 2025 hold for silver? As the new year approaches, investors are closely watching how Trump's policies and actions could impact the precious metal, along with supply and demand trends in the space.

Keep reading...Show less

First Majestic Provides Update Regarding Gatos Silver's Joint Venture with Dowa Metals & Mining Co., Ltd.

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") announces that Gatos Silver, Inc. ("Gatos") has advised the Company that it has amended and restated its agreements (the "Amended Agreements") with Dowa Metals & Mining Co., Ltd. ("Dowa") regarding the Los Gatos Joint Venture (the "LGJV"). The Amended Agreements, which become effective on January 1, 2025, expand Gatos' management rights within the LGJV and allow for the financial statements of the LGJV to be fully consolidated. For copies of the Amended Agreements, please see the Form 8-K filed by Gatos under its EDGAR profile at www.sec.govedgar. The Amended Agreements do not affect the respective ownership interests of Gatos and Dowa in the LGJV, which remain unchanged at 70% and 30%, respectively. Concurrent with this news release, the Company has filed a material change report dated December 19, 2024 (the "December Material Change Report") under its SEDAR+ profile at www.sedarplus.com, with further details of the Amended Agreements.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Silver bar beside several silver coins.

Silver Price 2024 Year-End Review

The silver price put on a strong performance in 2024, hitting highs not seen in over a decade.

Despite some volatility, factors like increasing industrial demand, safe-haven buying from investors and weakening mining supply all came together during the year to support gains in the price.

All told, silver is up nearly 35 percent since the start of 2024, outperforming gold's 32 percent gain.

Keep reading...Show less

Guanaceví Mill Operating at Full Capacity After Trunnion Installation

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to announce the successful fabrication and installation of its primary ball mill trunnion at the Guanaceví mine.

Guanaceví processing resumed to full capacity this week after the trunnion failure in August (see news release dated August 19 here ). After a 15-week period of operating at a reduced capacity averaging 620 tonnes per day (tpd), the newly fabricated trunnion was installed on November 30 with alignment testing occurring over the ensuing two weeks, restoring the plant to its designed capacity of 1,200 tpd. The total cost of fabrication and installation was just over US$400,000.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×