Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.


Managing Director, Tony James commented, “Record underground development in November with delivery of the first 9,000t of ore to the ROM pad along with successful plant commissioning to date puts Abra on the verge of a quick transition into production. Recruitment and other operational readiness activities are well advanced in preparation for January production”.

Figure 1 – First material being tipped into the crusher during commissioning (Photo 26 November).

Figure 2 – Crushing and screening plant commissioning (Photo 26 November).

The following link will show a short video of the Abra crusher commissioning. https://youtube.com/shorts/iSG58MiW_3o

Update on Abra Project progress

Overall progress continues as planned, with first concentrate production expected in Q1 CY2023, following ore commissioning in January 2023. Practical completion of the processing plant is now expected ahead of schedule in December 2022. The processing plant engineering, procurement and construction has reached 99% complete. Piping and electrical works have made significant progress and at the end of November were 96% and 92% complete, respectively. Mechanical items installation is almost complete at 99%.

In November, the first material was crushed and screened as part of the staged commissioning process. The crushing plant ran at design capacity and all commissioning milestones were successfully achieved. Dry commissioning also progressed in most areas of the plant including water and air services, tailings and concentrate thickening, grinding and reagents. Dry commissioning of the remaining areas will be completed in December. Water commissioning commenced in the tailings and concentrate thickening areas of the plant and the remaining areas are expected to be wet commissioned by the end of December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Mining site with the words "CAPITAL GAINS" superimposed on top of it.

Will Changes to Canada's Capital Gains Tax Hurt Mining Investment and Innovation?

On April 16, the Canadian government tabled its 2024 budget proposal. Called "Fairness for Every Generation," it is aimed at helping Millennials and Gen Zs, with C$535 billion earmarked by the Trudeau government for investments in housing, clean economy initiatives, childcare, healthcare and national security.

But one section of the document has garnered widespread attention — changes to the capital gains tax scheme.

Starting on June 25, 2024, changes to Canada's tax system will aim to “enhance fairness” by adjusting the inclusion rate for capital gains. Individuals with over C$250,000 in annual capital gains will see their inclusion rate increase from one-half to two-thirds, while those with gains below this threshold will maintain the 50 percent inclusion rate.

Keep reading...Show less
Industrial Minerals Limited

IND Establishes HPQ Exploration Target at Pippingarra Project

Industrial Minerals Ltd (ASX: IND or the Company) is pleased to announce a Maiden Exploration Target for High Purity Quartz (HPQ) at its Pippingarra Quarry Project (Pippingarra) located 30km south-east of Port Hedland, in the Pilbara region of Western Australia (Figure 1).

Keep reading...Show less
Firebird Metals

China-Based Battery Grade High-Purity Manganese Production Strategy

Investor Site Visit Presentation - April 2024

Firebird Metals Limited (ASX:FRB) is pleased to present its investor presentation.
Keep reading...Show less
  Summit Minerals Limited

Summit to Acquire Transformational Brazilian Niobium, Rare Earth & Lithium Portfolio

Summit Minerals Limited (ASX: SUM) (“Summit” or the “Company”) is excited to announce that it has signed binding agreements (“Agreements”) to acquire tenement packages highly prospective for rare earth elements (REE), niobium, and lithium. Term sheets were signed with vendors RTB Geologia & Mineracao Ltda (RTB), Sandro Arruda Silva Ltda. (SAS), and Mineracao Paranal Ltda (MPL) to acquire legal ownership and title over certain Exploration Permits and Applications for Exploration covering an area of 29,267 hectares in Minas Gerais and Paraiba States, Brazil (Figure 1; Table 2).

Keep reading...Show less
West Cobar Metals Limited

Positive Findings from Newmont Ti Benchmarking Study

West Cobar Metals Limited (ASX:WC1) (“West Cobar”, “the Company”) is pleased to provide an update on activities at its Salazar critical minerals project in Western Australia.

Keep reading...Show less
Augustus Minerals

High Grade Copper Rock Chips to 18% on New Targets at Ti-Tree

Augustus Minerals (ASX: AUG; “Augustus” or the “Company”) is pleased to advise the results of recent reconnaissance mapping and sampling at the Ti-Tree Project, located 200kms east of Carnarvon in Western Australia. The mapping, supported by 26 rock chip samples, identified two areas containing mineralised veins and historic workings (Figure 1). Neither of these prospects are recorded on GSWA maps.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×