Construction Nearly Completed at Trevali Mining’s Santander Mine

Silver Investing

Trevali Mining Corporation (TSX:TV,OTCQX:TREVF,FWB:4TI) reported that core site infrastructure at its Santander Zinc-Lead-Silver Mine in Peru is now complete and fully operational, and that construction of the plant is progressing well, with commissioning anticipated in the fourth quarter.

Trevali Mining Corporation (TSX:TV,OTCQX:TREVF,FWB:4TI) reported that core site infrastructure at its Santander Zinc-Lead-Silver Mine in Peru is now complete and fully operational, and that construction of the plant is progressing well, with commissioning anticipated in the fourth quarter.

As quoted in the press release:

Construction of the Plant is progressing: the mills are installed, the flotation building erected and the flotation cells are installed, crusher and zinc and lead thickener foundations completed, new steel for mill and crusher buildings is on site and is being erected and the crushers are being installed, tailings dam sealing is ongoing and mineral stockpile preparation is advanced.

Based on current development schedules it is anticipated that approximately 95,000 tonnes of mineralized material grading 5.61% Zn, 0.65% Pb and 1.65 oz/t Ag will be stockpiled and available for mill commissioning.

Click here to read the Trevali Mining (TSX:TV,OTCQX:TREVF,FWB:4TI) press release

See this press release on Marketwire
Click here to see the Trevali Mining (TSX:TV,OTCQX:TREVF,FWB:4TI) profile

The Conversation (0)
×