- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
Heron Resources Announces December 2017 Quarterly Update on the Woodlawn Zinc-Copper Project
Heron Resources Ltd. (TSX: HER; ASX: HRR) (“Heron” or the “Company”) announces its quarterly activities for the three months ended December 31, 2017. Details of the Company’s results are contained in the filing “Heron Resources Limited Quarterly Report December 2017” which is available on SEDAR at www.sedar.com and the Company’s website www.heronresources.com.au As quoted in …
Heron Resources Ltd. (TSX: HER; ASX: HRR) (“Heron” or the “Company”) announces its quarterly activities for the three months ended December 31, 2017. Details of the Company’s results are contained in the filing “Heron Resources Limited Quarterly Report December 2017” which is available on SEDAR at www.sedar.com and the Company’s website www.heronresources.com.au
As quoted in the press release:
December Quarter 2017 Highlights
Woodlawn Zinc-Copper Project
Earthworks – significant works completed over the process plant area, ROM pad, site access road and administration areas. Works commenced on Tailings Storage Facility 4, box-cut and haul road construction
EPC – engineering design is 50% completed and procurement 30%. Civil works are scheduled to start in the current quarter
Project Schedule – the project critical path schedule remains on track and on budget
Underground Mining Contract – discussion are well advanced with award expected in the current quarter
Port Contract – discussions are well advance and award is expected in the current quarter
Operational Readiness – recruitment continues with a focus on the operational superintendents with a number of appointments expected in the current quarter