SEMAFO Announces Commissioning of the Boungou Mine is Underway

Precious Metals

SEMAFO Inc. announced that the commissioning of the Boungou Mine process plant is underway, with first gold pour expected in June.

SEMAFO Inc. (TSX:SMF) announced that the commissioning of the Boungou Mine process plant is underway, with the first ore scheduled to be introduced to the mill circuit by month-end. The company expects to achieve the first gold pour at Boungou in June, slightly ahead of schedule.

Highlights are as follows:

Overall project 97 percent complete

  • Construction of the processing plant 100 percent complete

• Commissioning 57 percent complete

  • Crushing circuit, vertimill, pre-leach and tailings thickeners, leaching/CIP circuit and water services are already commissioned
  • Commissioning of the SAG mill, gravity, elution circuit, gold room, compressors and oxygen plant initiated in May

• Development on budget with US$202 million of the US$231 million capital expenditure incurred

• Pre-stripping 87 percent completed with 15.6 million of the projected 18 million tonnes extracted

  • 70,000 tonnes of low-grade ore have been stockpiled on the ROM pad

• Recruitment of mine operator employees is near-complete

  • Training will be completed in May

• 1,480 personnel including contractors were employed on site, 86 percent of whom are Burkinabe

  • Demobilisation of construction and contract personnel has commenced

• 5.2 million man-hours (515 days) have been worked without lost-time injury

Click here to read the full SEMAFO Inc. (TSX:SMF) press release.