- WORLD EDITIONAustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
Equinox Gold Begins Stockpiling of Ore at Aurizona Gold Mine
Equinox Gold Corp. provided an update on construction progress at its Aurizona gold mine in Brazil. Construction remains on budget and on schedule to pour gold by late 2018 with the expectation of producing on average 136,000 ounces of gold per year.
Equinox Gold Corp. (TSXV:EQX, OTC:EQXGF) provided an update on construction progress at its Aurizona gold mine in Brazil. Construction remains on budget and on schedule to pour gold by late 2018 with the expectation of producing on average 136,000 ounces of gold per year.
Highlights are as follows:
- Stockpiling of ore commenced on July 18
- New SAG and ball mills have been delivered to site and installation is underway
- Overall project is 60 percent complete
- Concrete work is 82 percent complete
- Plant construction is 51 percent complete
- EPCM (engineering, procurement and construction management) activities are 75 percent complete
- Engineering is complete
As quoted in the press release:
The SAG and ball mills have been delivered to site and installation is underway. Concrete work continues in the surge bin, reagent and thickening areas and is 92 percent complete in the crusher area, 93 percent complete in the grinding area and finished in the leaching area. Structural steel erection in the grinding area is well advanced and the thickener tank platework is complete.
Pre-production mining activities commenced in mid-April and are progressing on schedule. The mining contractor has removed more than 986,000 tonnes of waste to date and roadwork is well advanced. Stockpiling of ore to prepare for commissioning of the plant commenced on July 18, 2018.
The US$146 million project budget remains fully funded. As at June 30, 2018, the company had spent US$64 million of the project budget. The remaining US$82 million of project spend will be funded by a combination of: (i) cash on hand at June 30, 2018 of US$65 million; (ii) US$30 million of project debt draws (the company drew US$40 million of project debt from the US$85 million facility during Q2-2018 and US$15 million in Q4-2017); and (iii) receivables as at June 30, 2018 totalling over US$12 million.
Latest News
Investing News Network websites or approved third-party tools use cookies. Please refer to the cookie policy for collected data, privacy and GDPR compliance. By continuing to browse the site, you agree to our use of cookies.