Dynacor Gold Mines Reports Veta Dorada Ore Processing Plant Construction 70 Percent Complete

Gold Investing

Dynacor Gold Mines (TSX:DNG) put out a second progress report on construction of its 300 tonne per day ore processing plant in Chala, Southern Peru. Construction is now 70 percent complete, and the company expects construction to be finished during the first quarter of 2016.

Dynacor Gold Mines (TSX:DNG) put out a second progress report on construction of its 300 tonne per day ore processing plant in Chala, Southern Peru. Construction is now 70 percent complete, and the company expects construction to be finished during the first quarter of 2016.
As quoted in the press release:

Installation of the seven (7) cyanidation tanks on their bases (see photo below) as well as the two (2) primary ore crushers and three (3) conical ore crushers is moving forward quickly and should be completed by the end of January 2016. Ore transport conveyor belts will be installed as soon as possible thereafter.
Work on the ore storage area and the tailings pond is underway and should be completed by the end of January 2016. Building of the laboratory and the desorption plant has begun and is scheduled to be finished in February 2016.
The Corporation has a Quality Assurance and Quality Control program (QA/QC) that systematically monitors and tests every step of the construction process in order to avoid any surprises later on. For instance, quality control tests are performed to determine concrete resistance parameters and all the welding is independently inspected.
The work on the plant is moving forward at a satisfactory pace and construction activities will continue throughout the Christmas and New Year holiday season.