Japan’s First Reactor Restart Delayed to August

Energy Investing

Reuters reported that Kyushu Electric Power Company’s Sendai reactor restart has been delayed to August instead of the previous target of restarting in July.

Reuters reported that Kyushu Electric Power Company’s (TYO:9508) Sendai reactor restart has been delayed to August instead of the previous target of restarting in July.

As quoted in the market news:

The delay to mid-August from the previous target of late July follows a warning by Japan’s nuclear regulator in April that the utility’s schedule for a restart was too optimistic.

All 43 of Japan’s operable nuclear reactors are currently offline. A restart of Sendai’s 890-megawatt No. 1 unit following stringent safety checks would mark the first resumption of nuclear power generation in nearly two years.

Prime Minister Shinzo Abe has said rebooting the country’s nuclear sector is needed to cut the cost of using fossil fuels for power generation, but he faces a deeply skeptical public after the meltdowns at the Fukushima Daiichi plant north of Tokyo.

Kyushu has notified the nuclear regulator that operational checks of some facilities needed before it can start loading uranium fuel into the reactor are likely to end two weeks later than previously announced, a Kyushu spokesman said.

Delaying the restart would likely raise the consumption of fossil fuels in the peak summer demand season, the spokesman said, declining to give details.

Click here to read the full Reuters report.