- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
Northern Minerals Managing Director George Bauk is pleased to provide a progress update on the Browns Range Pilot Plant Project, under construction in the East Kimberley region of WA, including the following achievements: Mining 65% completed and on track to be completed by end of 2017 Bulk earthworks completed and Maca Civil demobilised First shipment …
Northern Minerals Managing Director George Bauk is pleased to provide a progress update on the Browns Range Pilot Plant Project, under construction in the East Kimberley region of WA, including the following achievements:
- Mining 65% completed and on track to be completed by end of 2017
- Bulk earthworks completed and Maca Civil demobilised
- First shipment of modular process plant equipment from Sinosteel MECC on water and due in Australia by end of October
- Construction group, Primero mobilised and first concrete poured Mining of ore at the Wolverine and Gambit West pits is 65% complete, with 117,000 tonnes of ore delivered to the ROM pad. Mining, being undertaken by MACA Mining, is on schedule for completion before the end of 2017.