GoviEx Uranium Announces Positive Feasibility Study Results for Madaouela Uranium Project

  • Feasibility Study brings GoviEx closer to its principal objective of becoming a significant uranium producer
  • Solid results coupled with strengthening sentiment in favour of nuclear and shortage of supply underpin project development

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx or the Company") is pleased to announce the results of its Feasibility Study ("FS") representing an important milestone as GoviEx advances the Madaouela Uranium Project (the "Project") towards Project financing and development.

The FS was prepared by SRK Consulting (UK) Limited and SGS Bateman (Pty) Ltd., in the format of the Canadian Securities Administrators' National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") with the support of the Company's internal technical team. The Feasibility Study will be filed by GoviEx under its profile at www.sedar.com within 45 days from the date of this news release.

The FS represents an extremely detailed, fully costed, and updated engineering study of the Project taking into account international best practices and standards for responsible project development.

FS Highlights:

  • One of the largest uranium resources in the world, with 100 million pounds of U3O8 in measured and indicated mineral resources, plus inferred resources of 20 million pounds of U3O8
  • Located in a mining-friendly jurisdiction with all major permits required for development already secured.
  • FS is based on a self-sustaining operation including process plant and renewable power supply with no reliance on third party facilities
  • After tax NPV 8% of USD 140 million and IRR of 13.3%
  • Life of mine ("LOM") uranium production of 50.8 million pounds U3O8; averaging 2.67 million pounds U3O8 per annum over 19 years
  • Intensive pilot plant testing underpinning LOM recovery of 92.2% for uranium and 80.7% for molybdenum
  • Total initial capital costs of USD 343 million
  • LOM EBITDA of USD 1,570 million, at an average annual rate of USD 82.6 million and net free cashflow of USD 672 million
  • Reduced construction and operational risks through process simplification utilizing industry standard process design
  • Strong commitment to ESG through prioritizing the use of local skilled labour, local vendors, and labour force diversification
  • Grid connection with the addition of 8MW of hybrid solar power plant resulting in 26% of renewable power generation
  • Next steps to accelerate Project financing and offtake discussions

Commenting on the completion of its FS, Govind Friedland, Executive Chairman, said:

"The FS confirms the strength of the Madaouela project and its ability to deliver good economic results at a time when inflationary pressures are having a significant impact on the development of new projects and operating mines. The completion of our FS represents another major step in our company's development and its goal of becoming a significant uranium producer. This FS, along with the current strengthening uranium demand combined with the fact that our project is fully permitted, distinguishes Madaouela as a unique development opportunity.

We believe the results of this FS will appeal to stakeholders, potential investors, customers, and lenders and will allow us to evaluate a wide range of development alternatives as we continue to focus on maximizing shareholder value. We maintain our projection to be able to start producing in 2025, subject to project financing".

The FS succeeded in delivering a project that is technically robust and significantly simplified, reducing development and operational risk at a time of high inflationary pressure.

Daniel Major, CEO, added: "We are delighted with the series of elegant engineering solutions our technical team has achieved to place the Madaouela project ready for development and to potentially become one of the first new mines developed in this exciting new uranium cycle. The strong FS results further indicate the technical strength of GoviEx's main uranium project in Africa. The next steps for us are to accelerate project financing and to continue to pursue offtake opportunities.

With two permitted mines in two mining-friendly jurisdictions, the backdrop of a strengthening uranium market, we are well positioned to become a uranium producer. Additionally, we have a huge exploration potential upside as we hold one of the largest underdeveloped uranium resources in the world"

The Project will provide considerable employment opportunities in the area, contributing towards social and economic development through the payment of royalties and taxes to the government of Niger. GoviEx is committed to acting responsibly across all of the activities it undertakes, and the Company strategy includes diversification of the workforce and a commitment to local employment and local procurement. Our partnership with the Niger government has been strong and reliable and GoviEx looks to continuing this cooperative relationship as the project is developed.

Project Overview

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_001.jpg

Madaouela Site Drilling Program at Madaouela

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_001full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_002.jpg

Madaouela Site Drilling Program at Madaouela

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_002full.jpg

The Project is situated in the Agadez region in the northern part of the Republic of Niger adjacent to ORANO SA's operations of SOMAIR and COMINAK and benefits from the existing infrastructure and an experienced local uranium mining labour force. GoviEx operates the Project and holds an 80% interest of the Nigerien operating company COMIMA with the remaining 20% held by the Republic of Niger, of which 10% represents a free-carry interest. The Project also includes a series of other deposits, not included in the 2022 FS, that are anticipated to be mined by either open pit or underground methods.

The Republic of Niger is currently the 5th largest producer of uranium in the world and was the largest supplier of U3O8 to Europe in 2021, accounting for approximately a quarter of total imports. The project therefore is advantageously placed in a mining friendly jurisdiction and currently has all major permits required for development.

The current structural deficit in the uranium market requires that new mines are developed in the near term to continue the generation of carbon-free nuclear power. GoviEx has taken another important step towards further developing our mining plans through completing this FS.

The FS included detailed environmental and social criteria which informed engineering and process designs and equipment choices. The standards in the ESG criteria build on GoviEx's corporate commitment that the project will meet International Financial Corporation performance standards. The design criteria were driven by the minimisation of water use, inclusion of solar power and local recruitment and training commitments.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_003.jpg

Exploration activities at Madaouela

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_003full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_004.jpg

Exploration activities at Madaouela

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_004full.jpg 

Mineral Resource Estimate

Mineral Resources of the Project comprise the Miriam, M&M, MSNE, MYVE, MSEE, and MSCE sandstone-hosted uranium deposits. A significant infill diamond drilling program, conducted by GoviEx in 2021 at both the Miriam and M&M deposits, has locally increased sample density and provided chemical assay data for Uranium ("U") and Molybdenum ("Mo"). The U assay information has been used to verify the eU assays derived from downhole radiometric surveys, upon which the Mineral Resources are based.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_005.jpg

Figure 1: Plan view of the Madaouela Uranium Project

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_005full.jpg

The geological models and Mineral Resource estimates for the Miriam, M&M, MSCE, and MSEE have been updated considering drill hole information available to March 31, 2022, and key observations of uranium mineralization controls that have been interpreted from this data.

The Mineral Resources have been classified and reported considering the definitions and guidelines of the CIM Definition Standards for Mineral Resources & Mineral Reserves. The 2021 GoviEx drilling program has successfully increased confidence in the Mineral Resource estimates which is reflected in the increased tonnage reporting in the Measured category for both Miriam and M&M deposits compared to the April 5, 2021, Updated pre-feasibility Study ("PFS")1.

The addition of molybdenum assays from the 2021 program have also facilitated the modelling and estimation of molybdenum Mineral Resources for the first time at both Miriam and M&M deposits. However, due to the limited lateral extent covered by molybdenum sampling compared to eU, molybdenum Mineral Resources have not been estimated for the entire uranium mineralized volume at M&M.

Table 1- Summary of the Madaouela Uranium Mineral Resources, effective date July 01, 2022

ClassificationTonnes (Mt)GradeMetal
eU (kg/t)eU3O8 (kg/t)eU3O8 (t)eU3O8 (Mlb)
M&M
Measured3.001.501.775,25711.6
Indicated14.001.191.4119,72643.5
Inferred3.100.961.143,4777.7
Miriam
Measured10.700.670.798,38418.5
Indicated0.500.460.542810.6
MSNE
Indicated5.051.371.618,11117.9
Inferred0.101.141.341310.3
Maryvonne
Indicated1.231.521.792,1954.8
Inferred0.421.411.667031.6
MSCE
Inferred1.161.151.351,5713.5
MSEE
Inferred1.951.311.543,0036.6
TOTAL MEASURED13.700.851.0013,64130.1
TOTAL INDICATED20.781.241.4630,31366.8
TOTAL INFERRED6.731.121.338,88519.6

 

Table 2 - Summary of the Madaouela Molybdenum Mineral Resources, July 01, 2022.

ClassificationTonnes (Mt)GradeMetal
Mo (ppm)Mo (Tonnes)
M&M
Indicated1.90486914
Inferred4.903881,897
Miriam
Measured10.701011,076
Indicated0.503820
TOTAL MEASURED10.701011,076
TOTAL INDICATED2.40393934
TOTAL INFERRED4.903881,897

 

In reporting the Mineral Resource statement, SRK notes the following:

  1. Mineral Resources have an effective date of July 01, 2022
  2. Mineral Resources are classified according to the CIM Definition Standards for Mineral Resources and Mineral Reserves (November 29, 2019).
  3. Mineral Resources are reported here are Inclusive of Mineral Reserves and are reported as undiluted, with no mining recovery applied in the Mineral Resource statement.
  4. Technical and economic assumptions were agreed between SRK and GoviEx for mining factors (mining and processing costs) and processing factors (metal recovery, processing costs), which were used for optimisation, and which were developed to a Feasibility Study level of detail and accuracy.
  5. SRK considers there to be reasonable prospects for economic extraction by constraining the resources within an optimized pit shell shape constructed assuming a Uranium price of US$70/lb U3O8
  6. Mineral Resources are reported within volumes defined by the Optimized pit shell above a eU cut-off of 0.22 kg/t.
  7. Tonnages are reported in metric units, grades in kilograms-per-tonne (kg/t) and parts-per-million (ppm), and the contained metal in Tonnes and Million pounds (M lbs). Tonnages, grades, and contained metal totals are rounded appropriately.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_006.jpg

Figure 2: M&M deposit coloured by classification for eU

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_006full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_007.jpg

Figure 3: M&M deposit coloured by classification for Molybdenum

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_007full.jpg

Open Pit Mining

Mining operations for the Project are planned to be based on standard truck and shovel open pit mining for the Miriam deposit at a planned rate of 1 Mt per annum of ore feed to the process plant.

The life of pit stripping ratio was reduced to 9.3:1 from the 9.9:1 set out in the PFS, due to re-allocating ramps along the internal walls. A re-scheduling of pre-production waste stripping has reduced this process to 9 months instead of the two years forecast in the PFS, resulting in a reduction of capital mining costs. Following pre-production Miriam continues for a further five years of mining operations.

Mining operating and capital costs have been updated with a high degree of confidence as they are based on current supplier quotes to define owner-operator operating costs of USD 2.06 /tonne mined.

Table 3 - Summary of the Madaouela Uranium Mineral Reserves for the Miriam open pit deposit

ClassificationQuantity
(kt)
U Grade
(kg/t)
Mo Grade
(ppm)
U Contained
(t)
U3O8 Contained
(Mlb)
Mo Contained
(t)
Open Pit Miriam
Proven5,3440.88124.34,69612.21664
Probable550.400.0220.060
Sub-Total5,3990.87123.14,71812.27664

 

Notes:

  1. All figures are rounded to reflect the relative accuracy of the estimate and have been used to derive sub-totals, totals and weighted averages. Such estimates inherently involve a degree of rounding and consequently introduce a margin of error. Where these occur, SRK does not consider them to be material.
  2. The Concession is wholly owned by and exploration is operated by Goviex.
  3. The standard adopted in respect of the reporting of Mineral Reserves for the Project, following the completion of required technical studies, is in accordance with the NI 43-101 guidelines and the 2014 CIM Definition Standards, and have an Effective Date of 1 July 2022.
  4. The Open Pit Mineral Reserves are reported with engineered pit designs using a cut-off grade of 0.28 kg/t U, which is based on a selling price of US$55/lb U3O8, operating costs of US$33.48/t feed, recovery of 94.5%, royalty of 9%, and transportation costs of 0.97/lb U3O8.
  5. The Open Pit Mineral Reserves are derived from a regularized block model of 7.5 m x 7.5 m x 0.75 m and include an additional 2% dilution and no mining loss.
  6. The qualified person for the open pit design is Colleen MacDougall, PEng employee of SRK Consulting (Canada) Inc.
  7. Rob Bowell and Guy Dishaw of SRK both appropriate "independent qualified person" as defined in National Instrument 43-101 have completed site inspections of the deposit
  8. The qualified person for the FS Reserve Statement is Rob Bowell PhD, C.Chem. C.Geol, employee of SRK Consulting (UK) Ltd

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_008.jpg

Figure 4: Plan view of Miriam Waste Storage Areas (Source: SRK, 2022)

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/137769_2c589e9094300bcb_008full.jpg

Underground

The M&M and MSNE-Maryvonne deposits are planned to be mined as two independent underground room and pillar operations. M&M is to be mined first following completion of the Miriam open pit operation, with MSNE-Maryvonne mined after M&M. These mining methods are similar to the adjacent ORANO S.A.'s. COMINACK mine (closed in 2021) and SOMAIR mine, which together created a wide pool of skilled, trained labor in the area.

At both underground operations the mine development and ore production operations are planned to be by conventional drill and blast. Ore panels are to be mined as room and pillar, with ventilation provided by multiple raise bored holes positioned in each panel. Mined ore is expected to be fed onto a conveyor system via feed breakers. Run of mine ore will be sorted at the portal by X-ray fluorescence ("XRF"), and post sorted ore is planned to be trucked to the process plant at a rate of 1.0 Mtpa.

M&M development is planned to take 18 months until first ore, with an estimated production duration of 11 years. MSNE-Maryvonne decline and development are planned to start in Year 10, with a development period of 28 months and an estimated production duration of 5 years.

Updates to the underground mining study include:

  1. M&M mine design updated with adjustments to main access tunnels and panel orientations in the SW of the deposit,
  2. Increased granularity in M&M's mine schedule following a new approach to define the ore body mining tonnes.
  3. Review and update of the mine ventilation approach for both M&M and MSNE-Maryvonne mine.
  4. Reserve update following mine design adjustments and resource classification update.

Underground mining costs have been updated following a cost model rebuild and minor cost input updates, with owner-operating costs of USD 31.44 per tonne of ore mined.

Besides the improvements in the underground mine plan, there have also been schedule and overall underground mining assumption improvements. The underground mining study has updated considerably but overall remains at a pre-feasibility level.

Table 4 Underground Reserves

ClassificationQuantityU GradeMo GradeU ContainedU3O8 ContainedMo Contained
(kt)(kg/t)(ppm)(t)(Mlb)(t)
Underground M&M
Proven3,1491.063,3538.72
Probable10,6020.81798,62922.43834
Sub-Total13,7500.876111,98131.15834
Underground MSNE+Maryvonne
Proven
Probable6,6520.795,27313.71
Sub-Total6,6520.795,27313.71
Total
Proven3,1491.063,3538.72
Probable17,2540.81 4813,90236.14834
Total20,4030.854117,25544.86834

 

Notes:

  1. All figures are rounded to reflect the relative accuracy of the estimate and have been used to derive sub-totals, totals and weighted averages. Such estimates inherently involve a degree of rounding and consequently introduce a margin of error. Where these occur, SRK does not consider them to be material.
  2. The Concession is wholly owned by, and exploration is operated by, GoviEx.
  3. The standard adopted in respect of the reporting of Mineral Reserves for the Project, following the completion of required technical studies, is in accordance with the NI 43-101 guidelines and the 2014 CIM Definition Standards, and have an Effective Date of 1 July 2022.
  4. The Underground Mineral Reserves are reported using a variable cut-off grade ranging between 0.5 and 0.6 kg U/t to account for the effect of ore sorting to reduce the dilution associated with varying seam thicknesses in different underground panels. This is based on a selling price of US$55/lbU3O8 , operating costs of US$33.48/t feed, recovery of 94.5%, royalty of 9%, and transportation costs of 0.97/lb U3O8.
  5. The qualified person for the underground design is Jurgen Fuykschot, MAusIMM(CP), employee of SRK Consulting (UK) Limited at the time of the Feasibility Study.
  6. Rob Bowell and Guy Dishaw of SRK, both appropriate "independent qualified person" as defined in National Instrument 43-101 have completed site inspections of the deposit.
  7. The qualified person for the FS Reserve Statement is Rob Bowell PhD, C.Chem. C.Geol, employee of SRK Consulting (UK) Ltd

The reported Mo grade is averaged over the total reserve tonnage and does not represent the in-situ Mo grade for the total reserve. It should be noted that at M&M the Mo grade, for the indicated Mo resource only, is 486ppm.

Processing

The process plant is designed around two stage acid leaching to maximised uranium and molybdenum recovery whilst reducing overall acid consumption. Plant feed is designed at 1 Mtpa, with ore initially crushed before milling. The Feasibility Study has been moved away from SAG milling in the comminution circuit due to the introduction of the two VeRo Liberator mills as a replacement in order to reduce operating and capital costs associated with the comminution process as well as improving total power required.

Milled ore is planned to be leached using sulphuric acid to extract the uranium and molybdenum into solution, with the molybdenum to be removed from the solution by continuous flow Ion Exchange, rather than cartridge approach to reduce operating costs, with precipitation of the molybdenum to produce molybdenum tri-sulphide (MoS3). The Project is designed to produce triuranium octoxide (U3O8) through industry standard ammonium diuranate (ADU) and calcination.

The Company undertook a considerable program of processing test-work with an aim to validate the technical risks associated with the application of each process route, targeting ore upgrading, acid consumption reduction and general reduction of costs. The test-work completed included: Comminution test work and VeRo pilot testing, Leach optimization, Thickening and Filtration, Ion Exchange ("IX"), Solvent Extraction ("SX") and flotation. Work focused on defining the circuit optimized operating conditions and validation of processing technologies and application.

Assay results confirm that the U3O8 produced as a result of the test work is well within the specifications required by the convertors.

The key design parameters for the Madaouela Process plant are summarised in the tables below for the open pit and the underground. The difference in uranium and molybdenum recoveries is associated with losses forecast in the XRF sorting process.

Table 5 - Key Process Design Parameters (Open Pit mining)

Parameter
Annual Ore Fed to Process Plant (Design)1,000,000 tpa
Uranium Recovery94.8%
Molybdenum Recovery88.9%
Acid Consumption per tonne of ore feed50 kg/t
Raw Water Feed106 m3/hr

 

Table 6 - Key Process Design Parameters (Underground mining)

Parameter
Annual Ore Fed to Process Plant (Design)1,000,000 tpa
Uranium Recovery91.5%
Molybdenum Recovery79.9%
Acid Consumption per tonne of ore feed50 kg/t
Raw Water Feed106 m3/hr

 

The simplification of the process flowsheet and the extensive level of confirmatory test work completed by the Company readily translates to a confident feasibility design with optimized comminution, leaching, solvent extraction, and ion exchange recovery processes.

Infrastructure

The Project benefits from its close proximity to the uranium mining towns of Arlit and Akokan, and this includes access to grid level electrical power existing near the Project boundary. However, grid power is not stable 24/7 and accordingly, the feasibility study includes addition of a standalone hybrid diesel-solar-battery power plant to compliment grid power and ensure energy security as well as optimize running costs through renewable energy supply to the project.

The power supply strategy utilises two key advantages of the area; connection to the grid and installation of a solar farm. Grid power is accessed via a dedicated 20 kV overhead power line. The standalone hybrid diesel-solar-battery power plant will ensure energy security, optimize the levelized cost of energy through renewable energy supply and minimize GHG emissions through renewable energy supply. The selected solution comprises 8 MW of installed solar panels and a 5 MWh battery storage system. This results in renewables accounting for approximately 26% total power consumption. There will be opportunity to consider a power purchase agreement (PPA) in the next stage to reduce upfront capital costs, and potential to increase the installed solar capacity in the future.

Water Supply and Management

The feasibility study included development of a site wide water balance, with the design parameters including strategies to minimise and conserve water consumption. Accordingly, open pit and underground mining dewatering plans are designed to either to use the water in the process plant or re-inject into local aquifers. Make-up water demand for the process plant will be supplied by a wellfield approximately 6 km to the east, which will have a total installed capacity of 150 m3/hr provided by 5 production wells powered by solar power.

Tailings Management

The Project's tailings storage facility ("TSF") has been designed for filtered tailings, like the disposal methodology used at the nearby SOMAIR and COMINAK sites. The TSF site has been selected based on proximity to the processing plant and orientated to take advantage of the natural topography to promote seepage to a lined evaporation pond at the edge of the facility. The whole TSF will be lined and progressively capped and rehabilitated to minimise dust generation over the life of the mine.

Operating Costs

A detailed reassessment of the operating costs has been fully updated and based in recent quotations and tenders. Open pit and underground mining costs, as well as SG&A costs remained relatively unchanged from the PFS. Process costs have, however, been impacted by the global inflation of reagents prices associated with the hydrocarbon industry, in particular sulfur, used to make sulfuric acid for the leaching of uranium, has increased 63% since the PFS.

Table 7 - Project Unit Operating Costs

USD /t ProcessUSD /lb U3O8
Open Pit Mining20.769.13
Underground Mining44.0116.04
Total Mining*38.0714.50
Processing35.7513.62
SG&A9.293.53
Royalty Tax12.064.59
Total Operating Costs95.5836.41
Total Operating Costs net of Mo reserve case 94.0035.8
Total Operating Costs
Net of Mo all resource case
88.0233.52

 

*Weighted average between open pit and underground mining costs

The Madaouela Project contains molybdenum mineralisation in both the Miriam open and the underground mines, and this saleable by-product results in additional revenue to support the development of the project and its cashflows.

It is of note that the process plant has been designed and costed for the recovery of molybdenum for the life of the mine. While molybdenum reserves are defined for the Miriam open pit and the initial mining period in the M&M, the molybdenum resources have not been classified for the rest of M&M and MSNE, but the financial model continues to incur the associated costs with its recovery. The table below provides an estimate of the impact of inclusion of the non-M&I molybdenum mineral resources as a sensitivity.

Table 8 - Molybdenum by-product credits

USD /t ProcessUSD /lb U3O8
Mo Mineral Reserve Case1.580.60
Mo All resources Case 7.562.88

 

Capital Costs

The table below shows the proposed capital requirements of the Project's initial development and remaining life of mine sustaining capital costs. The majority of the sustaining costs are related to the development costs associated with the M&M and MNSE-Maryvonne deposits.

Initial capital costs are forecast to be USD 342.7m, and includes pre-stripping of the Miriam deposit.

Table 9 - Project initial and sustaining capital

USDm Initial CapitalSustaining Capital
Open Pit46.12.7
Underground-218.6
Processing242.43.1
Tailings14.87.8
Infrastructure28.636.7
Water management6.07.6
Owner costs4.8
Total Construction Costs342.7276.6

 

A contingency of 10% is included in the capital figure quoted above.

Based on a uranium price of USD 65/lb U3O8 and molybdenum price of USD 11/lb Mo over the life of mine, the Project is forecast to produce USD 672 million in free cash flow, including capital expenditure, and is forecast to produce an annual average of USD 82 million EBITDA.

The table below provides a sensitivity of the projects NPV and IRR% at a range of uranium prices and is based on the Mineral Reserves only, for both uranium and molybdenum.

Table 10: NPV and IRR sensitivity Mineral Reserve Case

Price (USD/lb U3O8)NPV8%IRR%
60419.7%
6512012.7%
7019915.5%

 

As noted above the process plant has been designed and costed for the recovery of molybdenum for the life of the mine. While molybdenum reserves are defined for the Miriam open pit and the initial mining period in the M&M, molybdenum resources have not been classified for the rest of M&M and MSNE, but the financial model continues to show the associated costs with its recovery. The table below provides an estimate of the impact of inclusion of the non-M&I molybdenum mineral resources as a sensitivity.

Table 11: NPV and IRR sensitivity including addition Mo resources

Price (USD/lb U3O8 )NPV8%IRR%
606110.4%
6514013.3%
7021916.0%

 

A number of potential optimisations are not included in the current study which will be assessed in the next stage, namely:

  • Use of a Power Purchase Agreement ("PPA") for the supply of renewable energy for the project. The FS assumes a USD 14.3 million capital investment at the start of the project to provide a solar hybrid power plant to ensure power stability. Now that the power load is finalised, the next stage can include negotiations for PPA contracts whilst ensuring the Levelised Cost of Electricity (LOCE) is improved.
  • The FS assumes that the Miriam mining fleet would be purchased new as the conservative option, however given the relatively short life of the Miriam deposit, an assessment of second hand/refurbished open pit mining equipment was undertaken. This study indicated that savings between 30 and 60% could be achievable by using second hand or refurbished open pit mining equipment. The initial mining equipment capital cost is currently planned at USD 26.4 million.
  • Underground mineable ore can be accessed from the base of the Miriam Pit and its development would potentially allow access to the MSCE and MSEE deposits, and this is currently not included in the mine plan. At Miriam, approximately 1.53 Mt of measured and indicated resource at 0.85 kg/t U and 0.40 Mt of inferred resource at 0.73 kg/t U, for a total of 1.8 Mlb U3O8, would be accessible from portals that could be developed from the base of the Miriam open pit. In addition, this development would potentially provide direct underground access to the MSCE and MSEE deposits which contain 10 Mlb in the inferred resources (see table 1).

The Company will now work with its debt advisors Endeavour Financial to assess potential financing options for the development of the Project, and parallel to this process will continue with its engagement program with potential off-takers, including North American and European utilities.

GoviEx Uranium will host a webinar to discuss the company's developments today, 20 September 2022 at 11 hrs EST. To participate, sign up here https://redcloudfs.com/rcwebinar-gxu-v-2/

Qualified Person

The scientific and technical information in this release has been reviewed and approved by Dr. Rob Bowell, a chartered chemist of the Royal Society of Chemistry, a chartered geologist of the Geological Society of London, and a Fellow of the Institute of Mining, Metallurgy and Materials, who is an independent Qualified Person under the terms of NI 43-101 for uranium deposits. Mr. Bowell has verified the data disclosed in this news release.

Note 1. See report titled "An Updated Pre-Feasibility Study for the Madaouela Project, Niger" with an effective date of April 5, 2021, which is available at GoviEx's profile on SEDAR at www.sedar.com.

Neither the TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

About GoviEx Uranium

GoviEx is a mineral resource company focused on the exploration and development of uranium properties in Africa. GoviEx's principal objective is to become a significant uranium producer through the continued exploration and development of its flagship mine-permitted Madaouela Project in Niger, its mine-permitted Mutanga Project in Zambia, and its multi-element Falea Project in Mali.

Contact Information

Isabel Vilela
Head of Investor Relations and Corporate Communications
Tel: +1-604-681-5529
Email: info@goviex.com
Web: www.goviex.com

Cautionary Statement Regarding Forward-Looking Statements

This news release may contain forward-looking information within the meaning of applicable securities laws. All information and statements other than statements of current or historical facts contained in this news release are forward-looking information.

Forward-looking statements are subject to various risks and uncertainties concerning the specific factors disclosed here and elsewhere in GoviEx's periodic filings with Canadian securities regulators. When used in this news release, words such as "will", "could", "plan", "estimate", "expect", "intend", "may", "potential", "should," and similar expressions, are forward- looking statements. Information provided in this document is necessarily summarized and may not contain all available material information.

Forward-looking statements include those in relation to, (i) the strength of the Project and its ability to deliver good economic results; (ii) the Project being a unique development opportunity; (iii) Project providing considerable employment opportunities in the area, contributing towards social and economic development through the payment of royalties and taxes to the government of Niger; (iv) the potential and magnitude of exploration potential upside of the Project; (v) that FS will advance the Project towards Project financing and development; (vi) the method and timing of any development and mining operations at the Project; and (vii) the potentially to bring the Project online as one of the first new mines developed in this exciting new uranium cycle.

Although the Company believes the expectations reflected in such forward-looking statements are based on reasonable assumptions, it can give no assurances that its expectations will be achieved. Such assumptions, which may prove incorrect, include the following: (i) that the FS will advance the Project towards Project financing and development; (ii) that the current uranium upcycle will continue and expand; (iii) that the integration of nuclear power into power grids world-wide will continue as a clean energy alternative; and (iv) that the price of uranium will remain sufficiently high and the costs of advancing the Company's mining projects will remain sufficiently low so as to permit GoviEx to implement its business plans in a profitable manner.

Factors that could cause actual results to differ materially from expectations include (i) that the market will not respond as anticipated to the FS; (ii) a regression in the uranium market price; (iii) inability or unwillingness of include or increase nuclear power generation by major markets; (iv) potential delays due to COVID-19 restrictions; (v) the failure of the Company's projects, for technical, logistical, labour-relations, or other reasons; (vi) a decrease in the price of uranium below what is necessary to sustain the Company's operations; (vii) an increase in the Company's operating costs above what is necessary to sustain its operations; (viii) accidents, labour disputes, or the materialization of similar risks; (ix) a deterioration in capital market conditions that prevents the Company from raising the funds it requires on a timely basis; and (x) generally, the Company's inability to develop and implement a successful business plan for any reason.

In addition, the factors described or referred to in the section entitled Risk Factors" in the MD&A for the year ended December 31, 2021, of GoviEx, which is available on the SEDAR website at www.sedar.com, should be reviewed in conjunction with the information found in this news release.

Although GoviEx has attempted to identify important factors that could cause actual results, performance, or achievements to differ materially from those contained in the forward- looking statements, there can be other factors that cause results, performance, or achievements not to be as anticipated, estimated, or intended. There can be no assurance that such information will prove to be accurate or that management's expectations or estimates of future developments, circumstances, or results will materialize. As a result of these risks and uncertainties, no assurance can be given that any events anticipated by the forward-looking information in this news release will transpire or occur, or, if any of them do so, what benefits that GoviEx will derive therefrom. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements in this news release are made as of the date of this news release, and GoviEx disclaims any intention or obligation to update or revise such information, except as required by applicable law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/137769

News Provided by Newsfile via QuoteMedia

GXU:CA,GVXXF
The Conversation (0)
GoviEx Uranium Statement on Recent Coup in Niger

GoviEx Uranium Statement on Recent Coup in Niger

In light of the recent coup d'état in Niger, GoviEx Uranium Inc. (TSXV: GXU) (OTCQB: GVXXF) wishes to assure its stakeholders, partners, and the people of Niger of the following:

GoviEx's operations in Niger remain unaffected by the current situation. We are committed to ensuring that our activities continue as normal, both at our Project site and our office in Niamey.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GoviEx Announces Substantial Increase of Open-Pit Mineral Resources at Its 100% Owned Muntanga Uranium Project in Zambia

GoviEx Announces Substantial Increase of Open-Pit Mineral Resources at Its 100% Owned Muntanga Uranium Project in Zambia

  • Measured & Indicated resources nearly tripled, now representing 74% from 29% of total resources.
  • Total in-pit constrained resources increased 18%.
  • Grade improvement in all mineral categories.
  • Current drilling targeting further potential in pit resource upgrade to measured and/or indicated.
  • Results fully support continued feasibility study.

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx or the "Company") is pleased to announce an updated Mineral Resource Estimate ("MRE") for its wholly owned, mine permitted Muntanga Uranium Project in Zambia (the "Muntanga Project"). The Muntanga Project consists of three mining permits that cover some 720km2, and contains five deposits: Dibbwi, Dibbwi East, Muntanga, Gwabi and Njame.

Daniel Major, CEO of GoviEx commented: "Our drilling campaigns in 2021 and 2022 have led to a significant update in the Muntanga mineral resource estimate. This progress is characterized by a notable growth in in-pit resources, a substantial conversion of inferred resources into the Indicated category, and an overall rise in uranium grades. What's more exciting is that this upward trajectory in resource growth persists even under lower uranium prices, such as the USD50/lb used in our Preliminary Economic Assessment( PEA)1. There is also additional potential for further upgrading of inferred resources, thereby expanding the resources that can be included in the feasibility study. These are very promising results and will be integrated into our ongoing feasibility study."

The 2023 updated MRE is the result of extensive infill drilling, including 8,010 metres drilled in 2021 and a further 19,990 metres drilling in 2022, predominately on the Dibbwi East deposit, to further delineate the deposit and convert inferred resources to the indicated category. The mineral resource update included a comprehensive reassessment of previous work and a revised correlation between down-hole radiometric probe data and chemical assays used to convert down-hole radiometric data into equivalent uranium grades (eU3O8) for mineral resource estimation.

Table 1.0 Comparison between 2017 & 2023 Constrained Mineral Resource Estimates

Constrained Mineral Resource Constrained Mineral Resource % Change
20172023
Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb) Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb) Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb)
Measured & Indicated 16.1735312.5942.5935933.7163%2%168%
Inferred 38.8229425.1614.9533010.88-61%12%-57%

 

Based on the USD50/lb U3O8, used to define the mining schedule in the 2017 PEA, constrained total pit resources are 36.5 Mlb eU3O8, comprising 34 Mt at 374 ppm eU3O8 for 28.4 Mlb in measured and indicated and 11 Mt at 348 ppm eU3O8 for8.1 Mlb of inferred, highlighting the robustness of the mineral resources at Muntanga. With the quality of the resource estimate improved, higher M&I, higher grade and a notable increase in estimated resources within the constrained open-pit area, we are optimistic that the updated MRE will be favourable to the project economics previously estimated for Muntanga in the PEA, and especially as the ongoing drilling is targeting conversion of more inferred resources into indicated resources.

As per the regulations applicable in 2017 when the Company released its NI 43-101 Technical Report1, the MRE reported did not need to be constrained by pit shells based on any particular uranium price, as almost all mineralisation at the time occurred within 125 m of surface with uranium grades that were, in general, considered to have a reasonable prospect for eventual economic extraction ("RPEEE") by open pit mining. The cut-off grade used for reporting the 2017 MRE was 100 ppm eU3O8.

The 2023 MRE is disclosed including an additional constraint applied to comply with the RPEEE and is accordingly reported within a constraining open-pit shell based on a uranium selling price of USD70/lb U3O8 and a 100 ppm eU3O8 cut-off grade. The updated 2023 MRE is presented in Table 3.0.

To facilitate a comparison between the 2023 and 2017 MRE, Table 2.0 below provides an assessment on the impact of a constraining open-pit shell based on uranium selling price of USD70/lb U3O8 and a 100 ppm eU3O8 cut-off grade on the 2017 MRE.

Table 2.0 Comparison of 2017 unconstrained and constrained mineral resources

Unconstrained Mineral Resource
2017
Constrained Mineral Resource
2017
Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb) Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb)
Measured & Indicated21.631815.116.235312.6
Inferred74.627344.938.829425.2

 

The 2017 constrained mineral resources are based on a fixed uranium price, and should uranium prices increase, a conversion of additional material into a constrained mineral resource would be anticipated.

Based on the drilling completed in 2021 and 2022, an updated mineral resource estimate has been prepared by SRK Consulting (Canada) Inc. ("SRK"). The Mineral Resource is that portion of the resource estimate which has been constrained within an open-pit shell, considering reasonable mining, processing and general and administrative cost, geotechnical parameters and processing recoveries. SRK considers that the material reported as a Mineral Resource fulfils the requirement by the CIM Guidelines of having a RPEEE through open pit mining.

A summary of the Mineral Resources for all deposits comprising the Muntanga Project are presented in Table 3.0 below.

Table 3.0 Mineral Resource Statement*, Muntanga Uranium Project, Zambia, effective date of March 31, 2023

ClassificationDepositTonnesU3O8 GradeU3O8
(Mt)(ppm)Mlb
MeasuredGwabi1.12540.6
Njame2.23741.8
IndicatedMuntanga7.53605.9
Dibbwi3.12551.8
Dibbwi East25.237420.8
Gwabi2.73742.2
Njame0.83210.6
     Total M&I42.635933.7
InferredMuntanga4.03192.8
Dibbwi0.62500.3
Dibbwi East9.13446.9
Gwabi0.22790.1
Njame1.13260.8
     Total Inferred15.033010.9

 

*Notes:

  1. The effective date of the mineral resource statement is March 31, 2023. The QP for the estimate is Cliff Revering, P.Eng., an employee of SRK Consulting (Canada) Inc.
  2. Mineral resources are prepared in accordance with CIM Definition Standards (CIM, 2014) and the CIM estimation of Mineral Resources and Mineral Reserves Best Practise Guidelines (CIM, 2019).
  3. Mineral Resources are reported at a cut-off grade of 100 ppm eU3O8.
  4. Mineral resources are constrained within an optimized pit shell using a uranium price of USD70/lb U3O8, mining costs of USD2.90/t, processing costs of USD8.00/t ore, additional ore mining costs of USD0.50/t ore, G&A costs of USD1.50/t ore, royalty of 5% on U3O8 price and a discount rate of 8%.
  5. Mineral resources are not mineral reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the mineral resources will be converted into mineral reserves in the future.
  6. All figures have been rounded to reflect the relative accuracy of the estimate.

Analysis of the open-pit shell used to constrain the MRE highlights that there are still inferred category mineral resources that have the potential to be converted to indicated resources with additional drilling. That would enable them to be included in the economics related to any future feasibility study, as the examples below indicate. This work is currently under way as part of this year's previously announced drilling program.

Figures 1&2: Sections from Dibbwi East showing resource classification and MRE Shell

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_001.jpg

Fig 1

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_001full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_002.jpg

Fig 2

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_002full.jpg

Figure 3 - Dibbwi East drillhole and cross-section location map

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_003.jpg

Fig 3

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_003full.jpg

In conclusion, the updated MRE for the Muntanga Project is a testament to GoviEx's strategic focus and commitment to maximizing the potential of its vast resource base. As the only uranium developer with two African projects ready to begin development and near-term production, GoviEx is well placed to benefit from future growth.

Qualified Person Statement
The technical information and associated data in this release has been reviewed, verified and approved by Cliff Revering, P.Eng., who is an independent Qualified Person under the terms of NI 43-101 for uranium deposits.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

About GoviEx Uranium Inc.
|GoviEx is a mineral resource company focused on the exploration and development of uranium properties in Africa. GoviEx's principal objective is to become a significant uranium producer through the continued exploration and development of its flagship mine-permitted Madaouela Project in Niger, its mine-permitted Mutanga Project in Zambia, and its multi-element Falea Project in Mali.

Contact Information
Isabel Vilela, Head of Investor Relations and Corporate Communications
Tel: +1-604-681-5529
Email: info@goviex.com Web: www.goviex.com

Cautionary Statement Regarding Forward-Looking Statements
This news release contains forward-looking information within the meaning of applicable securities laws. All information and statements other than statements of current or historical facts contained in this news release are forward-looking information.

Forward-looking statements are subject to various risks and uncertainties concerning the specific factors disclosed here and elsewhere in GoviEx's periodic filings with Canadian securities regulators. When used in this news release, words such as "will", "could", "plan", "estimate", "expect", "intend", "may", "potential", "should," and similar expressions, are forward-looking statements. Information provided in this document is necessarily summarized and may not contain all available material information.

Although the Company believes the expectations reflected in such forward-looking statements are based on reasonable assumptions, it can give no assurances that its expectations will be achieved. Such assumptions, which may prove incorrect, include the following: (i) that the Company will be successful in its exploration and development plans for all its projects; (ii) that projected low capital expenditures for the mine-permitted projects will remain unchanged or improve; (iii) that the planned exploration and development programs on GoviEx's projects will be completed as planned and meet GoviEx's objectives; and (iv) that the price of uranium will remain sufficiently high and the costs of advancing the Company's projects will remain sufficiently low so as to permit GoviEx to implement its business plans in a profitable manner.

Factors that could cause actual results to differ materially from expectations include (i) the risk that the Company may not be able to fully realize the anticipated benefits of the updated MRE and the conversion of inferred resources to indicated resources; (ii) the risk that the ongoing feasibility study may not yield the expected results; (iii) the risk that the current drilling program may not result in further potential resource upgrades; (iv) potential delays or changes in the Company's development plans due to various factors, including COVID-19 restrictions; (v) the failure of the Company's projects, for technical, logistical, labour-relations, or other reasons; (vi) a decrease in the price of uranium below what is necessary to sustain the Company's operations; (vii) an increase in the Company's operating costs above what is necessary to sustain its operations; (viii) accidents, labour disputes, or the materialization of similar risks; (ix) a deterioration in capital market conditions that prevents the Company from raising the funds it requires on a timely basis; and (x) generally, the Company's inability to develop and implement a successful business plan for any reason.

In addition, the factors described or referred to in the section entitled "Risks Factors" in the MD&A for the year ended December 31, 2022, of GoviEx, which is available on the SEDAR website at www.sedar.com, should be reviewed in conjunction with the information found in this news release.

Although GoviEx has attempted to identify important factors that could cause actual results, performance, or achievements to differ materially from those contained in the forward-looking statements, there can be other factors that cause results, performance, or achievements not to be as anticipated, estimated, or intended. There can be no assurance that such information will prove to be accurate or that management's expectations or estimates of future developments, circumstances, or results will materialize. As a result of these risks and uncertainties, no assurance can be given that any events anticipated by the forward-looking information in this news release will transpire or occur, or, if any of them do so, what benefits that GoviEx will derive therefrom. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements in this news release are made as of the date of this news release, and GoviEx disclaims any intention or obligation to update or revise such information, except as required by applicable law.


News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GoviEX Uranium Files Annual Information Form

GoviEX Uranium Files Annual Information Form

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx" or the "Company"), a mineral resource company specializing in uranium exploration and development in Africa, announces that further to the filing of its audited consolidated financial statements and management's discussion and analysis for the year ended December 31, 2022, it has today voluntarily filed its Annual Information Form for the year ended December 31, 2022. These filings can be found on the Company's website at www.goviex.com and under the Company's SEDAR profile at www.sedar.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GoviEx Sponsors Barefoot College International's Solar Project in Niger to Support Local Communities

GoviEx Sponsors Barefoot College International's Solar Project in Niger to Support Local Communities

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx" or the "Company") is proud to announce its sponsorship of Barefoot College International's Solar Project in Niger.

This groundbreaking initiative is dedicated to empowering rural women without formal education through comprehensive training in solar technology installation and maintenance, livelihoods development and a holistic women's empowerment curriculum. By fostering self-sufficiency, promoting livelihood development, and ensuring environmental sustainability, the Solar Project aims to enhance the quality of life for individuals living in rural areas.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GoviEx Uranium Provides Update on the Sale of the Falea Exploration Project

GoviEx Uranium Provides Update on the Sale of the Falea Exploration Project

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx" or the "Company"), a mineral resource company specializing in uranium exploration and development in Africa, announces that the agreement with African Energy Metals Inc. ("AEM") for AEM's acquisition of all the issued and outstanding shares of GoviEx's wholly-owned Malian subsidiary, Delta Exploration Mali SARL ("Delta"), which holds the Falea project in Mali, has been terminated due to the fact that AEM was unable to complete its obligations for closing.

In light of this development, GoviEx retains ownership of the Falea project. GoviEx's primary focus is to concentrate its resources on the development of its two advanced-stage mine-permitted projects, namely Madaouela in Niger and Muntanga in Zambia.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GTI Energy

Major 50% Upgrade Boosts Lo Herma Uranium Resource to 8.57Mlbs, Scoping Study Initiated

GTI Energy Ltd (GTI or Company) is pleased to update the uranium Mineral Resource Estimate (MRE) at its Lo Herma Project (Lo Herma or the Project) located in Wyoming’s Powder River Basin (Figure 1). The MRE for the Project is focused on mining by In-Situ Recovery (ISR) methods and is reported at an appropriate cut-off grade of 200 ppm U3O8 and a minimum grade thickness (GT) of 0.2 per mineralised horizon as:

6.21 million tonnes of total mineralisation at average grade of 630 ppm eU3O8 for 8.57 million pounds (Mlbs) of eU3O8 contained metal classified as 2.78Mlbs of Indicated (32%) and 5.79Mlbs of Inferred.

Keep reading...Show less
Nick Hodge, gold bars.

Nick Hodge: Uranium and Gold Outlook for 2025, Plus Battery Passport Profits

In an interview at the New Orleans Investment Conference, Nick Hodge, publisher at Digest Publishing, discussed the growing prevalence of "battery passports" and the investment angle he sees there.

He also shared his thoughts on how to invest in uranium at this point in the cycle, saying that power-intensive artificial intelligence (AI) data centers are boosting demand for the commodity, which was already strong.

"I've been a uranium bull for a long time — our moment is here. You can't have AI without uranium," said Hodge.

Keep reading...Show less
Nuclear Fuels CEO and President Greg Huffman.

Nuclear Fuels Aims to Boost US Domestic Uranium Supply Chain, CEO Greg Huffman says

Issues facing the global uranium supply chain have created a significant opportunity for emerging explorers and producers to leverage the growing demand for nuclear energy and build more secure and stable domestic supply chains.

In an interview with the Investing News Network, Nuclear Fuels (CSE:NF) CEO and President Greg Huffman said his company is strategically positioned to supply growing US uranium demand by advancing its uranium projects in Wyoming.

“We have massive, massive increases in terms of expected demand for uranium,” he said. “What we at Nuclear Fuels are focused on is being able to come up with new sources of domestic US uranium to help supply that increase in demand for nuclear power.”

Keep reading...Show less

Laramide's 2024 Drill Program Continues to Return Strong Results at the Westmoreland Project in Queensland, Australia, including Notable Gold Mineralisation

Highlights:

  • Results continue to demonstrate the potential to link the Huarabagoo and Junnagunna uranium deposits
    • HJ24DD017 – 25.00m @ 393.64 ppm (0.04%) U 3 O 8 from 15.00m ,
      • including 1.00m @ 1,015.29 ppm (0.10%) U 3 O 8 from 28.00m
      • and 1.00m @ 2,128.46 ppm (0.21%) U 3 O 8 from 34.00m
    • HJ24DD019 – 6.00m @ 1,177.43 ppm (0.12%) U 3 O 8 from 87.00m ,
      • including 4.00m @ 1,520.58 ppm (0.15%) U 3 O 8 from 89.00m
  • Uranium mineralisation at Huarabagoo continues to deliver impressive results including:
    • HB24DD010 – 15.60m @ 2,237.03 ppm (0.22%) U 3 O 8 and 0.53 g/t Au from 68.40m ,
      • including 1.00m @ 2,264.06 ppm (0.23%) U 3 O 8 and 0.23 g/t Au from 70.00m
      • and 7.00m @ 4311.16 ppm (0.43%) U 3 O 8 and 0.10 g/t Au from 76.00m
      • with highest intercept result of 1.00m @ 1.42% U 3 O 8 and 0.01 g/t Au from 80.00m
  • Broad zones of gold mineralisation were also intercepted with grades up to 24.2g/t Au
    • HB24DD008 – 19.00m @ 620.58 ppm (0.06%) U 3 O 8 and 1.95 g/t Au from 48.00m ,
      • including 2.00m @ 1,720.45 ppm (0.17%) U 3 O 8 and 1.64 g/t Au from 57.00m
      • and 2.00m @ 2,202.16 ppm (0.22%) U 3 O 8 and 12.39 g/t Au from 64.00m
      • with highest intercept result of 1.00m @ 2,299.44 ppm (0.22%) U 3 O 8 and 24.20g/t Au from 65.00m
    • HB24DD006 – 8.00m @ 1,449.86 ppm (0.14%) U 3 O 8 & 0.22 g/t Au from 36.00m ,
      • including 1.70m @ 6,208.83 ppm (0.62%) U 3 O 8 & 0.78 g/t Au from 37.60m .
  • New Exploration Permit (EPM 28807) granted adjacent to Westmoreland Project adding 327km   2 of highly prospective tenure in NW Queensland

Laramide Resources Ltd. ( "Laramide" or the "Company" ) (TSX: LAM) (ASX: LAM) (OTCQX: LMRXF), a uranium mine development and exploration company with globally significant assets in the United States and Australia is pleased to announce another batch of assay results from the 2024 drilling campaign completed at the Westmoreland Uranium Project in Queensland, Australia ( "Westmoreland" ) and the receipt of a permit for exploration for a large land package immediately east of and adjacent to the current Westmoreland land tenure.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less