Mining Weekly reported Sylvania Platinum (ASX:SLP,LSE:SLP) said its Tweefontein project is on track for its float plant to be completed by the end of August.
Mining Weekly reported Sylvania Platinum (ASX:SLP,LSE:SLP) said its Tweefontein project is on track for its float plant to be completed by the end of August.
As quoted in the market news:
During the plant-planning period, a design option was considered, which would allow for the processing of the planned expanded production from the host mine. The original plant design of 20 000 t/m of run-of-mine feed was consequentially updated to 31 000 t/m and is now aligned with the host mine’s MG2 adit planned production volumes.
Click here to read the full Mining Weekly report.