Colossus Minerals Reports Development Update on Serra Pelada

Palladium Investing

Colossus Minerals Inc. (TSX:CSI,OTCQX:COLUF) reported a development update for its 75% owned Serra Pelada gold-platinum-palladium mine in Brazil. The project is a joint venture between Colossus and Cooperativa de Mineração dos Garimpeiros de Serra Pelada, and construction is currently 85% complete.

Colossus Minerals Inc. (TSX:CSI,OTCQX:COLUF) reported a development update for its 75% owned Serra Pelada gold-platinum-palladium mine in Brazil. The project is a joint venture between Colossus and Cooperativa de Mineração dos Garimpeiros de Serra Pelada, and construction is currently 85% complete.

As quoted in the press release:

HIGHLIGHTS

  • The Company remains on track for initial production in the third quarter of 2013 at a rate of 250 tonnes per day (“tpd”). Current planning indicates ramp-up to 1,000 tpd is achievable by the end of the first quarter of 2014. A photo update is included in this release.
  • The Company has substantially completed its bulk sample program. Additional development is ongoing in the Central Mineralized Zone (“CMZ”) for grade control purposes and to continue building a stockpile ahead of process plant commissioning. The Company currently has approximately 2,500 tonnes of material on the run of mine (“ROM”) pad including lower grade halo mineralization and CMZ material. Assays are pending and initial grade reconciliation ongoing.
  • The remainder of June and July will be focused on extending the excavation in the bulk sample access drift in order to build a 10,000 tonne surface stockpile ahead of mill commissioning in the third quarter. This stockpile will include bulk-sample material which will be segregated and processed separately for grade control testing. The Company also expects to begin development of a second access drift into the CMZ by the end of June.
  • Project construction is currently 85% complete. Structural steel erection is now 55% complete. The ball mill is in place and all three gravity concentrators have been installed. Commissioning will commence in July starting with the primary crusher and progressing through other individual operating areas of the process plant.
  • Other underground development remains on schedule and continues to average in excess of three metres per day. The drive towards the ventilation shaft remains on schedule.
  • Other infrastructure development remains on schedule.
    • Commissioning of the power house is complete and this facility is providing 100% of the Company’s power requirements.
    • The tailings dam is approximately 35% complete and is expected to be ready in conjunction with start of mill commissioning.
    • The ventilation shaft has been collared and expansion is well advanced. The upgraded ventilation facility will be completed by the end of the third quarter.

Colossus Minerals Inc. Chief Executive Officer, Claudio Mancuso, said:

We continue to remain focused on development and beginning production in the third quarter of 2013. We have achieved a number of significant milestones in the past month such as substantially completing our bulk sample program, commissioning our power house, collaring the ventilation shaft and raising additional capital to provide flexibility during ramp-up. We are pleased with our development progress and look forward to pouring gold in the third quarter of this year.

Click here to read the Colossus Minerals Inc. (TSX:CSI,OTCQX:COLUF) press release

See this press release on Marketwire
Click here to see the Colossus Minerals Inc. (TSX:CSI,OTCQX:COLUF) profile

The Conversation (0)
×