- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
Detour Gold (TSX:DGC) reported on the construction progress of its Detour Lake open-pit gold mine in northeastern Ontario, Canada.
Detour Gold (TSX:DGC) reported on the construction progress of its Detour Lake open-pit gold mine in northeastern Ontario, Canada. The project remains on budget and on schedule for gold production to start in the first quarter of 2013.
As quoted in the press release:
The following project milestones have recently been achieved:
- Project construction reached 75% completion mark on June 30
- 230 kV transmission line connected to grid on July 19
- Pre-stripping reaches 10 million tonnes mined
- Process plant mechanical contract at 60% completion
- New peak in construction activities with 1,550 workers at site
- Now over 279 Detour Gold employees at site and Cochrane office
Gerald Panneton, President and CEO of Detour Gold commented:
“We have achieved another significant milestone with the successful connection of the 230 kV transmission line, which will allow for the full commissioning of the grinding mills to start as planned before year-end. We are pleased with the performance of our contractors in achieving the 75% completion mark at the end of June. Our site and Cochrane team of 279 employees are actively preparing for the commencement of operations. The Company remains on budget with sufficient cash to complete the project construction and on schedule for gold production to commence in the first quarter of 2013.”
Click here to read the full press release