Highbank Resources 2 Weeks Ahead of Schedule at Swamp Point North

Company News

Highbank Resources Ltd. (TSXV:HBK) reported that over half of the pilings needed for its load-out facility at Swamp Point North have now been installed. This places the company roughly two weeks ahead of schedule.

Highbank Resources Ltd. (TSXV:HBK) reported that over half of the pilings needed for its load-out facility at Swamp Point North have now been installed. This places the company roughly two weeks ahead of schedule.

As quoted in the press release:

Improvement to the site and camp continue. Telephone and internet communications have been established. A camp perimeter electrified bear fence as per site requirements has been installed. Road access development and overburden stripping is proceeding satisfactorily. The region has experienced record rainfall affording on-site environmental personnel to precisely implement the requirements for compliance with water management and other regulations. Despite the extremely high rainfall in the area, development continues well on track.

Click here to read the Highbank Resources Ltd. (TSXV:HBK) press release

See this press release on Marketwire
Click here to see the Highbank Resources Ltd. (TSXV:HBK) profile.

The Conversation (0)
×