Stornoway Diamond Corporation (TSX:SWY) announced it has started the principal concrete pour at the Renard Diamond Project process plant.

Stornoway Diamond Corporation (TSX:SWY) announced it has started the principal concrete pour at the Renard Diamond Project process plant.

As quoted in the press release,

Specialized concrete work for the plant’s foundations is expected to continue through the spring and early summer before the erection of structural steel begins in June. The plant building is scheduled to be completed and heated by the fourth quarter of this year, allowing the installation of the temperature sensitive crushing and recovery circuits through the first half of 2016. The plant is scheduled to be energized in the second half of 2016 with wet commissioning beginning in the fourth quarter of that year.

Click here for the full Stornoway Diamond Corporation (TSX:SWY) press release

 