Paladin Energy Ltd. (TSE:PDN, ASX:PDN) reports the completion test will begin 1 November 2010, in accordance with the Kayelekera Mine project finance loan.
Paladin Energy Ltd. (TSX:PDN, ASX:PDN) reports the completion test will begin 1 November 2010, in accordance with the Kayelekera Mine project finance loan.
The press release is quoted as saying:
The Completion Test requires the Project to operate at a minimum of 90% design production for a continuous period of 90 days. It will include a number of specific performance parameters, including tests for mining, recovery, production, grade and milling.