- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
China's General Nuclear Connects Third Yangjiang Unit to Electrical Grid
World Nuclear News reported that China General Nuclear’s (CGN’s) Yangjiang plant has connected Unit 3 to the electricity grid and the reactor is expected to begin commercial operation by the end of 2015.
World Nuclear News reported that China General Nuclear’s (CGN’s) Yangjiang plant has connected Unit 3 to the electricity grid and the reactor is expected to begin commercial operation by the end of 2015.
As quoted in the market news:
Plant constructor China Nuclear Industry 23 Construction Company Limited announced today that the unit was connected to the grid at 3.00pm on 18 October. Grid connection marks “formal entry into the commercial operation preparation phase”, the company said.
A series of tests will now be conducted at Yangjiang 3 before it enters commercial operation later this year.
Construction of the unit began in November 2010. The loading of fuel assemblies into the reactor’s core was completed on 11 September this year, with the unit achieving first criticality on 11 October.
Six units are planned for the Yangjiang site by CGN. The first two units are 1021 MWe (net) CPR-1000 pressurized water reactors, with units 3 and 4 being 1089 MWe CPR-1000+ units, and units 5 and 6 being 1080 MWe ACPR-1000s. Unit 1 entered commercial operation in March, while unit 2 began commercial operation in June. Unit 4 – construction of which began in late 2012 – is scheduled to start up in 2017.