- WORLD EDITIONAustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
Nevsun Resources (TSX:NSU) reported that its Bisha mine will shut for two weeks due to a mechanical issue with its ball mill. A cracked output shaft bearing was discovered during routine inspection for the mill, which has led to the company’s decision to accelerate gearbox maintenance that was scheduled for April.
Nevsun Resources (TSX:NSU) reported that its Bisha mine will shut for two weeks due to a mechanical issue with its ball mill. A cracked output shaft bearing was discovered during routine inspection for the mill, which has led to the company’s decision to accelerate gearbox maintenance that was scheduled for April.
The company also reported that its zinc expansion project remains on track.
As quoted in the press release:
The Company believes this temporary shutdown will not negatively impact its 2015 annual production guidance but may take approximately two weeks to resolve. During this temporary shutdown, the mine plans to catch up on waste mining and accelerate other preventative maintenance that was scheduled for later in 2015.
While conducting a planned routine ball mill inspection, it was decided to accelerate gearbox maintenance for the mill, initially scheduled for April, upon observing a cracked output shaft bearing. The spare output shaft bearings were already onsite as critical spares however key tools and ancillary equipment are currently being expedited to site to complete the work already commenced with supplier Thyssen Polysius over the coming week. Despite the estimated two week unplanned shutdown for this repair, this will save some time for the planned ball mill reline scheduled in Q2 2015. During this temporary shutdown, the mine plans to catch up on waste mining and accelerate other preventative maintenance that was scheduled for later in 2015.
The Company will provide an update on when the plant is back online.