King Island Scheelite Provides Tungsten Project Update
During 2018, King Island’s primary focus at the Dolphin project was the construction of a new processing plant.

Critical metals developer King Island Scheelite (ASX:KIS) released an update for its ongoing redevelopment efforts at the solely-owned Dolphin tungsten project on King Island, Tasmania.
During 2018, King Island’s primary focus for the Dolphin project was the construction of a new processing plant designed to treat ore produced from the Dolphin mine.
Production ceased at the Dolphin mine in 1992 due to depressed tungsten prices. King Island is currently implementing its redevelopment strategy for the mine amid steady, yet restrained tungsten prices.
One of the key components to the redevelopment of the site was design and cost analysis of the proposed processing plant. King Island looked to Gekko Systems to design the facility.
Gekko was tasked with designing a plant capable of treating the ore from the Dolphin mine, based on metallurgical test work completed at the ALS laboratory in Tasmania.
The proposal from the plant design company was completed in mid-December.
“A modular design was preferred as this will minimize construction and commissioning times on site and result in reduced costs,” Johann Jacobs, King Island chairman said in the announcement.
“Capital and operating costs are significantly lower than those determined in previous feasibility studies, due largely to the re-design of the flow sheet.”
Using the proposed modular design, it is estimated that procurement, construction and commissioning could be feasible within a twelve-month period.
The relocation of the processing plant from its previous position is also part of the larger redevelopment.
In order to move the plant from the eastern side of the pit to the western, the company sought approval from the King Island Council. After consulting with the Tasmanian Environmental Protection, the King Island Council granted the planning permit approval.
“The new site has significant operational advantages over the previous site, in terms of reduced environmental impact (noise and visual), vehicle accessibility, proximity to the Grassy Port, reduced civil work costs and a much safer environment for light vehicles,” added Jacobs.
A detailed mine plan and schedule for the Dolphin project allows for eight years of open cut mining at an average rate of 400,000 tonnes per year of ore.
Shares of King Island were up 6 percent on Monday (January 21), trading at AU$0.08.
Don’t forget to follow us @INN_Resource for real-time updates!
Securities Disclosure: I, Georgia Williams, hold no direct investment interest in any company mentioned in this article.