- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
Sandstorm Gold (NYSE:SAND; TSX:SSL) has provided an update at a variety of its projects underlying its streams and royalties. As quoted in the press release: The Cerro Moro project is a high grade gold and silver deposit in the Santa Cruz province of Argentina, currently in the development stage with first production planned for 2018. …
Sandstorm Gold (NYSE:SAND; TSX:SSL) has provided an update at a variety of its projects underlying its streams and royalties.
As quoted in the press release:
The Cerro Moro project is a high grade gold and silver deposit in the Santa Cruz province of Argentina, currently in the development stage with first production planned for 2018. Yamana Gold Inc. (“Yamana”) has been carrying out a 2016 work program at Cerro Moro including the ramp-up of site construction activities, the continuation of detailed engineering, as well as the advancement of underground mining in order to gain a better understanding of in-situ mining conditions. Yamana’s planned expenditures for 2016 are expected to be approximately US$53 million, leaving US$224 million in total for 2017 and 2018, with the majority of the capital being spent in 2017. This development approach allows for further exploration drilling in order to increase the size of the Cerro Moro mineral resources, and to improve the current mineral resource categorization. The 2016 exploration program at Cerro Moro is expected to complete a total of approximately 16,000 metres of drilling and is focused on discovering a new high grade structure and expanding the current Indicated mineral resources.
Development progress at Cerro Moro is outlined below:
- 325 metres of underground development (of the 617 metres planned for 2016) were completed as of the end of the second quarter 2016;
- the ramp-up of site construction is continuing with bulk earthworks completed during Q2 2016 and the concrete contractor having mobilized to site;
- detailed engineering is 73% complete and is advancing to a planned 85% completion by the end of the 2016 year; and
- procurement progress is tracking well, the upgrade of an existing mine truck facility is advanced, and the phase 2 construction camp installation as well as the tailings dam design have concluded.