- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
Robex Resources' Nampala Mine Generates Positive Net Cash Flows
Robex Resources Inc. (TSXV:RBX,FWB:RB4) is pleased to announce that preproduction at the Nampala mine, is currently in a period of increasing production rates (ramp-up), now allows the Nampala mine to generate positive cash flow for the first time in its history. Currently, the production level is around 3,000 tonnes per day (tpd) and is very …
Since mid-July 2016, the ball mill has started and the mine is in a commissioning period in order to gradually bring production to the final target of 4,000 tpd at the beginning of 2017. In early August, the last two additional CIL tanks were also added to the circuit to bring the total to six tanks.
The table below summarizes the daily tonnage averaged per week since the start of the 750 kW ball mill. This illustrates the steady increase of the preproduction at the mine.
Average daily tonnage : https://media3.marketwire.com/docs/1069781e.jpg
Click this link if you do not see the table: Average daily tonnage.
Period | Total tonnage for the period | Average daily tonnage |
July 12 to 18 | 11,225 | 1,604 |
July 19 to 25 | 11,888 | 1,698 |
July 26 to August 1 | 13,635 | 1,948 |
August 2 to 8 | 17,540 | 2,506 |
August 9 to 15 | 18,684 | 2,669 |
August 16 to 22 | 18,452 | 2,636 |
August 23 to 29 * | 6,818 | 2,727 |
August 30 to September 5 | 21,798 | 3,114 |
September 6 to 12 ** | 20,058 | 2,865 |
August 31 to September 12 | 39,002 | 3,000 |
* The mine came to a complete stop for four and a half days during the week of August 23, 2016 to perform a correction on the alignment of the drive system of the ball mill.
** The mine went through a planned shutdown for a half-day for maintenance during the week of September 6, 2016. Without this shutdown, the period would have had a daily average tonnage of 3,086 tonnes.
The equipment availability is at this stage particularly satisfactory in the commissioning, it has reached an availability rate of 88% since the beginning of September. The recovery, as well, with a rate of 81% in August and 84% in September was satisfactory in regards to the target rate of 86%.
The tonnage is currently limited by several factors. A first factor is the hard laterite ore that was strongly present at the start of operations at the mine. This ore is expected to be exhausted or in low proportion by the end of 2016. Of course, as in any ramp-up, different points of varying complexities arise and are solved one by one, for example: the tank overflow, the water availability, moving trucks during the rainy season, the deficient pumping, etc.
Even if the plant is currently operational, there are still certain elements to improve. The gravimetrical sectors, reagents and coal processing are not yet operational. Completing these elements in the coming months will increase productivity and optimize recovery. Moreover, the company plans to soon install a complete fire assay laboratory on site.
Mr. Georges Cohen, president and CEO of the company said: “Although the construction of the mine has taken longer than expected, I am very excited at this stage, reaching in September the production target of close to 3,000 tonnes per day that we had set for 2016. This demonstrates without a doubt that the Nampala mine has all the expertise required to rapidly bring the production to 4,000 tonnes per day.”
Data were validated by Antoine Berton Eng, Ph.D., Soutex metallurgist, a metallurgical consulting firm and who treat the ore on site.
Several pictures and videos of the Nampala mine were recently added to the company’s website. Visit Robexgold.com to view them, or click directly on one of these links: Pictures and Videos.
Nomination of Simon Boudreau
The Company recently carried out the re-employment of Mr. Simon Boudreau, engineer, as director of operations at the Nampala mine. Mr. Boudreau had held the position of Director of Nampala mine in 2014. He worked as an independent consultant in mining engineering; he was project manager at Dumas Contracting Ltd. from 2010 to 2012, and Chief Engineer at High River Gold from 2006 to 2010. Mr. Boudreau is a graduate from University Laval in mining engineering and mineral processing (2003) and is a member of the Ordre des ingénieurs du Québec.
This press release contains statements that may constitute “forward-looking information” or “forward-looking statements” as set out within the context of security law. This forward-looking information is subject to many risks and uncertainties, some of which are beyond Robex’s control. The actual results or conclusions may differ considerably from those that have been set out, or intimated, in this forward-looking information. There are many factors which may cause such disparity, especially the instability of metal market prices, the results of fluctuations in foreign currency exchange rates or in interest rates, poorly estimated reserves, environmental risks (stricter regulations), unforeseen geological situations, unfavourable extraction conditions, political risks brought on by mining in developing countries, regulatory and governmental policy changes (laws and policies), failure to obtain the requisite permits and approvals from government bodies, or any other risk relating to mining and development. There is no guarantee that the circumstances anticipated in this forward-looking information will occur, or if they do occur, how they will benefit Robex. The forward-looking information is based on the estimates and opinions of Robex’s management at the time of the publication of the information and Robex does not assume any obligation to make public updates or modifications to any of the forward-looking statements, whether as a result of new information, future events, or any other cause, except if it is required by securities laws.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Augustin Rousselet, CFO
(581) 741-7421
info@robexgold.com
Latest News
Investing News Network websites or approved third-party tools use cookies. Please refer to the cookie policy for collected data, privacy and GDPR compliance. By continuing to browse the site, you agree to our use of cookies.