GoviEx Files Updated Pre-Feasibility Study for the Madaouela Project

Start-Up Capital and Operating Costs Reduced

GoviEx Uranium Inc. (TSXV: GXU) (OTCQB: GVXXF) ("GoviEx or the Company") is pleased to announce that a technical report titled, "An Updated Pre-Feasibility Study for the Madaouela Project, Niger" dated effective April 5, 2021 (the "Report"), which supports the disclosure in the Company's news release dated February 18, 2021, has been filed today under the Company's profile on SEDAR.

Key Highlights of the Report, as previously described in the February 18, 2021, news release:

  • Open pit mining in the early years with CapEx reduced by 15% and OpEx down by 20%
  • Captive water source, consumption reduced by 66%
  • Grid level electrical power existing within Madaouela Project boundary
  • Prioritize local skilled labour and local venders
  • Straightforward industry standard process design - reducing construction and operational risks
  • Mining Permit and Environmental Certificate already secured
  • Potential to service debt of USD 150-180 million
  • Ability to fast track feasibility study in 2021 to target rapid development
  • Next steps to accelerate project financing and offtake options

The Report was prepared by SRK Consulting (UK) Limited ("SRK") in accordance with Canadian National Instrument 43-101 Standards of Disclosure for Mineral Projects, and is available on the Company's website (www.goviex.com) and under the Company's profile on SEDAR (www.sedar.com).

Qualified Persons

The qualified persons from SRK for the Report are:

  • Eur.Geol. Robert John Bowell, PhD C.Chem. C.Geol - Corporate Consultant (Geochemistry & Processing)
  • Daniel Rene Guibal, Min Eng, FAusIMM (CP), MMICA, MGAA - Corporate Consultant (Geostatistics & Resources)
  • Timothy John McGurk B.Eng (Hons), C.Eng, MIMMM - Corporate Consultant (Mining Engineering)
  • Filip Orzechowski (MSc FIMMM CEng) - Principal Consultant (Mining)
  • Jurgen Fuykschot (MSc MBA, MAusIMM) - Principal Consultant (Mining Engineering)

The scientific and technical information in this release has been reviewed and approved by Dr. Rob Bowell, a chartered chemist of the Royal Society of Chemistry, a chartered geologist of the Geological Society of London, and a Fellow of the Institute of Mining, Metallurgy and Materials, who is an independent Qualified Person under the terms of NI 43-101 for uranium deposits. Mr. Bowell has verified the data disclosed in this news release.

Neither the TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

About GoviEx Uranium

GoviEx is a mineral resource company focused on the exploration and development of uranium properties in Africa. GoviEx's principal objective is to become a significant uranium producer through the continued exploration and development of its flagship mine-permitted Madaouela Project in Niger, its mine-permitted Mutanga Project in Zambia, and its multi-element Falea Project in Mali.

Contact Information

Govind Friedland, Executive Chairman
Daniel Major, Chief Executive Officer
Tel: +1-604-681-5529
Email: info@goviex.com
Web: www.goviex.com

Cautionary Statement Regarding Forward-Looking Statements

This news release may contain forward-looking information within the meaning of applicable securities laws. All information and statements other than statements of current or historical facts contained in this news release are forward-looking information.

Forward-looking statements are subject to various risks and uncertainties concerning the specific factors disclosed here and elsewhere in GoviEx's periodic filings with Canadian securities regulators. When used in this news release, words such as "will", "could", "plan", "estimate", "expect", "intend", "may", "potential", "should," and similar expressions, are forward- looking statements. Information provided in this document is necessarily summarized and may not contain all available material information.

Forward-looking statements include those in relation to, (i) the Company's ability to fast-track a feasibility study on the Madaouela Project in 2021; (ii) the method and timing of any development and mining operations at the Madaouela Project; (iii) the potentially to bring the Madaouela Project online within the economic parameters and development and mining processes set out in the Report; (iv) that the open pit alone has the potential to service debt of USD 150-180 million at a U3O8 price of USD 50-55 per pound and (v) accelerating financing and offtake options as next steps from the publication of the Report.

Although the Company believes the expectations reflected in such forward-looking statements are based on reasonable assumptions, it can give no assurances that its expectations will be achieved. Such assumptions, which may prove incorrect, include the following: (i) that the Report will advance the Madaouela Project towards project financing and development; (ii) that the current uranium upcycle will continue and expand; (iii) that the integration of nuclear power into power grids world-wide will continue as a clean energy alternative; and (iv) that the price of uranium will remain sufficiently high and the costs of advancing the Company's mining projects will remain sufficiently low so as to permit GoviEx to implement its business plans in a profitable manner.

Factors that could cause actual results to differ materially from expectations include (i) that the market will not respond as anticipated to the Report; (ii) a regression in the uranium market price; (iii) inability or unwillingness of include or increase nuclear power generation by major markets; (iv) potential delays due to COVID-19 restrictions; (v) the failure of the Company's projects, for technical, logistical, labour-relations, or other reasons; (vi) a decrease in the price of uranium below what is necessary to sustain the Company's operations; (vii) an increase in the Company's operating costs above what is necessary to sustain its operations; (viii) accidents, labour disputes, or the materialization of similar risks; (ix) a deterioration in capital market conditions that prevents the Company from raising the funds it requires on a timely basis; and (x) generally, the Company's inability to develop and implement a successful business plan for any reason.

In addition, the factors described or referred to in the section entitled "Financial Risks and Management Objectives" in the MD&A for the year ended December 31, 2019, of GoviEx, which is available on the SEDAR website at www.sedar.com, should be reviewed in conjunction with the information found in this news release.

Although GoviEx has attempted to identify important factors that could cause actual results, performance, or achievements to differ materially from those contained in the forward- looking statements, there can be other factors that cause results, performance, or achievements not to be as anticipated, estimated, or intended. There can be no assurance that such information will prove to be accurate or that management's expectations or estimates of future developments, circumstances, or results will materialize. As a result of these risks and uncertainties, no assurance can be given that any events anticipated by the forward-looking information in this news release will transpire or occur, or, if any of them do so, what benefits that GoviEx will derive therefrom. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements in this news release are made as of the date of this news release, and GoviEx disclaims any intention or obligation to update or revise such information, except as required by applicable law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/79384

News Provided by Newsfile via QuoteMedia

The Conversation (0)
GoviEx Uranium Inc.

GoviEx Uranium Inc.

GoviEx Uranium Inc is a Canada-based company involved in the industrial metals and mining business sector. It is focused on the evaluation and development of uranium properties located in the Republic of Niger. The asset portfolio of the company includes uranium development projects, including the Madaouela project in Niger, Mutanga project in Zambia, and Falea in Mali.

C29 Metals

Clarification Announcement

C29 Metals Limited (ASX:C29) (C29, or the Company) released an announcement to ASX on 24 July 2024 titled “License Applications Lodged around Ulytau Uranium Project” (Announcement). Following discussions with the ASX, the Company retracts the information in respect of the foreign estimates and foreign exploration results included in the Announcement.

Keep reading...Show less

Ur-Energy Inc. Announces Proposed Public Offering of Common Shares

Ur-Energy Inc. (NYSE American:URG)(TSX:URE) ("Ur‑Energy") announced today that it intends to offer and sell its common shares in an underwritten public offering. In connection with this offering, Ur-Energy expects to grant the underwriters a 30-day option to purchase additional common shares, equal to up to 15% of the number of securities sold in the offering. The offering is subject to market conditions, and there can be no assurance as to whether or when the offering may be completed, or as to the actual size or terms of the offering. All of the securities in the offering are to be sold by Ur-Energy

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Gladiator Resources Limited

4th Quarter Activities and Appendix 5B

Gladiator Resources Ltd (ASX: GLA) (Gladiator or the Company) is pleased to provide shareholders with the Company’s Activities and Appendix 5B Cashflow Report for the quarter ending 30 June 2024.

Keep reading...Show less

Global Atomic Announces Private Placement upsized to C$20 Million

NOT FOR DISTRIBUTION TO UNITED STATES NEWS WIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES

Global Atomic Corporation (" Global Atomic " or the " Company ") (TSX: GLO, OTCQX: GLATF, FRANKFURT: G12) is pleased to announce that due to significant investor demand, the Company has increased the maximum gross proceeds of its previously announced non-brokered private placement (the " Offering ") from C$15,000,000 to C$20,000,000. Under the revised Offering, the Company will sell 14,814,815 units of the Company (each, a " Unit ") at a price of C$1.35 per Unit. Red Cloud Securities Inc. is acting as a finder in connection with the Offering.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
GTI Energy

Rights Entitlement Offers Underwritten to $1.6M

GTI Energy Ltd (GTI or Company) is pleased to advise that existing shareholders will be offered the opportunity to participate in a non-renounceable pro-rata rights entitlement offer of one (1) new share for every five (5) existing Shares, held by those Shareholders registered at the relevant record date, at an issue price of $0.0045 per New Share to raise up to $2,294,952 (before costs), together with one (1) free attaching new option for every three (3) New Shares subscribed for and issued (Entitlement Issue Offer). Each new option will have an exercise price of $0.01 and entitle the holder to subscribe for one (1) new share before their expiry at 5:00 pm (WST), four (4) years from their date of issue (New Option).
Keep reading...Show less
GTI Energy

Entitlement Issue Prospectus

GTI Energy Ltd (GTI or Company) is pleased to share its Entitlement Offer Prospectus.
Keep reading...Show less

Latest Press Releases

Related News

×