Ero Copper Reports Temporary Power Disruption at the Tucumã Operation Following Severe Windstorm

Ero Copper Corp. (TSX: ERO, NYSE: ERO) ("Ero" or the "Company") announces that its Tucumã Operation has experienced a temporary power disruption following a severe localized windstorm that occurred in the southwest region of the Carajás Mineral Province in Pará State, Brazil on October 5, 2024. The Company's workforce is safe, and there has been no damage to infrastructure at the Tucumã Operation.

The regional power grid, including the main 230kV transmission line servicing the region, sustained damage during the storm, resulting in a loss of power to more than 200,000 residents as well as major industrial users. Power has since been fully restored to residential communities and partially restored to industrial consumers. The owner and operator of the transmission line has advised that full power restoration to industrial consumers, including the Company's Tucumã Operation, is expected within two weeks.

The power disruption at Tucumã has impacted the milling, flotation and filtration circuits within the processing plant. Mining and crushing operations remain unaffected, with ore continuing to be placed on the run-of-mine and crushed ore stockpiles. The Company expects the primary impact will be on the ramp-up schedule of the processing plant, and in turn, full-year production results at the Tucumã Operation. While the extent of the impact will depend on the timing of full power restoration, Ero Copper remains well-positioned to manage this temporary disruption and will provide further updates as the situation develops.

ABOUT ERO COPPER CORP
Ero is a high-margin, high-growth, low carbon-intensity copper producer with operations in Brazil and corporate headquarters in Vancouver, B.C. The Company's primary asset is a 99.6% interest in the Brazilian copper mining company, Mineração Caraíba S.A. ("MCSA"), 100% owner of the Company's Caraíba Operations (formerly known as the MCSA Mining Complex), which are located in the Curaçá Valley, Bahia State, Brazil and include the Pilar and Vermelhos underground mines and the Surubim open pit mine, and the Tucumã Operation (formerly known as Boa Esperança), an open pit copper mine located in Pará, Brazil. The Company also owns 97.6% of NX Gold S.A. ("NX Gold") which owns the Xavantina Operations (formerly known as the NX Gold Mine), comprised of an operating gold and silver mine located in Mato Grosso, Brazil. Additional information on the Company and its operations, including technical reports on the Caraíba Operations, Xavantina Operations and Tucumã Operation, can be found on SEDAR+ ( www.sedarplus.ca/landingpage/) and on EDGAR ( www.sec.gov). The Company's shares are publicly traded on the Toronto Stock Exchange and the New York Stock Exchange under the symbol "ERO".

FOR MORE INFORMATION, PLEASE CONTACT
Courtney Lynn, SVP, Corporate Development, Investor Relations & Sustainability (604) 335-7504
info@erocopper.com

CAUTION REGARDING FORWARD LOOKING INFORMATION AND STATEMENTS

This press release contains "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable Canadian securities legislation (collectively, "forward-looking statements"). Forward-looking statements include statements that use forward-looking terminology such as "may", "could", "would", "will", "should", "intend", "target", "plan", "expect", "budget", "estimate", "forecast", "schedule", "anticipate", "believe", "continue", "potential", "view" or the negative or grammatical variation thereof or other variations thereof or comparable terminology. Forward-looking statements may include, but are not limited to, statements with respect to the expected restoration of power and the restart of the processing plant at the Tucumã Operation; the Company's ability to manage the impact of the power disruption to the commissioning timeline at the Tucumã Operation and to its full-year production results; and any other statement that may predict, forecast, indicate or imply future plans, intentions, levels of activity, results, performance or achievements.

Forward-looking statements are not a guarantee of future performance. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements involve statements about the future and are inherently uncertain, and the Company's actual results, achievements or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties and other factors, including, without limitation, those referred to herein and in the Company's most recent Annual Information Form under the heading "Risk Factors".

The Company's forward-looking statements are based on the assumptions, beliefs, expectations and opinions of management on the date the statements are made, many of which may be difficult to predict and beyond the Company's control. In connection with the forward-looking statements contained in this press release and in the AIF, the Company has made certain assumptions about, among other things: continued effectiveness of the measures taken by the Company to mitigate the possible impact of COVID-19 on its workforce and operations; favourable equity and debt capital markets; the ability to raise any necessary additional capital on reasonable terms to advance the production, development and exploration of the Company's properties and assets; future prices of copper, gold and other metal prices; the timing and results of exploration and drilling programs; the accuracy of any mineral reserve and mineral resource estimates; the geology of the Caraíba Operations, the Xavantina Operations and the Tucumã Project being as described in the respective technical report for each property; production costs; the accuracy of budgeted exploration, development and construction costs and expenditures; the price of other commodities such as fuel; future currency exchange rates and interest rates; operating conditions being favourable such that the Company is able to operate in a safe, efficient and effective manner; work force continuing to remain healthy in the face of prevailing epidemics, pandemics or other health risks (including COVID-19), political and regulatory stability; the receipt of governmental, regulatory and third party approvals, licenses and permits on favourable terms; obtaining required renewals for existing approvals, licenses and permits on favourable terms; requirements under applicable laws; sustained labour stability; stability in financial and capital goods markets; availability of equipment; positive relations with local groups and the Company's ability to meet its obligations under its agreements with such groups; and satisfying the terms and conditions of the Company's current loan arrangements. Although the Company believes that the assumptions inherent in forward-looking statements are reasonable as of the date of this press release, these assumptions are subject to significant business, social, economic, political, regulatory, competitive and other risks and uncertainties, contingencies and other factors that could cause actual actions, events, conditions, results, performance or achievements to be materially different from those projected in the forward-looking statements. The Company cautions that the foregoing list of assumptions is not exhaustive. Other events or circumstances could cause actual results to differ materially from those estimated or projected and expressed in, or implied by, the forward-looking statements contained in this press release. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

Forward-looking statements contained herein are made as of the date of this press release and the Company disclaims any obligation to update or revise any forward-looking statement, whether as a result of new information, future events or results or otherwise, except as and to the extent required by applicable securities laws.


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

ERO:CA
The Conversation (0)
Many copper bobbins and warehouse copper pipes.

Top 10 Copper-producing Companies

Copper miners with productive assets have much to gain as supply and demand tighten.

In May 2024, the copper price hit a new all-time high of US$10,954 per metric ton (MT) on the London Metal Exchange and US$5.20 per pound on the COMEX on the back of increasing demand and growing supply concerns.

Copper is one of the most important resources for the energy transition. However, in recent years, demand for the red metal has outpaced mining supply. While construction and electrical grids have long been major markets for copper, today the rise in demand for electric vehicles, EV charging infrastructure and energy storage applications are emerging drivers of copper consumption.

Another trend driving future copper demand is the rapid urbanization in the Global South, as rural populations migrate to cities, putting pressure on electricity grids.

Keep reading...Show less
White Cliff Minerals

John Hancock to join White Cliff Minerals Board

Astrotricha Capital SEZC appointed Advisors

White Cliff Minerals Limited (“WCN” or the “Company”) (ASX: WCN; OTCQB: WCMLF) is pleased to announce that John Hancock will join the Board of White Cliff Minerals effective 1 August 2025.

Keep reading...Show less
Gavel on books with "5 Top Canadian Mining Stocks This Week" text overlay.

Top 5 Canadian Mining Stocks This Week: Royalties Inc. Jumps 183 Percent on Legal Win

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX, TSXV and CSE, starting with a round-up of Canadian and US news impacting the resource sector.

Friday (June 20) was the last day for the spring session of Canada’s parliament before its summer break.

On the agenda for the day was a vote on bill C-5, “The One Canadian Economy Act,” which was introduced on June 5.

Keep reading...Show less
Cyprium Metals

Nifty Copper Project Virtual Site Visit

Cyprium Metals Limited (ASX: CYM, OTC: CYPMF) (Cyprium or the Company) invites shareholders to join an investor webinar and live Q&A hosted by Executive Chairman Matt Fifield on Tuesday 24th June 2025. Investors will be guided on a virtual site visit of the Nifty Copper Complex showcasing the sulphide and heap leach resources and extensive brownfield infrastructure.

Keep reading...Show less
Mining Execs Call for Clarity as Canada Eyes Faster Permitting Timelines for Critical Minerals Projects

Mining Execs Call for Clarity as Canada Eyes Faster Permitting Timelines for Critical Minerals Projects

Faster permitting timelines for critical minerals projects could be a welcome game changer for junior mining and resource development companies, but clarity will be key to any meaningful reforms.

This was the sentiment among executives from junior mining companies in a recent panel discussion on Bill C-5, the Canadian government’s new major projects bill that will essentially fast track permitting for “national-interest” projects, including those essential to the country's critical minerals strategy.

The bill proposes the establishment of a Major Projects Office meant to be the single permitting agency for qualified projects that will cut permitting timelines from the typical five years down to two years.

Keep reading...Show less
Sun Summit Commences 2025 Exploration Program at the JD Project, Toodoggone District, British Columbia

Sun Summit Commences 2025 Exploration Program at the JD Project, Toodoggone District, British Columbia

Sun Summit Minerals Corp. (TSXV: SMN) (OTCQB: SMREF) ("Sun Summit" or the "Company") is pleased to announce the commencement of its $6 million 2025 project-wide exploration program at the JD Project, Toodoggone Mining District, north-central British Columbia. Over 5,000 meters of drilling together with geophysical and geochemical surveys are designed to focus on target advancement, target generation and discovery.

Highlights and Next Steps:

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×