Horizonte Minerals PLC - Araguaia Nickel Project Construction on Schedule

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 which is part of UK law by virtue of the European Union (Withdrawal) Act 2018 ("MAR").

Horizonte Minerals Plc (AIM:HZM)(TSX:HZM) a nickel company developing two Tier 1 assets in Brazil, is pleased to provide a progress update for its flagship 100% owned Araguaia Nickel Project ("Araguaia" or the "Project

Summary of Progress at Araguaia

  • Construction is progressing to schedule with overall project progress of approximately 16% as at 30 September 2022 and Engineering approximately 71%
  • US$375m of capital commitments on budget as of the end of August 2022
  • No lost time injuries recorded to date, with over 375,000 hours worked.
  • Project remains on schedule to deliver first nickel in Q1 2024
  • Inflationary pressure combined with engineering improvements to de-risk the operation have resulted in a 12.6% cost increase with total project capex now forecast at U$537million

Horizonte's CEO, Jeremy Martin said, "We are pleased with the progress that has already been made at Araguaia, with the Project remaining on schedule to produce first nickel in Q1 2024. There has been substantial progress in the four months since we mobilised to site and broke ground in May with the foundations of the furnace and rotary kiln well advanced and earthworks close to complete.

The project team is focussed on ensuring that the site is prepared ahead of the upcoming wet season. Site drainage is well advanced, access roads and bridges are being upgraded to the standard required for year-round operation and the mains power to site is close to being energised. This work is all designed to ensure we are able to maintain a safe working environment, while sustaining the high productivity levels seen to date and going forward.

We have updated our forecast operating costs and are pleased to report that we believe Araguaia is and will remain in the lowest cost quartile versus a peer group who, over the last 24 months, have seen significant operational cost increases. By using the low-cost hydroelectric power available to Araguaia, we will ensure that our high grade FeNi product will be a new leading low carbon emissions product in the market.

I am also pleased to announce that we will be advancing the engineering work of the 2nd Line at Araguaia with the objective of producing an AACE class 3 capital cost estimate and advancing the design to basic engineering. As part of this work, we will look at the option of adding a nickel matte converter into the plant flowsheet providing the optionality to convert a portion of the FeNi output to nickel matte, a product that has the potential to be sold directly into the battery metal supply chain. The overall objective of this engineering work is to potentially fast-track Araguaia towards a ~29,000 tpa nickel producer.

Unfortunately we are not immune to global inflationary pressures and this along with engineering improvements designed to de-risk the operation have led to an increase in our forecast capital expenditures. However, through our rigorous focus on cost discipline we expect to be able to limit the increase to 12.6% which is broadly in line with the peak of the Brazilian inflation cycle earlier this year and we are now taking proactive steps to ensure that we have adequate access to capital through both equity and to enable first utilisation under the senior debt facilities, targeted for Q4 2022.

Nickel, a critical metal in the clean energy transition, is showing significant future demand growth and we hope to remain well positioned to deliver our product into a robust market. We look forward to announcing further updates on our development milestones as we advance Araguaia towards production and Vermelho through Feasibility, ultimately transitioning Horizonte into a large-scale Tier 1 nickel producer."

Detailed Information

Following the ground breaking at Araguaia in May 2022, good progress has been achieved, with overall project progress of approximately 16% as at 30 September 2022, and site construction activities moving forward in accordance with the planned construction schedule.

Early works including the municipal and state road improvements are nearing completion ahead of the wet season, ensuring safe and secure access to the site from the nearby township of approximately 46,000 people of Conceição do Araguaia. The 13.8 kV local power line to support site construction is being installed and planned to be energised in October. Companhia Paranaense de Construção S.A. ("Copa") were awarded the Earthworks and Civil engineering contract, currently approximately 41% and 4% advanced respectively, with work focused on the furnace and rotary kiln foundations. The bulk earthworks scope covering all key plant platforms is completed to the stage where concrete foundations are being installed, with initial focus on the crusher retaining wall and foundation, and the furnace foundation. Further, 45 piles have been installed for the kiln foundations to date and work has begun on the water storage reservoir. Main power line construction awarded to Remo Engineering, with two work fronts established and tower construction underway. All major and long-lead-time process plant equipment contracts have been awarded. The furnace base plate components supplied by Hatch arrived on site on 3rd October, with onsite assembly and erection expected to commence within the next two weeks, and FLSmidth is also well advanced with manufacturing of the rotary kiln. Further, the Company has secured all key equipment supply and technical support services for the balance of the Araguaia process flow sheet from leading global suppliers. Combined, these contract awards act as a significant de-risking event for the Project.

Social programmes including SENAI vocational training continue, with 362 community members having already graduated or enrolled to provide a locally sourced workforce for the construction phase and the ongoing operation of Araguaia.

As part of working towards the Company's objective of producing 29,000 tpa nickel at Araguaia an engineering study is planned for Line 2 with the objective of providing an AACE Class 3 cost estimate and to advance the basic engineering.

The Horizonte project team have worked diligently to mitigate inflationary pressures on the Project budget to date which has included extensive efforts to optimise quantities through lean design and engineering, maximising competitive tension with Project suppliers and the successful deployment of a business improvement culture across the organisation, yielding material cost savings. Together, these efforts have allowed US$375m of capital commitments to be placed on budget as of the end of August 2022.

However, notwithstanding the strong progress made to date and these cost mitigation initiatives, the Project continues to face cost pressures driven by global inflation, a robust construction and mining environment in Brazil and rising interest rates, amongst others.

With a number of key local service contracts nearing award the Company now forecasts that the total project capital expenditure is expected to be US$537 million, versus the US$477 million originally budgeted in November 2021. Whilst the majority of this increase is driven by inflationary pressures the Company has also opted to invest in additional EPCM and owners team resources to further de-risk the Project schedule and seek to ensure delivery of first nickel in Q1 2024, in line with the original plan.

Further Information

Using a nickel price of US$23,000/t, the Araguaia Technical Report (as defined below) estimated a post-tax NPV8 of US$1.5B and post-tax IRR of 43%. Using the same nickel price, the Vermelho Technical Report (as defined below) estimated a post-tax NPV8 of US$3.4B and post-tax IRR of 39%.The feasibility study economics for Araguaia and the pre-feasibility study economics for Vermelho are both based on a nickel price of US$23,000/t and presented for information purposes only to reflect the latest pricing information and are otherwise based on all the same parameters as those underlying the economic analysis presented in the Araguaia Technical Report and the Vermelho Technical Report, respectively, which remain current. The Araguaia Technical Report parameters do not include the forecast increase in the capital expenditure amount to US$537 million.

Qualified Person(s)

David Hall acting a consultant to the Company is a qualified person as defined in National Instrument 43-101, and has reviewed, approved and verified the technical and scientific disclosure contained in this press release.

For additional information, including with respect to the economic parameters discussed herein on the Araguaia and the Vermelho projects, and the key assumptions and risks associated thereto, please refer to the Company's technical reports entitled Feasibility Study for the Araguaia Nickel Project Federative Republic of Brazil NI 43-101 Technical Report, dated November 2018 (the "Araguaia Technical Report") and Pre-Feasibility Study for the Vermelho Nickel-Cobalt Project Federative Republic of Brazil NI 43-101 Technical Report, dated October 2019 (the "Vermelho Technical Report") available at www.sedar.com. The Araguaia Technical Report remains current and the economic parameters therein do not include the forecast increase in capital expenditure at the Project.

Latest images from the Araguaia site

Horizonte Minerals PLC, Tuesday, October 4, 2022, Press release picture

Aerial view of the primary crusher pad and entrance ramp

Horizonte Minerals PLC, Tuesday, October 4, 2022, Press release picture

Preparation of the primary crusher retaining wall

Horizonte Minerals PLC, Tuesday, October 4, 2022, Press release picture

Deep pile foundation activity within the main furnace area

Horizonte Minerals PLC, Tuesday, October 4, 2022, Press release picture

Operating concrete plant with concrete slabs for the reinforced crusher wall

Horizonte Minerals PLC, Tuesday, October 4, 2022, Press release pictureHorizonte Minerals PLC, Tuesday, October 4, 2022, Press release picture

Arrival of Hatch furnace components in Brazil and first deliveries to site

For further information, visit www.horizonteminerals.com or contact:

Horizonte Minerals plc

Jeremy Martin (CEO)

info@horizonteminerals.com

+44 (0) 203 356 2901

Peel Hunt LLP (Nominated Adviser & Joint Broker)

Ross Allister

David McKeown

Georgia Langoulant

+44 (0)20 7418 8900

BMO (Joint Broker)

Thomas Rider

Pascal Lussier Duquette

Andrew Cameron

+44 (0) 20 7236 1010

Tavistock (Financial PR)                        

Emily Moss

Cath Drummond

+44 (0) 20 7920 3150

About Horizonte Minerals:

Horizonte Minerals plc (AIM & TSX: HZM) is developing two 100%-owned projects in Pará state, Brazil; the Araguaia Nickel Project and the Vermelho Nickel-Cobalt Project. Both projects are large scale, high-grade, low-cost, low-carbon and scalable. Araguaia is in construction. The project is expected to produce 29,000 tonnes of nickel per year to supply the stainless steel market. Vermelho is at feasibility study stage and is expected to produce 25,000 tonnes of nickel and 1,250 tonnes of cobalt to supply the EV battery market. Horizonte's combined near-term production profile of over 50,000 tonnes of nickel per year would position the Company as a globally significant nickel producer. Horizonte is developing a new nickel district in Brazil that will benefit from established infrastructure, including hydroelectric power available in the Carajás Mining District.

CAUTIONARY STATEMENT REGARDING FORWARD LOOKING INFORMATION

Except for statements of historical fact relating to the Company, certain information contained in this press release constitutes "forward-looking information" under Canadian securities legislation. Forward-looking information includes, but is not limited to, the ability of the Company to complete the acquisition of equipment and commence onsite erection as described herein; forecasts of total capital expenditure for the Project; statements with respect to the potential of the Company's current or future property mineral projects; the success of exploration and mining activities; cost and timing of future exploration, production and development; the ability of the Company to achieve its goals in respect of growing its mineral resources; the realization of mineral resource and reserve estimates and achieving production in accordance with the Company's potential production profile or at all. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, and are inherently subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to risks related to: the inability of the Company to complete the acquisition of equipment contemplated herein, on time or at all; exploration and mining risks, competition from competitors with greater capital; the Company's lack of experience with respect to development-stage mining operations; fluctuations in metal prices; uninsured risks; environmental and other regulatory requirements; exploration, mining and other licences; the Company's future payment obligations; potential disputes with respect to the Company's title to, and the area of, its mining concessions; the Company's dependence on its ability to obtain sufficient financing in the future; the Company's dependence on its relationships with third parties; the Company's joint ventures; the potential of currency fluctuations and political or economic instability in countries in which the Company operates; currency exchange fluctuations; the Company's ability to manage its growth effectively; the trading market for the ordinary shares of the Company; uncertainty with respect to the Company's plans to continue to develop its operations and new projects; the Company's dependence on key personnel; possible conflicts of interest of directors and officers of the Company, and various risks associated with the legal and regulatory framework within which the Company operates, together with the risks identified and disclosed in the Company's disclosure record available on the Company's profile on SEDAR at www.sedar.com, including without limitation, the annual information form of the Company for the year ended December 31, 2020, the Araguaia Report and the Vermelho Report. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

SOURCE: Horizonte Minerals PLC



View source version on accesswire.com:
https://www.accesswire.com/718809/Horizonte-Minerals-PLC--Araguaia-Nickel-Project-Construction-on-Schedule

News Provided by ACCESSWIRE via QuoteMedia

HZM:CA,HZM:LN
The Conversation (0)
FPX Nickel (TSXV:FPX)

FPX Nickel Completes Production Run of Battery-Grade Nickel Sulphate to Support Discussions with Prospective EV Battery Supply Chain Partners

FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) ("FPX" or the "Company") is pleased to announce successful production of additional battery-grade nickel sulphate from its Baptiste Nickel Project ("Baptiste" or the "Project"). Building on the success of previous testing campaigns, a production run was completed to produce larger quantities of nickel sulphate crystals. The nickel sulphate samples, which meet the strict target specifications for battery applications, will be provided to selected prospective downstream partners including pCAM producers, battery companies, and automakers pursuing supply security, traceable sourcing, and low carbon intensity production.

"The production of high-purity nickel sulphate further positions us to engage in strategic discussions with prospective downstream partners across the global EV supply chain," commented Martin Turenne, FPX Nickel's President and Director. "This milestone further demonstrates the strategic flexibility of the Baptiste awaruite concentrate and the technical maturity of the awaruite refining process."

Keep reading...Show less
Nickel bars in front of a world map.

Top 9 Nickel-producing Countries

The top nickel producing countries list has been shaken in recent years by Indonesia's rapid rise to the top, beating the Philippines and New Caledonia.

Demand for nickel is mounting. Stainless steel accounts for the vast majority of nickel demand, but electric vehicle (EV) batteries represent a growing application for the base metal as the shift toward a greener future gains steam.

But while nickel's long-term outlook appears bright, it may face headwinds in the short term. Nickel prices have been trending down since breaking US$20,000 per metric ton in May 2024 as weak usage coincides with strong output from top producer Indonesia.

Keep reading...Show less

First Atlantic Nickel to Attend Benchmark Mineral Intelligence's GIGA USA 2025 Conference, Highlighting Atlantic Nickel Project's Smelter-Free Processing for North America's Critical Minerals Supply Chain

First Atlantic Nickel Corp. (TSXV: FAN) (OTCQB: FANCF) (FSE: P21) ("First Atlantic" or the "Company") is pleased to announce its participation at the Benchmark Mineral Intelligence GIGA USA 2025 conference, taking place June 3-4, 2025, in Washington, DC. The Company will participate in strategic meetings during this critical mineral conference to demonstrate how its Atlantic Nickel Project addresses the growing need for nickel mining that can be completely processed in North America. The Atlantic Nickel Project contains nickel in the form of awaruite, a naturally occurring, sulfur-free, highly magnetic mineral with approximately 75% nickel content. These unique properties enable direct processing through magnetic separation and flotation, eliminating reliance on foreign overseas smelting or roasting operations. This simplified mineral processing method significantly lowers energy requirements and reduces environmental impacts, strengthening the development of a resilient, domestic critical minerals supply chain.

The GIGA USA conference brings together key players from across the critical minerals sector for two days of networking, dealmaking, and policy discussions. Attendees include major automakers such as Tesla, Ford, General Motors, Rivian, Mercedes-Benz, and Volkswagen; battery manufacturers like LG Energy Solutions, Samsung SDI, and Panasonic Energy; and global mining companies including Rio Tinto, Vale, Glencore, South32, and Anglo American. Government representatives from the U.S. Department of Energy, U.S. Department of Commerce, U.S. Department of Defense, U.S. Department of State, the Government of Quebec, the Embassy of Canada, and the Delegation of the European Union will also attend. Conference topics will address the expansion of the United States' lithium-ion battery gigafactory industry and the need to establish secure, sustainable supply chains for critical raw materials, including lithium, nickel, graphite, cobalt, manganese and rare earth elements.

The conference addresses key areas of focus including strengthening the U.S. critical minerals supply chain through domestic production and expanded gigafactory capacity, examining policy and trade impacts, such as the Inflation Reduction Act (IRA), and enhancing national security through critical mineral independence. The conference will also focus on investment and financing opportunities for next-generation mining projects, innovations in battery technology and sustainability, and the importance of global collaboration and strategic partnerships.

The Company's Atlantic Nickel Project offers a secure and reliable solution for domestic nickel production. By leveraging awaruite's sulfur-free composition, high nickel content and magnetic properties, the project enables simple processing through magnetic separation and flotation without the need for secondary processing such as smelting or roasting. Unlike traditional nickel sulfide and laterite projects that undergo energy-intensive processes creating harmful waste and emissions, awaruite's metallurgical properties enable complete domestic nickel production while eliminating reliance on overseas processing. The lower energy requirements and sulfur-free nature of awaruite result in a reduced carbon and environmental footprint. The Company remains committed to strengthening North American critical minerals supply chains, with the Atlantic Nickel Project positioned to provide a secure, reliable nickel source for North American industries including electric vehicles, batteries, defense, and stainless steel manufacturing.

Conference Meeting Requests

First Atlantic welcomes the opportunity to meet with strategic partners, shareholders and investors during the GIGA USA 2025 conference. Interested parties are encouraged to contact Rob Guzman at rob@fanickel.com or by phone at 844-592-6337 to arrange meetings. The conference takes place June 3-4, 2025 in Washington, DC.

Phase 2 Drilling Update

The Phase 2 drilling program is currently underway and successfully expanding the awaruite mineralization identified in multiple drill holes during the Phase 1 campaign. Technical improvements, including optimized HQ/NQ drill configurations and enhanced drill bit selection, have enabled the current program to reach greater depths than previously achieved. The Company anticipated providing updates on the Phase 2 drill holes in the coming weeks.

For further information, questions, or investor inquiries, please contact Rob Guzman at First Atlantic Nickel by phone at +1-844-592-6337 or via email at rob@fanickel.com

Corporate Update

The Company also announces that on May 21, 2025 it closed the definitive agreement dated May 6, 2025 (the "Purchase Agreement") to acquire a 100% interest in eight mineral licenses totaling approximately 3,350 hectares. These licenses are strategically located around the Company's Atlantic Nickel Project in central Newfoundland, in the Cold Spring Pod and Coy Pond areas. Under the terms of the Purchase Agreement, the Company has issued 1,000,000 Shares at a deemed price of $0.205 per Share. These Shares are subject to a statutory hold period of four months and one day, in accordance with applicable Canadian securities laws. And further to its May 6, 2025 news release, it closed the previously announced settlement agreement (the "Settlement Agreement") on May 22, 2025, to settle outstanding obligations totaling $202,950 owed to an arm's length creditor (the "Creditor") related to accounting services provided under a consulting agreement dating back to 2017. Pursuant to the Settlement Agreement, the Company has issued an aggregate of 312,500 common shares (each, a "Share") at a deemed price of $0.32 per Share. These Shares will be released in three equal tranches over a 12-month period and are subject to a statutory hold period of four months and one day, in accordance with applicable Canadian securities laws.

Awaruite (Nickel-iron alloy Ni₂Fe, Ni₃Fe)

Awaruite, a naturally occurring sulfur-free nickel-iron alloy composed of Ni₃Fe or Ni₂Fe with approximately ~75% nickel content, offers a proven and environmentally safe solution to enhance the resilience and security of North America's domestic critical minerals supply chain. Unlike conventional nickel sources, awaruite can be processed into high-grade concentrates exceeding 60% nickel content through magnetic processing and simple floatation without the need for smelting, roasting, or high-pressure acid leaching 1 . Beginning in 2025, the US Inflation Reduction Act's (IRA) $7,500 electric vehicle (EV) tax credit mandates that eligible clean vehicles must not contain any critical minerals processed by foreign entities of concern (FEOC) 2 . These entities include Russia and China, which currently dominate the global nickel smelting industry. Awaruite's smelter-free processing approach could potentially help North American electric vehicle manufacturers meet the IRA's stringent critical mineral requirements and reduce dependence on FEOCs for nickel processing.

The U.S. Geological Survey (USGS) highlighted awaruite's potential, stating, "The development of awaruite deposits in other parts of Canada may help alleviate any prolonged shortage of nickel concentrate. Awaruite, a natural iron-nickel alloy, is much easier to concentrate than pentlandite, the principal sulfide of nickel." 3 Awaruite's unique properties enable cleaner and safer processing compared to conventional sulfide and laterite nickel sources, which often involve smelting, roasting, or high-pressure acid leaching that can release toxic sulfur dioxide, generate hazardous waste, and lead to acid mine drainage. Awaruite's simpler processing, facilitated by its amenability to magnetic processing and lack of sulfur, eliminates these harmful methods, reducing greenhouse gas emissions and risks associated with toxic chemical release, addressing concerns about the large carbon footprint and toxic emissions linked to nickel refining.

First Atlantic Nickel Corp.

Figure 1: Quote from USGS on Awaruite Deposits in Canada

The development of awaruite resources is crucial, given China's control in the global nickel market. Chinese companies refine and smelt 68% to 80% of the world's nickel 4 and control an estimated 84% of Indonesia's nickel output, the largest worldwide supply 5 . Awaruite is a cleaner source of nickel that reduces dependence on foreign processing controlled by China, leading to a more secure and reliable supply for North America's stainless steel and electric vehicle industries.

Investor Information

The Company's common shares trade on the TSX Venture Exchange under the symbol " FAN ", the American OTCQB Exchange under the symbol " FANCF " and on several German exchanges, including Frankfurt and Tradegate, under the symbol " P21 ".

Investors can get updates about First Atlantic by signing up to receive news via email and SMS text at www.fanickel.com . Stay connected and learn more by following us on these social media platforms:

https://x.com/FirstAtlanticNi

https://www.facebook.com/fanickelcorp

https://www.linkedin.com/company/firstatlanticnickel/

FOR MORE INFORMATION:
First Atlantic Investor Relations
Robert Guzman
Tel: +1 844 592 6337
rob@fanickel.com

Disclosure

Adrian Smith, P.Geo., a director and the Chief Executive Officer of the Company is a qualified person as defined by NI 43-101. The qualified person is a member in good standing of the Professional Engineers and Geoscientists Newfoundland and Labrador (PEGNL) and is a registered professional geoscientist (P.Geo.). Mr. Smith has reviewed and approved the technical information disclosed herein.

About First Atlantic Nickel Corp.

First Atlantic Nickel Corp. (TSXV: FAN) (OTCQB: FANCF) (FSE: P21) is a Canadian mineral exploration company developing the 100%-owned Atlantic Nickel Project, a large-scale nickel project strategically located near existing infrastructure in Newfoundland, Canada. The Project's nickel occurs as awaruite, a natural nickel-iron alloy containing approximately 75% nickel with no-sulfur and no-sulfides. Awaruite's properties allow for smelter-free magnetic separation and concentration, which could strengthen North America's critical minerals supply chain by reducing foreign dependence on nickel smelting. This aligns with new US Electric Vehicle US IRA requirements, which stipulate that beginning in 2025, an eligible clean vehicle may not contain any critical minerals processed by a FEOC (Foreign Entities Of Concern) 6 .

First Atlantic aims to be a key input of a secure and reliable North American critical minerals supply chain for the stainless steel and electric vehicle industries in the USA and Canada. The company is positioned to meet the growing demand for responsibly sourced nickel that complies with the critical mineral requirements for eligible clean vehicles under the US IRA. With its commitment to responsible practices and experienced team, First Atlantic is poised to contribute significantly to the nickel industry's future, supporting the transition to a cleaner energy landscape. This mission gained importance when the US added nickel to its critical minerals list in 2022, recognizing it as a non-fuel mineral essential to economic and national security with a supply chain vulnerable to disruption.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-looking statements:

This news release may include "forward-looking information" under applicable Canadian securities legislation. Such forward-looking information reflects management's current beliefs and are based on a number of estimates and/or assumptions made by and information currently available to the Company that, while considered reasonable, are subject to known and unknown risks, uncertainties, and other factors that may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking information.

Forward-looking information in this news release includes, but is not limited to: statements regarding: the timing, scope and results of the Company's Phase 1 and Phase 2 work and drilling programs; future project developments; the Company's objectives, goals, and future plans; statements and estimates of market conditions; the viability of magnetic separation as a low-impact processing method for awaruite; the strategic and economic implications of the Company's projects   ; and expectations regarding future developments and strategic plans;   Readers are cautioned that such forward-looking information are neither promises nor guarantees and are subject to known and unknown risks and uncertainties including, but not limited to, general business, economic, competitive, political and social uncertainties, uncertain and volatile equity and capital markets, lack of available capital, actual results of exploration activities, environmental risks, future prices of base and other metals, operating risks, accidents, labour issues, delays in obtaining governmental approvals and permits, and other risks in the mining and clean energy industries. Additional factors and risks including various risk factors discussed in the Company's disclosure documents which can be found under the Company's profile on http://www.sedarplus.ca. Should one or more of these risks or uncertainties materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual results may vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected.

The Company is presently an exploration stage company. Exploration is highly speculative in nature, involves many risks, requires substantial expenditures, and may not result in the discovery of mineral deposits that can be mined profitably. Furthermore, the Company currently has no mineral reserves on any of its properties. As a result, there can be no assurance that such forward-looking statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking information, except as required by applicable securities laws.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Ni-Co Energy

Ni-Co Energy Set to Mobilize Critical Minerals Exploration just 90 km from Montreal

Ni-Co Energy Inc. announces that its technical team will be mobilized to the Kremer property around mid-June 2025. The project is located approximately 90 km north of downtown Montreal and about 15 km from the nearest municipality, in a remote forested area with access via an existing road and close proximity to the hydroelectric grid.

Meet The Team:

Keep reading...Show less
Nickel Outlook: World Edition

Nickel Outlook: World Edition

Nickel Outlook: World Edition

Investing in nickel? Let our experts help you stay ahead of the markets.

✓ Trends✓ Forecasts✓ Top Stocks

Who We Are

The Investing News Network is a growing network of authoritative publications delivering independent, unbiased news and education for investors. We deliver knowledgeable, carefully curated coverage of a variety of markets including gold, cannabis, biotech and many others. This means you read nothing but the best from the entire world of investing advice, and never have to waste your valuable time doing hours, days or weeks of research yourself.

Keep reading...Show less

Latest Press Releases

Related News

×