Energizer Resources Inc. (TSX:EGZ,OTCBB:ENZR,FWB:YE5) announced its strategies and timelines for the development of its Molo Graphite deposit in Madagascar, including a full Feasibility Study in Q2 2013, construction of two pilot plants in Q2 2014, and production in Q4 2015.

Energizer Resources Inc. (TSX:EGZ,OTCBB:ENZR,FWB:YE5) announced its strategies and timelines for the development of its Molo Graphite deposit in Madagascar, including a full Feasibility Study in Q2 2013, construction of two pilot plants in Q2 2014, and production in Q4 2015.

As quoted in the press release:

Energizer is now focused on the next series of milestones. These include:

  • Commencement of a full Feasibility Study in Q2 2013
    • This includes construction of two pilot plants, each at a different accredited lab to;
      • i) Produce the necessary quantity of samples for presentation to potential off take partners
      • ii) Optimize flake size distribution
      • iii) To further upgrade our concentrates from purities between 98% and 98.6% graphitic carbon to battery grade target purity levels of greater than 99%
  • Full Feasibility Study completion targeted for Q4 2013
  • Start of mine construction targeted for Q2 2014
  • Production targeted for Q4 2015

Click here to read the Energizer Resources Inc. (TSX:EGZ,OTCBB:ENZR,FWB:YE5) press release

See this press release on Marketwire
Click here to see the Energizer Resources Inc. (TSX:EGZ,OTCBB:ENZR,FWB:YE5) profile.

The Conversation (0)
×