Magna Mining Inc's Shakespeare Nickel Project Feasibility Study Demonstrates Positive Economics and Carbon Neutral Nickel Mining Operation

Magna Mining Inc's Shakespeare Nickel Project Feasibility Study Demonstrates Positive Economics and Carbon Neutral Nickel Mining Operation

Magna Mining Inc (TSXV: NICU) (the "Company") is pleased to announce the results of the 2022 Feasibility Study for the Shakespeare Nickel Project ("Shakespeare") located 60 km south-west of Sudbury, Ontario. The Feasibility Study ("Study") is considered a base case and does not include any of the results from the 2021 Shakespeare drilling campaign (as highlighted in Figure 3). This Study remains within the constraints of current approvals, with only minor amendments and permits required prior to the start of construction. Shakespeare has a filed Closure Plan that has been accepted (approved) by the Ministry of Northern Development, Mines, Natural Resources and Forestry, and has obtained major permits for construction of a 4500 tonne per day (tpd) open pit mine, mill and tailing storage facility.

Included in the feasibility study is an analysis of the greenhouse gas (GHG) emissions over the life-of-mine. The deposit type, availability of renewable energy and emission reduction opportunities will allow the Shakespeare site to extract ore and produce nickel and copper concentrates with below average emission intensity. Verified carbon offsets for the remaining GHG emission sources have been included in operational costs, resulting in a carbon neutral nickel mining operation.

Highlights Include (all results are reported in Canadian Dollars unless otherwise noted):

  • Base Case results demonstrate a Pre-Tax NPV6% of $221 million, IRR of 27.2%, and a 3.4-year payback, and a Post-Tax NPV6% of $140 million, IRR of 21.5% and 3.5 year post-tax payback period based on metal prices of US$ 8.50/lb. nickel, US$ 3.95/lb. copper, US$ 24/lb. cobalt, US$ 950/oz platinum, US$ 1,750/oz palladium and US$ 1,600 gold and an exchange rate of 0.77 US$:CDN.
  • Initial capital requirements of $232.9 million, including all mine pre-production costs, co-disposal area preparation and sustaining capital of $9.2 million (including closure).
  • Operating Costs of $41.18/t ore include carbon offset purchases
  • Cash cost of US$(-0.76)/lb. nickel and AISC of US$(-0.61)/lb. nickel net of copper, cobalt and PGM by-product credits
  • Recovered in concentrate nickel of 65.7 million pounds, copper of 86.7 million pounds, cobalt of 3.0 million pounds and PGM's of 177,000 ounces
  • Average strip ratio of 4.98:1 with 11.9 million tonnes of reserves

Magna Mining CEO Jason Jessup commented: "This feasibility study demonstrates why we think the Shakespeare Nickel Project has the potential to be the next nickel producing project in Canada, and it confirms our belief that Shakespeare is an attractive stand-alone operation at current nickel and copper prices. The results of the study show positive economics, a modest upfront capital cost and strong leverage to the price of nickel and copper. Building the project as outlined in the feasibility would also give us a cornerstone asset with which to pursue Magna's vision of developing a hub and spoke production model in the world class Sudbury nickel mining camp. Aside from organic growth at our Shakespeare Project, we are evaluating acquisition opportunities that have synergies with Shakespeare. We are quite proud that the Study also includes detailed carbon accounting and incorporates the purchase of carbon offset credits to become a carbon neutral nickel mining operation. We believe that Shakespeare is the only feasibility stage nickel project in North America that can make this claim."

Paul Fowler, Magna Mining SVP added: "We are delighted to be able to complete this feasibility study within a year of our 2021 public listing, and it demonstrates the potential for Shakespeare to be Canada's next producing nickel mine. Our recent successful drill campaigns at the Shakespeare Mine and the adjacent P-4 exploration target also provide encouraging evidence that we will be able to fulfill our goal of further growing the resources at Shakespeare, potentially extending the life of mine and making new discoveries on our property package."

Financial Analysis

The Base Case using US$8.50/lb. nickel, US$3.95/lb. copper, US$ 24/lb. cobalt, US$ 950/oz platinum, US$ 1,750/oz palladium and US$ 1,600 gold and an exchange rate of 0.77 US$:CDN generates a before tax NPV6% of $221 million and an IRR of 27.2%, with a 3.4 year payback. After-tax NPV6% is $140 million, with an Internal Rate of Return (IRR) of 21.5%. Payback on the initial capital is 3.5 years.

Table 1: Summary of Shakespeare Project Economic Results - Metal Price Sensitivity


UnitsUpside CaseSpot Price
Jan 2022
Base CaseLow Case
Nickel US$/lb.12.0010.288.507.00
CopperUS$/lb.4.754.443.953.00
CobaltUS$/lb.33.0032.6624.0017.50
PlatinumUS$/oz1,0001,030950900
Palladium US$/oz2,1502,1531,7501,400
GoldUS$/oz1,8501,8381,6001,500
Pre-Tax NPV (6%) CDN$ millions48738022143
Pre-Tax IRR%51.141.527.210.3
Post-Tax NPV (6%)CDN$ millions31824714014
Post-Tax IRR (%)%41.133.321.57.5

 

Revenue for the project is primarily from nickel (49%) with copper as the second largest revenue contributor (32%). Cobalt and PGM's account for the remainder of revenues as shown in Figure 1.

The Study has a mine life of 7.1 years with the current reserves.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/8002/112113_d8db3eb98476a8be_002.jpg

Figure 1: Shakespeare Revenue By Metal

To view an enhanced version of Figure 1, please visit:
https://orders.newsfilecorp.com/files/8002/112113_d8db3eb98476a8be_002full.jpg

Capital and Operating Costs

The Study was prepared in accordance with National Instrument 43-101 (NI 43-101 of the Canadian Securities Administrators). The capital and operating cost estimates are summarized below. The operating costs have been detailed in Table 2, cash costs in Table 3 and the capital costs in Table 4.

The operating costs are estimated at $41.18/t ore over the mine life which include the purchase of carbon offsets and financing of the mining fleet with a 20% initial payment. The initial capital cost is $232.9 million with sustaining capital of $9.2 million including closure. The All In Sustaining Cost (AISC) is US$(0.61)/lb. nickel payable, net of by-product credits.

Table 2: Operating Cost Summary (CDN$)

Operating CostCost ($ M)$/t Ore
Mining243.720.53
Processing179.715.14
G&A35.32.98
Transport & Refining9.20.78
Carbon Offset Purchase3.10.26
Royalties17.71.49
Total Operating Cost488.841.18

 

Table 3: Cash Costs and All In Sustaining Costs (US$)

Operating CostUnitsCost
Nickel Cash CostUS$/lb. payable$8.00
Nickel Cash Cost (including by-product credits) US$/lb. payable$ (0.76)
Nickel All In Sustaining Costs (AISC)US$/lb. payable$8.15
Nickel AISC (including by-product credits) US$/lb. payable$(0.61)

 

Table 4: Capital Cost Summary ($CDN)

Capital CostTotal ($ M)Initial ($M)Sustaining ($M)
Mining61.458.72.6
Processing64.863.51.3
Infrastructure59.359.3-
Environmental7.01.85.2
Subtotal192.5183.49.1
Indirects29.929.9-
Contingency19.719.60.1
Total Capital Cost242.1232.99.2

 

The Study estimates the metal production as shown in Table 5.

Table 5: Life of Mine Metal Production

MetalRecovery (%)Contained Metal in Concentrate (Mlbs. or K oz)
Nickel76.865.7
Copper95.186.7
Cobalt55.93.0
Platinum76.293
Palladium42.958
Gold38.326

 

Mining and Infrastructure

The Study considers the use of an owner operated fleet including 12-91 tonne trucks, hydraulic excavators, wheel loaders and drills. The mine is designed to provide 4,500 tpd of mill feed to the process plant to be constructed adjacent to the pit. The annual mining rate averages 11.5 Mtpa in the first four years, peaking at 11.9 Mtpa in Year 3 before tapering off until the end of the mine life. The production profile is shown in Figure 2 with the two main grade items: nickel and copper.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/8002/112113_d8db3eb98476a8be_003.jpg

Figure 2: Shakespeare Mine Production Profile

To view an enhanced version of Figure 2, please visit:
https://orders.newsfilecorp.com/files/8002/112113_d8db3eb98476a8be_003full.jpg

Material from the pit will be used to construct the Co-Disposal Area (CDA) for storage of waste and tailings in the adjacent valley. This facility will be lined allowing the long-term storage of potentially acid generating tailings (PAG) material from the process plant and any PAG material from the mine beneath the water level and control of the drainage from the waste stored within its footprint. The process plant will generate both PAG tailings and non-acid generating tailings (NAG) that are separated at the plant. The NAG tailings will be stored with the NAG waste rock from the mine. NAG waste not used in construction of the plant pad and haul roads will be stored in the CDA. The CDA includes a settling pond, polishing pond and water treatment facility for any variances in water quality encountered prior to discharge to the environment. The water management system has been designed to reuse site water for process applications, minimize freshwater requirements and effectively collect contact run-off in accordance with legislative requirements.

The Shakespeare benefits from past mining infrastructure that still exists and its proximity to Sudbury. This enables the mine to operate without the need of camp facilities due to its all-season road currently in place. Existing infrastructure and nearby infrastructure include:

  1. All season access road only requiring minor upgrading
  2. Existing sand and gravel quarries for construction material of the plant and CDA
  3. Access to hydro power at Espanola for quick connection to the grid
  4. Settling ponds in place adjacent to the pit
  5. Access to the edges of the pit for mining equipment

Mineral Resources and Reserves

The Open Pit Indicated Mineral Resource Estimate upon which the Study is based includes 203.8 Mlbs of nickel equivalent from 16.51 Mt grading 0.34% nickel, 0.36% copper, 0.02% cobalt, 0.33 g/t platinum, 0.36 g/t palladium and 0.19 g/t gold. No Inferred Mineral Resource is contained within the Mineral Resource pit shell.

Underground Mineral Resources use a 0.4% NiEq cutoff and are estimated below the open pit resource shell. The Underground Mineral Resource contains 44.8 Mlbs of nickel equivalent Indicated Resource and 29.6 Mlbs of nickel equivalent in the Inferred Resource.

The mineral resources are shown in Table 6.

Table 6: Shakespeare Mineral Resources (June 1, 2021)


UnitsOpen Pit
Underground
Total
Indicated
IndicatedInferred
IndicatedInferred
CutoffNi Eq%0.2%
0.4%0.4%
0.2/0.4%0.4%
TonnageM Tonnes16.51
3.832.36
20.342.36
Nickel%0.34
0.310.33
0.330.33
Copper%0.36
0.360.40
0.360.40
Cobalt%0.02
0.020.02
0.020.02
Platinumg/t0.33
0.300.34
0.320.34
Palladiumg/t0.36
0.320.37
0.350.37
Goldg/t0.19
0.190.20
0.190.20
Nickel Equivalent%0.56
0.530.57
0.550.57









NickelMlbs.123.7
26.217.1
149.917.1
CopperMlbs.131.0
30.420.8
161.420.8
CobaltMlbs.7.3
1.71.0
9.01.0
PlatinumK oz175.1
25.317.7
200.517.7
PalladiumK oz191.1
27.019.2
218.119.2
GoldK oz100.8
16.110.4
116.910.4
Nickel EquivalentMlbs.203.8
44.829.6
248.629.6

 

  1. Mineral Resources are exclusive of material mined.
  2. CIM (2014) definitions were followed for Mineral Resources Reporting.
  3. Mineral resources which are not mineral reserves do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. Composites have been capped where appropriate.
  4. Open pit Mineral Resources are reported at a base case cut-off grade of 0.2% NiEq within a conceptual pit shell.
  5. Underground (below-pit) Mineral Resources are estimated from the bottom of the pit and are reported at a base case cut-off grade of 0.4% NiEq. The underground Mineral Resource grade blocks were quantified above the base case cut-off grade, below the constraining pit shell and within the constraining mineralized wireframes. At this base case cut-off grade the deposit shows excellent deposit continuity.
  6. Based on the size, shape, and orientation of the Deposit, it is envisioned that the underground mineralization may be mined using the longitudinal longhole retreat mining method (a branch of the generic mining method known as sublevel stoping).
  7. A fixed specific gravity value of 3.00 was used to estimate the resource tonnage from block model volumes; an SG of 2.85 for waste.
  8. NiEq Cut-off grades are based on metal prices of $7.50/lb Ni, $3.25/lb Cu, $21.00/lb Co, $1,000/oz Pt, $2,000/oz Pd and $1,600/oz Au, and metal recoveries of 75% for Ni, 96% for copper, 56% for Co, 73% for Pt, 39% for Pd and 36% for Au.
  9. The results from the pit optimization are used solely for the purpose of testing the "reasonable prospects for economic extraction" by an open pit and do not represent an attempt to estimate mineral reserves. The results are used as a guide to assist in the preparation of a Mineral Resource statement and to select an appropriate resource reporting cut-off grade.
  10. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. There is no certainty that all or any part of the Inferred Mineral Resource will be upgraded to an Indicated or Measured Mineral Resource as a result of continued exploration.

Mineral Reserves for the Shakespeare Project have been shown in Table 7. The Mineral Reserve is based on a marginal cutoff using a net smelter calculation which is equivalent to a 0.23% nickel cutoff grade.

Table 7: Shakespeare Mineral Reserves (December 31, 2021)


UnitsOpen Pit
Probable
CutoffNi%0.23
TonnageM Tonnes11.87
Nickel%0.33
Copper%0.35
Cobalt%0.02
Platinumg/t0.32
Palladiumg/t0.36
Goldg/t0.18



NickelMlbs.85.6
CopperMlbs.91.1
CobaltMlbs.5.4
PlatinumK oz122.2
PalladiumK oz135.7
GoldK oz68.9

 

Note: CIM Definition Standards (2014) were followed for calculating Mineral Reserves. The mineral reserve estimate is as of December 31, 2021 and is based on the mineral resource estimate for the Shakespeare Property dated June 1, 2021. The mineral reserve estimate was completed under the supervision of Gordon Zurowski, P.Eng. of AGP, who is a Qualified Person as defined under NI 43-101. Mineral reserves are stated within the final pit design based on metal prices of US$ 6.50/lb. nickel, US$ 3.00/lb. copper, US$ 17/lb. cobalt, US$ 900/oz platinum, US$ 1,700/oz palladium and US$ 1,500 gold and an exchange rate of 0.77 US$:CDN. Metal recoveries are 76.8% nickel, 95.1% copper, 55.9% cobalt, 76.2% platinum, 42.9% palladium and 38.3% gold. The nickel cutoff applied was 0.23% nickel. Open pit mining costs used were $2.30/t mined. Processing costs were $15.23/t ore and G&A was $2.59/t ore. Numbers may not sum due to rounding.

Opportunities for Optimization and Growth

Given that the feasibility study is based on maintaining the operational parameters under which permits for construction of the Shakespeare Mine, mill and tailings storage facility have been issued, numerous opportunities remain for optimization and growth. The most significant of these opportunities are:

  • Expansion of Mineral Resources and Conversion to Mineral Reserves
    • The feasibility study resources have an effective date of June 1, 2021 and therefore does not include the results of the 2021 drilling program at Shakespeare (with additional assays still pending). Reported assays in the Gap, West and East Zones will be incorporated into a resource update in the future (see Fig. 1).
  • Underground Mining Potential
    • Underground resources have been outlined beneath the Feasibility open pit which may represent an opportunity for low-cost, bulk underground mining. This will be investigated in future studies to determine if a viable underground mine could provide additional feed to the mill and extend the life of mine.
  • Effect of Higher Nickel Prices on Final Pit Design
    • Reserves for the Study were calculated using US$6.50/lb nickel, US$3.00/lb copper, US$17/lb cobalt, US$900/oz platinum, US$1700/oz palladium and US$1500/oz gold. At higher metal prices, there is potential to push the pit deeper which may incorporate additional resource material, possibly extending mine life.
  • New Exploration Targets
    • Magna intends to continue to explore and expand on existing mineralized targets which show potential to become economic, high grade satellite deposits to feed a future Shakespeare mill.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/8002/112113_d8db3eb98476a8be_004.jpg

Figure 3: Longitudinal Section of Shakespeare Deposit Showing Feasibility Open Pit Design and Resource Shell and Selected Previously Reported 2021 Exploration Drilling Results

To view an enhanced version of Figure 3, please visit:
https://orders.newsfilecorp.com/files/8002/112113_d8db3eb98476a8be_004full.jpg

All composite intervals are reported as core length as true width has not been determined.

Nickel Equivalent (NiEq%) grade is calculated based on metal prices of $6.25/lb Ni, $2.80/lb Cu, $31.00/lb Co, $950/oz Pt, $900/oz Pd and $1,250.00/oz Au, and metal recoveries of 76.4% for Ni, 95.9% for Cu, 71% for Co, 74.8% for Pt, 42.4% for Pd and 38.4% for Au.

Qualified Person

Certain technical information in this press release has been reviewed and approved by Mynyr Hoxha, Ph.D., P.Geo., the Company's Vice President of Exploration. Dr. Hoxha is a qualified person under Canadian National Instrument 43-101. Dr. Hoxha is an employee of Magna and is not independent of the Company under NI 43-101

The Feasibility Study was prepared under the direction and supervision of Gordon Zurowski, P. Eng Principal Mining Engineer with AGP, and the supporting Technical Report (the "Technical Report") will be available on SEDAR (www.sedar.com) under the Company's issuer profile within 45 calendar days. Mr. Zurowski, who is an independent Qualified Person as defined under NI 43-101, has reviewed, and approved the technical information pertaining to the Feasibility Study disclosed in this press release.

About Magna Mining Inc.

Magna Mining is an exploration and development company focused on nickel, copper and PGM projects in the Sudbury Region of Ontario, Canada. The Company's flagship asset is the past producing Shakespeare Mine which has major permits for the construction of a 4500 tonne per day open pit mine, processing plant and tailings storage facility and is surrounded by a contiguous 180km2 prospective land package. Additional information about the Company is available on SEDAR (www.sedar.com) and on the Company's website (www.magnamining.com).

For further information, please contact:
Jason Jessup
Chief Executive Officer
or
Paul Fowler, CFA
Senior Vice President
Email: info@magnamining.com

Cautionary Statement

This press release contains certain forward-looking information or forward-looking statements as defined in applicable securities laws. Forward-looking statements are not historical facts and are subject to several risks and uncertainties beyond the Company's control, including statements regarding the production at the Shakespeare Mine, the economic and operational potential of the Shakespeare Mine, potential acquisitions, plans to complete exploration programs, potential mineralization, exploration results and statements regarding beliefs, plans, expectations, or intentions of the Company. Resource exploration and development is highly speculative, characterized by several significant risks, which even a combination of careful evaluation, experience and knowledge may not eliminate. All forward-looking statements herein are qualified by this cautionary statement. Accordingly, readers should not place undue reliance on forward-looking statements. The Company undertakes no obligation to update publicly or otherwise revise any forward-looking statements whether as a result of new information or future events or otherwise, except as may be required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accept responsibility for the adequacy or accuracy of this press release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/112113

News Provided by Newsfile via QuoteMedia

NICU:CA
The Conversation (0)
Magna Mining Appoints Jonathan Goodman as a Non-Executive Director

Magna Mining Appoints Jonathan Goodman as a Non-Executive Director

Magna Mining Inc. (TSXV: NICU) ("Magna" or the "Company") is pleased to announce the appointment of Jonathan Goodman to Magna's Board of Directors. Mr. Goodman is currently the President and CEO of Dundee Corporation ("Dundee") and is also the President and CEO of Dundee Goodman Merchant Partners, a mining focused merchant bank. Dundee currently holds a 19.2% investment interest in Magna as of October 26, 2021 (see news release).

Mr. Goodman previously served as CEO of Dundee Precious Metals from 1995 to 2013, as Executive Chairman from April 2013 to September 2017, at which time he was appointed Chairman.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Magna Mining Commissions Second Drill Rig at the Shakespeare Project and Provides an Update on the Evaluation of a Toll Milling Restart for Near-Term Nickel Production

Magna Mining Commissions Second Drill Rig at the Shakespeare Project and Provides an Update on the Evaluation of a Toll Milling Restart for Near-Term Nickel Production

Magna Mining Inc (TSXV: NICU) (the "Company") is pleased to announce that it has commissioned a second drill rig to accelerate exploration drilling at previously identified regional targets on the Shakespeare Nickel Project. The second rig was moved to site early this month, and recently began drilling at the Company's Spanish River Mine Option ("Spanish River"), located 1km south-west of the recent P-4 nickel discovery (see Fig. 1). Spanish River was previously in production as an underground Cu-Co-Au-Ag operation until 1970, and the current drill program is the first diamond drilling program since the mine closed.

The first drill rig of the 2022 drill program started in January and is currently drilling the P-4 Nickel target, which was discovered during the 2021 regional exploration drill program (see News Release). This drill is planning to complete an initial 2500m of drilling to further test the EM plate associated with the discovery hole, as well as the prospective trend of over 400m of strike length to the east. The Company expects this drilling to be completed in early April, with assay results coming out later that month. Magna is planning to complete 10,000m of drilling in 2022, with 5500 m still to be allocated based on results from the winter drilling program.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Magna Mining Files Technical Report for the Shakespeare Nickel Project

Magna Mining Files Technical Report for the Shakespeare Nickel Project

Magna Mining Inc. (TSXV: NICU) ("Magna" or the "Company") is pleased to announce that further to its news release dated January 31, 2022, it has filed on SEDAR an independent technical report titled "Shakespeare Project Feasibility Study Technical Report" in respect of its Shakespeare Nickel Project located 60 km south-west of Sudbury, Ontario. The technical report has been filed in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects. A copy of the technical report is available under the Company's profile page at www.sedar.com.

The independent technical report is dated March 17, 2022, with an effective date of January 31, 2022, and was prepared by AGP Mining Consultants Inc.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Magna Mining Inc. Announces Non-Binding Memorandum of Understanding for Proposed Joint Venture Arrangement with Mitsui & Co. for Shakespeare Mine

Magna Mining Inc. Announces Non-Binding Memorandum of Understanding for Proposed Joint Venture Arrangement with Mitsui & Co. for Shakespeare Mine

Magna Mining Inc. (TSXV: NICU) ("Magna" or the "Company") is pleased to announce that it has entered into a non-binding memorandum of understanding ("MOU") with Mitsui & Co., Ltd. ("Mitsui"), whereby Magna and Mitsui will discuss the possibility of Mitsui's acquirement of a 10 to 12.5% interest in Magna's Shakespeare Mine in exchange for cash consideration ranging between $8 million to $10 million on such terms as to be further negotiated between the parties (the "Transaction"). In connection with the Transaction, it is expected that the parties will enter into a joint venture agreement to jointly pursue the development of the Shakespeare Mine, with Magna being the operator of the Project (the "Joint Venture" or "JV").

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Magna Mining Engages Independent Trading Group as Market-Maker

Magna Mining Engages Independent Trading Group as Market-Maker

Magna Mining Inc. (TSXV: NICU) ("Magna" or the "Company") is pleased to announce that it has entered into a market-making agreement (the "Agreement") with Independent Trading Group ("ITG"), pursuant to which ITG has agreed to provide market-making services to the Company in accordance with the policies of the TSX Venture Exchange (the "Exchange") and applicable laws.

ITG will trade shares of the Company on the TSXV and other available trading venues with the objective of maintaining a reasonable market and improving the liquidity of the Company's common shares.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Miramar Resources

Quarterly Activities & Cashflow Report - Quarter ending 31 March 2024

Miramar Resources Limited (ASX:M2R, “Miramar” or “the Company”) is pleased to provide a summary of activities completed during the Quarter ending 31 March 2024.

Keep reading...Show less
Canadian Critical Minerals

Canadian Critical Minerals Closes $247,500 Flow-Through Financing

Canadian Critical Minerals Inc. (TSXV: CCMI) (OTCQB: RIINF) ("CCMI" or the "Company") has closed a flow-through financing for gross proceeds of $247,500, comprised of 4,500,002 Flow-Through Shares with an issue price of $0.055 per share.

All securities issued are subject to a statutory hold period that expires four months and one day from issuance.

Keep reading...Show less

Ero Copper Announces Voting Results of Annual General Meeting of Shareholders

Ero Copper Corp. (TSX: ERO, NYSE: ERO) ("Ero" or the "Company") reported the voting results from its Annual General Meeting of Shareholders held today in Vancouver, British Columbia. A total of 93,474,205 common shares were represented at the meeting, being 90.96% of the issued and outstanding common shares of the Company as at the March 5, 2024 record date. Shareholders voted in favour of all items of business before the meeting, including the re-election of management's nominees as directors for the ensuing year and the advisory vote on executive compensation. Detailed results of the votes are presented below.

Each item of business voted upon at the meeting is described in detail in the Company's Management Information Circular dated March 7, 2024 (the "Circular"), which is available on the Company's website ( www.erocopper.com ), on SEDAR+(www.sedarplus.ca/landingpage/) and on EDGAR (www.sec.gov).

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Forum Energy Metals to Present at the Energy Transition Metals Summit in Washington, DC April 29 - 30, 2024

Forum Energy Metals to Present at the Energy Transition Metals Summit in Washington, DC April 29 - 30, 2024

Join Forum Energy Metals (TSXV: FMC) (OTCQB: FDCFF) at the Energy Transition Metals Summit being held at the Marriott Marquis in Washington, DC on Monday, April 29 and Tuesday, April 30. Forum President & CEO, Richard Mazur and Dr. Rebecca Hunter, Vice President of Exploration will be available both days of the conference for 1 X 1 meetings to update investors on Forum's high grade uranium discovery in the Thelon Basin, Nunavut.

Qualified buy side parties can register at:
https://www.precioussummit.com/event/2024-energy-transition-metals-summit-washington-d-c/

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Hudbay to Host Conference Call for First Quarter 2024 Results

Hudbay Minerals Inc. ("Hudbay" or the "company") ( TSX, NYSE: HBM) senior management will host a conference call on Tuesday, May 14, 2024 at 11:00 a.m. ET to discuss the company's first quarter 2024 results.

First Quarter 2024 Results Conference Call and Webcast
Date: Tuesday, May 14, 2024
Time: 11:00 a.m. ET
Webcast: www.hudbay.com
Dial in: 1-416-764-8650 or 1-888-664-6383
Additional Dial-in

Hudbay plans to issue a news release containing the first quarter 2024 results before market open on Tuesday, May 14, 2024 and post it on the company's website. An archived audio webcast will be available on Hudbay's website following the call.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Culpeo Minerals

Culpeo Commences Drilling at Lana Corina Where Intersections Included 257m @ 1.10% CuEq

Culpeo Minerals Limited (“Culpeo” or the “Company”) (ASX:CPO, OTCQB:CPORF) is pleased to advise extensional drilling has commenced at the Lana Corina Project (the Project), Chile, building on the achievements of the 2023 program.

Keep reading...Show less

Latest Press Releases

Related News

×