Manuka Resources

Restart of Mount Boppy Gold Mine - Execution Update

Manuka Resources Limited (“Manuka” or the “Company”) is pleased to provide a progress update on the restart of gold doré production from its 100% owned Mt Boppy gold mine (“Mt Boppy”) located in the Cobar Basin, NSW (Figure 1).


Highlights

  • Manuka is executing a strategy to construct a fit-for-purpose processing and gold doré production facility at its 100% owned Mt Boppy gold mine.
  • Previously, ore from Mt Boppy had been hauled to and processed at the Company’s CIL plant located at the Wonawinta Silver Mine (“Wonawinta”) 150km south of Mt Boppy.
  • Mt Boppy is forecast to be a low capex (A$11.6M), high margin (~A$19M EBITDA per annum) operation1.
  • Relocation of the existing 400kW ball mill located at Wonawinta to Mt Boppy has commenced. The ball mill is surplus to requirements at Wonawinta where a 1800kW ball mill has been previously installed.
  • Acquisition of a second-hand Inline Pressure Jig (IPJ) and Intensive Leach Reactor (ILR) has resulted in approximately A$850k savings versus that originally budgeted. The purchased equipment is currently undergoing refurbishment at Gekko Systems, the original equipment manufacturer.
  • The Company is currently investigating opportunities to increase milling capacity and accelerate gold production at Mt Boppy.
  • The Company is targeting first gold production from Mt Boppy in Q4 2024.

Dennis Karp, Manuka’s Executive Chairman, commented:

“The execution of our plan to restart gold operations at Mt Boppy is well underway.

The opportunistic purchasing of selected second-hand processing equipment is consistent with our low capex strategy that includes the leveraging and repurposing of existing assets including the Wonawinta 400kW ball mill, diesel generators, 48-man accommodation camp and mobile screening plant.

We look forward to providing regular updates to the markets as we progress towards first gold production at Mt Boppy.

Figure 1: Location of Manuka’s Mt Boppy and Wonawinta Project within the Cobar basin.

Background

The Mt Boppy gold mine is an existing gold operation comprising a brownfields open pit and associated historic ROM stockpiles, rock dumps and tailings.

In April 2024, Manuka announced a strategy whereby a fit-for-purpose processing and gold production facility would be established at Mt Boppy for a capital cost A$11.6M to generate an average EBITDA of ~A$19M per annum over an initial 5-year period2.

A sonic drilling program over the Main Rock Dump and Tailings Storage Facility 3 (“TSF3”) was completed in late 2023 which improved confidence in Resource3 grade and ore type distribution and underpins the updated production strategy.

Previously, ore mined by Manuka at Mt Boppy had been hauled 150km to the CIL process plant located at Wonawinta at a cost of ~A$27/t. The updated strategy of on- site processing is expected to save in the order of A$7M per annum.


Click here for the full ASX Release

This article includes content from Manuka Resources Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

MKR:AU
Manuka Resources Limited

Manuka Resources Limited Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Manuka Resources Limited

Manuka Resources Limited


Keep reading...Show less
Manuka Strengthens Balance Sheet with Additional $1 Million

Manuka Strengthens Balance Sheet with Additional $1 Million

Manuka Resources Limited (MKR:AU) has announced Manuka Strengthens Balance Sheet with Additional $1 Million

Download the PDF here.

Heliostar Files Technical Reports on Mines and Development Project Recently Acquired in Mexico

Heliostar Files Technical Reports on Mines and Development Project Recently Acquired in Mexico

Company Overview on La Colorada:

  • La Colorada Operations show US$25.9M NPV5, 11.9% IRR, US$53.9M CAPEX and 287k total ounces produced at a US$2,000/oz gold price
  • New mineral reserve at Junkyard Stockpile supports restart of mining at La Colorada that has commenced this month
  • El Crestón expansion at La Colorada is expected to produce over 50,000 ounces of gold per year
  • Current drill program (five drill rigs) is targeting lower CAPEX and increased production for updated technical report planned for mid-2025
Au Price
(US$/oz Au)
Net Cash Flow
(US$M)
After-Tax NPV
@ 5.0% Discount Rate
(US$M)
IRR
(%)
Payback Period
(years)
Payback Multiple
2,000 154.9225.9311.92.21.4
2,600 2158.32110.0334.71.42.3

 

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

B2Gold Announces Amended Shareholder Return Strategy, including New Dividend Framework and Intention to Implement a Normal Course Issuer Bid

B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX: B2G) ("B2Gold" or the "Company") announces amendments to its shareholder returns strategy to increase financial flexibility as it completes its current phase of organic growth, including the anticipated commencement of initial production from Fekola Regional in Mali, the completion of construction of the Goose Mine in Nunavut, Canada, the development of the Antelope deposit at the Otjikoto Mine in Namibia, and de-risking activities at the Gramalote Project in Colombia. All dollar figures are in United States dollars unless otherwise indicated.

New Dividend Framework

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

B2Gold Announces Amended Shareholder Return Strategy, including New Dividend Framework and Intention to Implement a Normal Course Issuer Bid

B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX: B2G) ("B2Gold" or the "Company") announces amendments to its shareholder returns strategy to increase financial flexibility as it completes its current phase of organic growth, including the anticipated commencement of initial production from Fekola Regional in Mali, the completion of construction of the Goose Mine in Nunavut, Canada, the development of the Antelope deposit at the Otjikoto Mine in Namibia, and de-risking activities at the Gramalote Project in Colombia. All dollar figures are in United States dollars unless otherwise indicated.

New Dividend Framework

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

B2Gold Announces Total Consolidated Gold Production for 2024 of 804,778 oz, Within the Revised 2024 Guidance Range; Total Gold Production for 2025 Anticipated to be Between 970,000 and 1,075,000 oz; Goose Project Remains On Track for First Gold in Q2 2025 and Total Capital Estimate Remains at C$1,540 Million

B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX: B2G) ("B2Gold" or the "Company") is pleased to announce its gold production and revenue results for the fourth quarter and full year 2024, as well as its 2025 total gold production guidance and 2025 cost guidance for its current operating mines. All dollar figures are in United States dollars unless otherwise indicated.

Q4 and Full Year 2024 Highlights

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Kinross to announce 2024 Q4/full-year results and 2025 guidance on February 12, 2025

Kinross Gold Corporation (TSX: K; NYSE: KGC) (the "Company") will release its 2024 fourth-quarter and full-year financial statements and operating results on Wednesday, February 12, 2025, after market close. The Company will also provide its full-year 2025 guidance, mineral reserve, and mineral resource statement as of December 31, 2024, and an exploration and project update. Kinross will hold a conference call and audio webcast on Thursday, February 13, 2025, at 8 a.m. ET to present the results, followed by a question-and-answer session.

The call-in numbers for the conference call on Thursday, February 13, 2025, at 8 a.m. ET are as follows:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Kinross to announce 2024 Q4/full-year results and 2025 guidance on February 12, 2025

Kinross Gold Corporation (TSX: K; NYSE: KGC) (the "Company") will release its 2024 fourth-quarter and full-year financial statements and operating results on Wednesday, February 12, 2025, after market close. The Company will also provide its full-year 2025 guidance, mineral reserve, and mineral resource statement as of December 31, 2024, and an exploration and project update. Kinross will hold a conference call and audio webcast on Thursday, February 13, 2025, at 8 a.m. ET to present the results, followed by a question-and-answer session.

The call-in numbers for the conference call on Thursday, February 13, 2025, at 8 a.m. ET are as follows:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Manuka Resources Limited

Manuka Resources Limited Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×