
August 11, 2024
Manuka Resources Limited (“Manuka” or the “Company”) is pleased to provide a progress update on the restart of gold doré production from its 100% owned Mt Boppy gold mine (“Mt Boppy”) located in the Cobar Basin, NSW (Figure 1).
Highlights
- Manuka is executing a strategy to construct a fit-for-purpose processing and gold doré production facility at its 100% owned Mt Boppy gold mine.
- Previously, ore from Mt Boppy had been hauled to and processed at the Company’s CIL plant located at the Wonawinta Silver Mine (“Wonawinta”) 150km south of Mt Boppy.
- Mt Boppy is forecast to be a low capex (A$11.6M), high margin (~A$19M EBITDA per annum) operation1.
- Relocation of the existing 400kW ball mill located at Wonawinta to Mt Boppy has commenced. The ball mill is surplus to requirements at Wonawinta where a 1800kW ball mill has been previously installed.
- Acquisition of a second-hand Inline Pressure Jig (IPJ) and Intensive Leach Reactor (ILR) has resulted in approximately A$850k savings versus that originally budgeted. The purchased equipment is currently undergoing refurbishment at Gekko Systems, the original equipment manufacturer.
- The Company is currently investigating opportunities to increase milling capacity and accelerate gold production at Mt Boppy.
- The Company is targeting first gold production from Mt Boppy in Q4 2024.
Dennis Karp, Manuka’s Executive Chairman, commented:
“The execution of our plan to restart gold operations at Mt Boppy is well underway.
The opportunistic purchasing of selected second-hand processing equipment is consistent with our low capex strategy that includes the leveraging and repurposing of existing assets including the Wonawinta 400kW ball mill, diesel generators, 48-man accommodation camp and mobile screening plant.
We look forward to providing regular updates to the markets as we progress towards first gold production at Mt Boppy.
Figure 1: Location of Manuka’s Mt Boppy and Wonawinta Project within the Cobar basin.
Background
The Mt Boppy gold mine is an existing gold operation comprising a brownfields open pit and associated historic ROM stockpiles, rock dumps and tailings.
In April 2024, Manuka announced a strategy whereby a fit-for-purpose processing and gold production facility would be established at Mt Boppy for a capital cost A$11.6M to generate an average EBITDA of ~A$19M per annum over an initial 5-year period2.
A sonic drilling program over the Main Rock Dump and Tailings Storage Facility 3 (“TSF3”) was completed in late 2023 which improved confidence in Resource3 grade and ore type distribution and underpins the updated production strategy.
Previously, ore mined by Manuka at Mt Boppy had been hauled 150km to the CIL process plant located at Wonawinta at a cost of ~A$27/t. The updated strategy of on- site processing is expected to save in the order of A$7M per annum.
Click here for the full ASX Release
This article includes content from Manuka Resources Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
MKR:AU
Sign up to get your FREE
Manuka Resources Investor Kit
and hear about exciting investment opportunities.
- Corporate info
- Insights
- Growth strategies
- Upcoming projects
GET YOUR FREE INVESTOR KIT
The Conversation (0)
26 March
Manuka Resources
Investor Insight
Manuka Resources’ unique value proposition is focused on its three fully licenced projects, which include two precious metals assets in one of Australia’s most prolific regions for base and precious metals, and a company-making iron sands (vanadium and titanium co-products) project in New Zealand’s exclusive economic zone (EEZ) off the Taranaki bight. Manuka Resources is well-placed to deliver significant shareholder value, driven by a phased strategy that includes a clear pathway to near-term precious metals production.
Strategy Overview
Manuka Resources (ASX:MKR) is focused on bringing its precious metals assets in the Cobar Basin into production, as well as progressing its New Zealand domiciled Taranaki VTM iron sands project.
The company previously revealed a phased strategy focused on delivering maximum value to its shareholders. The first phase focused on bringing back the Mt Boppy gold mine into production and it released an optimised production plan for the mine restart. At the time, the company believed silver production would follow gold but noted it was flexible in this regard. In any event and simultaneous to this, will be the ongoing development of the Taranaki vanadium titano-magnetite (VTM) project.
The Cobar Basin located in the central-west of New South Wales, is one of the richest mining provinces in Australia, home to some of Australia’s largest mining companies and explorers.
The Mt Boppy gold mine was historically one of the richest in NSW, Australia and produced ~500,000 oz gold at an average grade of 15 grams per ton (g/t) gold. Accordingly, the company is very excited about its exploration potential.
Drone image looking South showing the main components of the Rock Dump and tailing resources in relation to the Mt. Boppy open pit.
The initial five-year mine plan is largely focused on the screening and processing of gold-bearing waste material above ground on the Mt Boppy mine site. The company had been processing these wastes from June 2023 to December 2023 at its Wonawinta plant and now will look to optimize the process.
The Wonawinta silver project will be the largest primary silver producer in Australia and expected to be back in silver production within 12 months. Manuka has released a maiden ore reserve (under its ownership) of 4.8Mt1 at 53.8g/t silver containing 8.4Moz of silver comprising proven ore reserves of 0.8Mt at 50.8g/t silver; and probable ore reserves of 4.1Mt at 54.3g/t silver. Ore Reserve is based solely on shallow (<40m deep) oxide material.
The Wonawinta 100tph Ball Mill
The gold and silver market appears to be in an upward trend, with prices for both precious metals hitting their all-time highs recently, in Australian dollar terms for silver, which bodes very positively for MKR.
Company Highlights
- Manuka Resources is an ASX-listed mining company focused on producing gold and silver from its two 100 percent owned fully permitted projects (one gold and one silver) in the Cobar Basin in New South Wales, Australia.
- In addition, MKR’s wholly owned subsidiary Trans-Tasman Resources Limited (“TTR”) is the owner of the Taranaki VTM (vanadiferous titanomagnetite) iron sands project, located in the New Zealand EEZ, off the south-west coast of the north island.
- Manuka released the details of the Taranaki VTM project’s pre-feasibility study (PFS) on 26 March 2025, which highlights the extremely robust economics of the project with an NPV10 of US$1.2B and IRR 39 percent
- TTR will also be lodging its application under New Zealand’s Fast Track Approvals Act for the Taranaki VTM project imminently. (The project was included in Schedule 2 of the Act). Successful conclusion of review under the Fast Track pathway will result in final regulatory approvals (marine discharge consent) being granted, completing the full suite of consents to operate the project for 20 years.
- The Company’s primary focus for its precious metals assets is on bringing both the fully permitted Wonawinta silver project and the Mt Boppy gold mine back into production during 2025. The Wonawinta processing plant (primarily constructed for silver production in 2012 with production capacity of 850,000-1 million tpa) has been recently used for both gold and silver processing and is on active care and maintenance for rapid restart..
- The Wonawinta silver project was previously the largest primary producer of silver in Australia, and Manuka expects this to again be the case once production restarts.
- While the substantially higher gold prices have been securing headlines over the past six months, it is worth noting that the silver price is also trading at an all time high which makes restarting the project very attractive (the all time high for silver is against the Australian dollar, currently silver is around AU$54/oz silver).
- Manuka released its maiden silver reserve in October 2024 making it the only production ready silver reserve on a project based in Australia.
- Elevated gold and silver prices should materially benefit Manuka Resources, resulting in strong profitability and cash flows once its projects move into production.
Key Projects
Mt Boppy Gold Project
The Mt Boppy gold project comprises three mining leases, four gold leases and one exploration license, spanning an area of more than 210 sq km in the prolific Cobar Basin in New South Wales, Australia. The project was acquired by Manuka in 2019 and has a current mineral resource of 4.3 Mt at 1.19 g/t gold. This includes a combination of oxidized and transitional/fresh mineralization in the ground, as well as mineralized rock dumps and tailings.
Historically, Manuka Resources has processed its stockpiles and gold mineralized waste products through its Wonawinta processing plant. However, inefficiencies associated with trucking and processing ore at the distant Wonawinta plant has led the company to revise its strategy. It is now looking to construct a processing plant at Mt Boppy so that ore from the mine can be processed on-site. Mt Boppy has excellent infrastructure including a 48-person mine camp and is fully permitted for the proposed processing plant and on-site production.
The updated mineral resource comprises 4.28 Mt at 1.19 g/t gold for 163 koz of contained gold, of which 82 percent is in the measured and indicated categories.
An on-site plant will offer significant cost savings and improve the project economics.
Manuka Resources anticipates Mt Boppy to deliver total EBITDA of >AU$90 million and cash flow of >AU$80 million over a five-year mine life.
Wonawinta Silver Mine Project
The Wonawinta plant
The Wonawinta project is fully permitted with all the necessary infrastructure, including an 850,000 to 1 million tpa processing plant. The plant has been used for processing ore from Mt Boppy. The Wonawinta silver mine is currently under care and maintenance. The company is considering the possibility of resuming operations at Wonawinta, leveraging the improved silver price environment. Manuka has released a maiden ore reserve (under its ownership):
- Ore Reserve of 4.8 Mt at 53.8 g/t silver containing 8.4 Moz of silver comprising:
- Proved Ore Reserves of 0.8 Mt at 50.8 g/t silver; and
- Probable Ore Reserves of 4.1 Mt at 54.3 g/t Ag.
The maiden silver ore reserve and the preparation of an implementation plan for Wonawinta support the potential restart of silver mining and processing operations in the near
future. The company is reviewing its silver restart plans in light of the current price increases and expects to announce a decision before the end of May 2025.
Taranaki VTM Project
The Taranaki VTM project is located within New Zealand's exclusive economic zone, approximately 22 to 36 kilometres offshore, outside the 12 nautical mile boundary from the coastline. The project boasts a JORC resource of 3.2 billion tons at 10.17 percent iron oxide, 1.03 percent titanium dioxide and 0.05 percent vanadium oxide. It holds a mining license allowing initial extraction of 50 million tons annually, resulting in 5 million tons of VTM concentrate per year for 20 years (concentrate grade of 56 to 57 percent iron, 8.5 percent titanium dioxide and 0.5 percent vanadium pentoxide). At this extraction rate, the JORC resource provides approximately 60 years of potential mining inventory.
The project was included in the New Zealand government's Schedule 2 of the Fast Track Approvals Act 2024. The next step for Manuka was to complete pre-feasibility study (“PFS”) on the project. This was released to the market on 26 March 2025 and presents an extremely robust economic outlook for the project as can be seen below.
Management Team
Dennis Karp – Executive Chairman
Dennis Karp is a former commodities trader with nearly four decades of corporate experience. He started his career in 1983 and worked in HSBC until 1997 before moving to Tennant, one of Australia’s largest physical commodities trading companies with operations in Asia and Europe. He was a principal shareholder of Tennant Metals until 2010 and a managing director until December 2014. He founded ResCap in December 2014. Since then, he has participated in diverse resource projects and investment opportunities across base metals and bulk commodities. He holds a Bachelor of Commerce from the University of Cape Town.
Alan Eggers – Executive Director
Alan Eggers has over 40 years of experience in the mining sector. He is a geologist and was the founder of Summit Resources, which became an ASX top 200 company and was acquired by Paladin Energy in 2007 for AU$1.2 billion. Throughout his career, he has held director positions at numerous companies. He holds a Bachelor of Science, Honours, and Master of Science degrees from Victoria University of Wellington. He is recognized as a fellow of the Society of Economic Geologists and holds memberships in AusIMM and the Australian Institute of Geoscientists.
John Seton – Non-executive Director
John Seton is a lawyer with extensive experience in the mineral resources sector. He has served as director in several ASX and NZX listed companies. He holds a Bachelor of Laws from Victoria University, Wellington, and a Master of Law (Honours) from the University of Auckland and is a chartered fellow of the New Zealand Institute of Directors.
Haydn Lynch – Chief Operating Officer
Haydn Lynch has over 25 years of experience in M&A, capital markets and private equity. He has been involved in executing several domestic and cross-border transactions in various sectors including metals and mining, and industrials. He has held leadership roles in global investment banks, including Bankers Trust Australia, Investec Bank, RBC Capital Markets and Southern Cross Equities. He has undergraduate degrees in mechanical engineering and economics from the University of Queensland and a Master in Commerce from the University of New South Wales.
Dieter Engelhardt – Chief Metallurgist and General Manager
Dieter Engelhardt has over 30 years of experience in the mining industry including roles as senior metallurgist at Telfer Gold Mine and Northparkes Mines, resident manager at McKinnons Gold Mine, and manager of ore processing at CSA Mine. Engelhardt was employed by Newcrest Mining (now Newmont) in various roles, including as manager of ore processing and principal metallurgist.
Phil Bentley – Chief Geologist
Phil Bentley has over 40 years of experience in the mining industry across New Zealand, South Africa, and Australia, holding senior geological roles as well as senior management and director positions. He has worked as a chief geologist at Randgold Resources and Randgold & Exploration, Global Head of Exploration at Trafigura Mining Services, and Principal Geologist Africa at CSA Global South Africa. He is a Qualified person under NI 43-101 (Canada) and JORC (Australia) and is a Fellow of the South African Geological Society. He holds a Bachelor of Science (Honours) in Geology at Victoria University of Wellington. He also has a Masters of Science in Economic Geology at Victoria University of Wellington and a Master’s of Science in Mineral Exploration from Rhodes University, Grahamstown South Africa.
Keep reading...Show less
Near-term production from both its silver and gold projects located in the Cobar Basin, Central West, New South Wales
30 May
Taranaki VTM Continues to Progress Through Fast-track
15 May
Taranaki Project proceeds to next stage of NZ Fast-Track
30 April
March 2025 Quarter Activities and Cashflow Reports
16h
Brunswick Exploration Announces AGM Results
Brunswick Exploration Inc. (“BRW” or the “Corporation”) is pleased to announce the results of its annual general meeting (“AGM”) of shareholders held on June 12, 2025. Shareholders holding a total of 80,309,202 common shares of the Corporation attended the AGM in person or were represented by proxy, representing approximately 37 % of the 218,274,932 common shares issued and outstanding.
Pierre Colas, Jeffrey Hussey, André Le Bel, Amy Satov, Mathieu Savard and Robert Wares were re-elected to the board of directors.
The shareholders also (i) approved the re-appointed Raymond Chabot Grant Thornton LLP as auditors for the ensuing financial year, (ii) approved the deferred share unit plan (the “DSU Plan”) adopted by the Corporation’s board of directors on April 30, 2025, allowing for a maximum of 2,400,000 common shares to be awarded as deferred share units under the DSU Plan, and (iii) ratified, approved and confirmed the stock option plan, as amended by the Corporation’s board of directors on April 30, 2025, allowing for a maximum of 19,400,000 common shares to be subject to stock options under the stock option plan.
Collectively, the number of common shares reserved for issuance under all the Corporation’s security-based compensation plans, namely the stock option plan and the DSU Plan, represents less than 10% of the Corporation’s currently issued and outstanding common shares.
The adoption of the DSU Plan and the amendment to the stock option plan remain subject to final approval by the TSX Venture Exchange.
About Brunswick Exploration
Brunswick Exploration is a Montreal-based mineral exploration company focused on grassroots exploration for lithium in Canada, a critical metal necessary to global decarbonization and energy transition. The Corporation is rapidly advancing the most extensive grassroots lithium property portfolio in Canada and Greenland.
Investor Relations/information
Mr. Killian Charles, President and Chief Executive Officer (info@BRWexplo.com)
Cautionary Statement on Forward-Looking Information
This news release contains “forward-looking information” within the meaning of applicable Canadian securities legislation based on expectations, estimates and projections as at the date of this news release. Forward-looking information involves risks, uncertainties and other factors that could cause actual events, results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward-looking information. Factors that could cause actual results to differ materially from such forward-looking information include, but are not limited to, delays in obtaining or failures to obtain required governmental, environmental or other project approvals; uncertainties relating to the availability and costs of financing needed in the future; changes in equity markets; inflation; fluctuations in commodity prices; delays in the development of projects; the other risks involved in the mineral exploration and development industry; and those risks set out in the Corporation’s public documents filed on SEDAR+ at www.sedarplus.ca. Although the Corporation believes that the assumptions and factors used in preparing the forward-looking information in this news release are reasonable, undue reliance should not be placed on such information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all. The Corporation disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.
Click here to connect with Brunswick Exploration Inc. to receive an Investor PresentationKeep reading...Show less
12 June
Harvest Gold Identifies 15 Primary And 10 Secondary Targets For Its Diamond Drill Program At Its Mosseau Project In Quebec
Harvest Gold Corporation (TSXV: HVG) (“Harvest Gold ” or the “Company ”) is pleased to announce the finalization of drill targets for its planned diamond drill program at the Company’s Mosseau Project, located in the Urban-Barry Greenstone Belt of Quebec (Figure 1).
Rick Mark, President and CEO of Harvest Gold, states: “Our geological team has done a tremendous job in compiling and collating the many datasets from the historic work of many companies in the northern area of Mosseau. They also built a new database for the central area with Harvest Gold’s 2024 air and ground programs data, captured using today’s technologies, layered over the data from historic work done sporadically. Drill permits are secured and a drill contract for a 5,000-metre program is signed. We are ready to drill.”
The planned 5,000 metre diamond drill program will focus on testing near-surface gold targets in two key areas of the property, the northern and central areas. (Figure 2, Figure 3, Figure 4). Both of these areas host similar geological, geophysical and structural features:
The more known northern area hosts numerous gold showings that remain open along strike and at depth.
The central area, and particularly the Kiask River Mineralized Corridor, has seen very limited historical exploration and was the focus of Harvest’s 2024 field work.
The drill targets have been developed through a detailed review and integration of:
- Historical showings
- Previous exploration work, including Induced Polarization and geological mapping surveys
- High-resolution airborne magnetic surveys
- Prospecting and reconnaissance mapping
- Soil sampling program
These exploration efforts have highlighted fifteen high-priority targets that can host significant gold mineralization. The planned drill program will also be the first systematic testing of the central area of Mosseau and is the beginning of unlocking the mineral potential of the Mosseau Project.
Permits Secured from Quebec Government
Harvest Gold is pleased to report that it has received the required Authorization to Initiate (ATI) permits from the Quebec Government, allowing the Company to proceed with its upcoming drill program. The ATI permits cover the planned drill sites and associated activities for the next two years, ensuring the program is compliant with all regulatory requirements.
Drill Contract Awarded to Forage Rouillier
The Company is also pleased to announce that it has awarded the drill contract for the upcoming program to Forage Rouillier Drilling, based in Amos, Quebec. Forage Rouillier is a highly regarded, locally-based contractor with extensive experience drilling in the Abitibi region. Harvest Gold looks forward to working with Forage Rouillier to execute the program safely and efficiently.
About Harvest Gold Corporation
Harvest Gold is focused on exploring for near surface gold deposits and copper-gold porphyry deposits in politically stable mining jurisdictions. Harvest Gold’s board of directors, management team and technical advisors have collective geological and financing experience exceeding 400 years.
Harvest Gold has three active gold projects focused in the Urban Barry area, totalling 377 claims covering 20,016.87 ha, located approximately 45-70 km west of Gold Fields - Windfall Deposit (Figure 1).
Harvest Gold acknowledges that the Mosseau Gold Project straddles the Eeyou Istchee-James Bay and Abitibi territories. Harvest Gold is committed to developing positive and mutually beneficial relationships based on respect and transparency with local Indigenous communities.
Harvest Gold’s three properties, Mosseau, Urban-Barry and LaBelle, together cover over 50 km of favorable strike along mineralized shear zones.
Figure 1: Project Location: Urban-Barry Greenstone Belt
Figure 2: Drill targets in the northern part of the Mosseau property (Geology)
Figure 3: Drill targets in the central part of the Mosseau property (Geology)
Figure 4: Drill targets in the central part of the Mosseau property (Magnetics)
Qualified Person Statement
All scientific and technical information in this news release has been prepared and approved by Louis Martin, P.Geo., Technical Advisor to the Company and considered a Qualified Person for the purposes of NI 43-101.
ON BEHALF OF THE BOARD OF DIRECTORS
Rick Mark
President and CEO
Harvest Gold Corporation
For more information please contact:
Rick Mark or Jan Urata
@ 604.737.2303 or info@harvestgoldcorp.com
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Forward Looking Information
This news release includes certain statements that may be deemed "forward looking statements". All statements in this news release, other than statements of historical facts, that address events or developments that Harvest Gold expects to occur, are forward looking statements. Forward looking statements are statements that are not historical facts and are generally, but not always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates", "projects", "potential" and similar expressions, or that events or conditions "will", "would", "may", "could" or "should" occur.
Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results may differ materially from those in the forward-looking statements. Factors that could cause the actual results to differ materially from those in forward looking statements include market prices, exploitation and exploration successes, and continued availability of capital and financing, and general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. Forward looking statements are based on the beliefs, estimates and opinions of the Company’s management on the date the statements are made. Except as required by securities laws, the Company undertakes no obligation to update these forward-looking statements in the event that management's beliefs, estimates or opinions, or other factors, should change.
Keep reading...Show less
12 June
Radisson Announces Results of its Annual and Special Meeting of Shareholders
Radisson Mining Resources Inc. (TSXV: RDS) (OTCQB: RMRDF) ("Radisson" or the "Company) is pleased to announce the results of its Annual and Special Meeting of Shareholders ("AGM") held on June 12, 2025. Shareholders voted in favour of all items of business, including the election of each director nominee, the appointment of auditors, and the adoption of a new Omnibus Equity Incentive Plan. A total of 156,469,851 votes were represented in the meeting amounting to 45.22% of the Company's class A shares issued as of the record date. Directors re-elected to the board were Pierre Beaudoin, Lise Chénard, Michael Gentile, Peter MacPhail, Matt Manson, Jeff Swinoga and Cindy Valence. Subsequent to the AGM, Pierre Beaudoin was re-appointed as Chairperson of the Board of Directors.
New Omnibus Equity Incentive Plan
The new Omnibus Equity Incentive Plan (the "Omnibus Plan") replaces the Company's previous stock option plan and introduces a best-practice framework to attract and retain personnel through a broader range of equity-based awards.
Under the Omnibus Plan, a rolling 10% share reserve will apply to all awards, including stock-options ("Options"), restricted share units ("RSUs"), performance share units ("PSUs"), and deferred share units ("DSUs"). The total number of common shares reserved for issuance under the Omnibus Plan, at any time, will not exceed 10% of the Company's issued and outstanding common shares. All outstanding stock-options granted under the previous plan will continue under the Omnibus Plan, unless the new plan materially impairs the rights of existing holders, in which case the terms of the original plan will remain in effect.
A full copy and summary of the Omnibus Plan is available in the Company's management information circular dated May 7, 2025, which can be accessed under Radisson's profile at www.sedarplus.ca and on the Company's website at www.radissonmining.com.
Grant of Equity Incentives
Subsequent to the AGM, the Board of Directors authorized the grant of an aggregate of 2,739,014 stock-options, to directors, officers, employees and consultants of the Company. The Options have an exercise price of $0.425 per share, are exercisable for a period of five-years from the date of grant and will vest as follows: one-third on the date of grant, one-third on the first anniversary of the date of grant and one-third on the second anniversary.
In addition, the Board of Directors authorized the grant of an aggregate 966,416 RSUs to officers of the Company and 541,176 DSUs to independent directors of the Company. A total of 262,004 RSUs vest on the first anniversary of the date of grant. The balance of the RSUs vest as follows: one-third on the first anniversary of the date of grant, one-third on the second anniversary and one-third on the third anniversary. The Options, RSUs and DSUs were granted in accordance with the Omnibus Plan.
Radisson Mining Resources Inc.
Radisson is a gold exploration company focused on its 100% owned O'Brien Gold Project, located in the Bousquet-Cadillac mining camp along the world-renowned Larder-Lake-Cadillac Break in Abitibi, Québec. The Bousquet-Cadillac mining camp has produced over 25 million ounces of gold over the last 100 years. The Project hosts the former O'Brien Mine, considered to have been Québec's highest-grade gold producer during its production. Indicated Mineral Resources are estimated at 0.50 million ounces (1.52 million tonnes at 10.26 g/t Au), with additional Inferred Mineral Resources estimated at 0.45 million ounces (1.60 million tonnes at 8.66 g/t Au). Please see the NI 43-101 "Technical Report on the O'Brien Project, Northwestern Québec, Canada" effective March 2, 2023 and other filings made with Canadian securities regulatory authorities available at www.sedar.com for further details and assumptions relating to the O'Brien Gold Project.
For more information on Radisson, visit our website at www.radissonmining.com or contact:
Matt Manson
President and CEO
416.618.5885
mmanson@radissonmining.com
Kristina Pillon
Manager, Investor Relations
604.908.1695
kpillon@radissonmining.com
Forward-Looking Statements
This news release contains "forward-looking information" within the meaning of the applicable Canadian securities legislation that is based on expectations, estimates, projections, and interpretations as at the date of this news release. Forward-looking statements including, but are not limited to, statements with respect to the closing of the Offering, the planned and ongoing drilling, the significance of drill results, the ability to continue drilling, the impact of drilling on the definition of any resource, the ability to incorporate new drilling in an updated technical report and resource modelling, the Company's ability to grow the O'Brien project and the ability to convert inferred mineral resources to indicated mineral resources. Any statement that involves discussions with respect to predictions, expectations, interpretations, beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using phrases such as "expects", or "does not expect", "is expected", "interpreted", "management's view", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and phrases or stating that certain actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be achieved) are not statements of historical fact and may be forward-looking information and are intended to identify forward-looking information. Except for statements of historical fact relating to the Company, certain information contained herein constitutes forward-looking statements Forward-looking information is based on estimates of management of the Company, at the time it was made, involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the companies to be materially different from any future results, performance or achievements expressed or implied by such forward-looking information. Such factors include, among others, risks relating to the drill results at O'Brien; the significance of drill results; the ability of drill results to accurately predict mineralization; the ability of any material to be mined in a matter that is economic. Although the forward-looking information contained in this news release is based upon what management believes, or believed at the time, to be reasonable assumptions, the parties cannot assure shareholders and prospective purchasers of securities that actual results will be consistent with such forward-looking information, as there may be other factors that cause results not to be as anticipated, estimated or intended, and neither the Company nor any other person assumes responsibility for the accuracy and completeness of any such forward-looking information. The Company believes that this forward-looking information is based on reasonable assumptions, but no assurance can be given that these expectations will prove to be correct and such forward-looking statements included in this press release should not be unduly relied upon. The Company does not undertake, and assumes no obligation, to update or revise any such forward-looking statements or forward-looking information contained herein to reflect new events or circumstances, except as may be required by law. These statements speak only as of the date of this news release.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.
Keep reading...Show less
12 June
Western Australia Approves Aston Minerals and Torque Metals Merger
Aston Minerals (ASX:ASO) and Torque Metals (ASX:TOR)made a joint announcement on Tuesday (June 10) acknowledging that the Supreme Court of Western Australia has approved their proposed merger.
First announced in January, the deal will see Torque acquire all of Aston's fully paid ordinary shares.
Aston’s delisting from the ASX is underway, with trading suspended on May 29. The company applied for termination of official quotation and removal from the ASX on the day the merger got the green light.
Torque's Western Australia-based Paris gold project will be one of the combined company's main assets.
Significant progress has been made at Paris recently, with Torque sharing the discovery of a new zone of shallow gold mineralisation at the site. The company also reported additional high-grade results from a drill campaign.
In May, Paris received AU$144,500 from the Australian government’s Exploration Incentive Scheme. The company said at the time that the funds would be used for forthcoming drilling.
“The immediate focus is on further defining shallow gold lodes and advancing Torque's first mineral resource estimate and maiden gold exploration target,” said Torque Managing Director Cristian Moreno.
Together, Torque and Aston will have 1.75 million ounces in gold resources across their exploration projects, focusing on areas in the Western Australian Goldfields and in Ontario, Canada.
Gold remains a coveted asset in 2025, with a projected record high average annual price of US$3,210 per ounce.
The new company will be led by Moreno, who will take the role of managing director. The board will also include existing Torque director Evan Cranston and Aston director Tolga Kumova.
Don’t forget to follow us @INN_Australia for real-time updates!
Securities Disclosure: I, Gabrielle de la Cruz, hold no direct investment interest in any company mentioned in this article.
Keep reading...Show less
12 June
NevGold Extends Oxide Gold-Antimony Mineralization Over 1.7 Kilometers at Cadillac Valley Target: 2.28 g/t AuEq Over 30.5 Meters (1.29 g/t Au And 0.22% Antimony) Within 1.61 g/t AuEq Over 61.0 Meters (1.08 g/t Au And 0.12% Antimony)
NevGold Corp. (“NevGold” or the “Company”) (TSXV:NAU) (OTCQX:NAUFF) (Frankfurt:5E50) is pleased to announce additional oxide gold-antimony (“Antimony”, “Sb”) results extending mineralization over 1.7 kilometers at the Cadillac Valley target at its Limousine Butte Project (the “Project”, “Limo Butte”) in Nevada. The Company continues to unlock the substantial gold-antimony potential of the Project, highlighting its promising prospects for further exploration and development in Nevada, one of the world’s prolific mining jurisdictions.
Key Highlights
- Expands oxide gold-antimony mineralization at Cadillac Valley over 1.7 kilometers with results including
- LB119: 2.28 g/t AuEq* over 30.5 meters (1.29 g/t Au and 0.22% Sb), within 1.61 g/t AuEq* over 61.0 meters (1.08 g/t Au and 0.12% Sb)
- LB155: 1.01 g/t AuEq* over 36.6 meters (0.47 g/t Au and 0.12% Sb), within 0.77 g/t AuEq* over 59.5 meters (0.40 g/t Au and 0.08% Sb)
- LB141: 1.03 g/t AuEq* over 12.2 meters (0.57 g/t Au and 0.10% Sb), within 0.55 g/t AuEq* over 77.7 meters (0.41 g/t Au and 0.03% Sb)
- LIM-18: 0.86 g/t AuEq* over 22.9 meters (0.65 g/t Au and 0.05% Sb), within 0.38 g/t AuEq* over 74.7 meters (0.25 g/t Au and 0.03% Sb) in hole at the most northeast part of the Cadillac Valley target (Figure 1)
- *Gold equivalents (“AuEq”) are based on assumed metals prices of US$2,000/oz of gold and US$35,000 per tonne of antimony (~30% discount to current spot prices), and assumed metals recoveries of 85% for gold and 70% for antimony.
- Mineralization at Cadillac Valley now expands over 1.7 kilometers northeast to southwest, and over 400 meters laterally (Figure 1, Figure 2)
- Over 27 oxide gold-antimony holes have been released highlighting the consistent results across the two key advanced target areas at Limo Butte; 19 holes at Resurrection Ridge and 8 holes at Cadillac Valley (Figure 3)
- Metallurgical testwork program continues with over 100 kg bulk sample from the Project and NevGold core drilling; positive progress has been made and results are expected over the coming weeks
Limo Butte Planned 2025 Activities / Status Update
NevGold will continue its active exploration program at Limo Butte including:
- Evaluate the historical geological database with focus on gold and antimony (completed);
- Evaluate and re-analyze historical drilling with focus on gold and antimony (in progress, continues);
- Metallurgical testwork (in progress, results over coming weeks);
- 2025 drilling of gold-antimony targets (in planning phase).
Figure 1 – Limousine Butte Gold-Antimony Project with selected gold-antimony drillhole results from the Cadillac Valley Target. To view image please click here
Figure 2 – Limousine Butte Gold-Antimony Project long-section at Cadillac Valley, with selected gold-antimony drillhole results. Thin colored discs show Antimony (Sb ppm) in drilling, and wide colored discs show Gold (Au ppm) in drilling. To view image please click here
Figure 3 – Limousine Butte Gold-Antimony Project with selected gold-antimony drillhole results at Resurrection Ridge and Cadillac Valley. The total strike length between Resurrection Ridge and Cadillac Valley is +5km.
To view image please click here
NevGold CEO, Brandon Bonifacio, comments: “The recent set of oxide gold-antimony results from Cadillac Valley significantly increases the size of the mineralization footprint at the target, which now extends over 1.7 kilometers northeast to southwest, and over 400 meters laterally. It is extremely encouraging to see the consistent hole thickness and oxide gold-antimony grades at both of our advanced target areas. We are focused on advancing both Resurrection Ridge and Cadillac Valley to the Mineral Resource Estimate (“MRE”) stage in 2025. We have also progressed our gold and antimony metallurgical testwork program, which is advancing with Kappes, Cassiday, and Associates (“KCA”) of Reno, Nevada, and we are expecting results over the coming weeks. We strongly believe we have one of the most advanced gold-antimony assets in the United States, and we will continue to focus on unlocking the value at the Project over 2025.”
Historical and Re-Assayed Drill Results
Hole ID | Length, m* | g/t Au | % Sb | g/t AuEq** | From, m | To, m |
Cadillac Valley | ||||||
LB119 | 61.0 | 1.08 | 0.12% | 1.61 | 146.3 | 207.3 |
including | 30.5 | 1.29 | 0.22% | 2.28 | 152.4 | 182.9 |
LB155 | 59.5 | 0.40 | 0.08% | 0.77 | 97.5 | 157.0 |
including | 36.6 | 0.47 | 0.12% | 1.01 | 97.5 | 134.1 |
LB141 | 77.7 | 0.41 | 0.03% | 0.55 | 61.0 | 138.7 |
including | 12.2 | 0.57 | 0.10% | 1.03 | 61.0 | 73.2 |
LIM-18 | 74.7 | 0.25 | 0.03% | 0.38 | 129.5 | 204.2 |
including | 22.9 | 0.65 | 0.05% | 0.86 | 129.5 | 152.4 |
LB22-007*** | 169.2 | 0.89 | 0.18% | 1.70 | 213.5 | 382.7 |
including | 54.4 | 2.26 | 0.13% | 2.85 | 213.5 | 267.9 |
also including | 3.10 | 0.76 | 2.76% | 13.15 | 259.2 | 267.9 |
LB22-006*** | 124.7 | 0.84 | 0.11% | 1.34 | 127.4 | 252.1 |
including | 24.3 | 1.32 | 0.20% | 2.23 | 160.6 | 184.9 |
LB22-019*** | 28.9 | 1.09 | 0.04% | 1.27 | 170.7 | 199.6 |
LB054*** | 12.2 | 0.42 | 0.08% | 0.79 | 12.2 | 24.4 |
*Downhole thickness reported; true width varies depending on drill hole dip and is ~70% to ~90% of downhole thickness.
**The gold equivalents (“AuEq”) are based on assumed metals prices of US$2,000/oz of gold and US$35,000 per tonne of antimony (~30% discount to current spot prices), and assumed metals recoveries of 85% for gold and 70% for antimony.
***Selected drillholes released in previous News Release on April 10, 2025.
Limo Butte Geology & Antimony Summary
A review of historical geochemical and drilling data at the Limousine Butte Project has identified multiple areas with strong gold-antimony potential. These zones correlate closely with outcrops of the Devonian Pilot Shale, the primary host rock for Carlin-type gold mineralization in the area. Positive gold grade at Limousine Butte is typically associated with silicification and the formation of jasperoid breccias within the Pilot Shale, an alteration feature also observed in the positive antimony results.
Through the Project data review, the Company uncovered reports detailing two small-scale historic mining operations at the Nevada Antimony Mine and Lage Antimony Prospect within the Limo Butte Project boundary. The Nevada Antimony Mine featured two prospect pits that extracted stibnite (formula: Sb2S3) from a hydrothermal breccia. The Lage Antimony Prospect reported historical unverified sampling results with up to 14.46% Antimony with additional prospect pits extracting antimony.
Historical geochemical rock chip sampling within the past-producing Golden Butte pit from a Brigham Young University (“BYU”) Thesis study produced numerous results that exceeded 1% antimony in jasperoid breccias (see Figure 1). Several results were greater than 5% antimony, including a sample of 9.6% antimony with visible stibnite and stibiconite. BYU Thesis Report
Figure 4 – Limousine Butte Project with historical antimony in rock chips and soils. The total strike length between Resurrection Ridge and Cadillac Valley is +5km. To view image please click here
US Executive Order – Announced March 20, 2025
The Company is pleased to report the recent, sweeping Executive Order to strengthen American mineral production and reduce U.S. reliance on foreign nations for its mineral supply. Antimony (Sb) has been identified as an important “Critical Mineral” in the United States essential for national security, clean energy, and technology applications, yet no domestically mined supply currently exists.
The Executive Order invokes the use of the Defense Production Act as part of a broad United States (“US”) Government effort to expand domestic minerals production on national security grounds. As it relates to project permitting, the Order states that it will "identify priority projects that can be immediately approved or for which permits can be immediately issued, and take all necessary or appropriate actions…to expedite and issue the relevant permits or approvals." Furthermore, the Order includes provisions to accelerate access to private and public capital for domestic projects, including the creation of a "dedicated mineral and mineral production fund for domestic investments" under the Development Finance Corporation ("DFC").
This decisive action by the US Government highlights the urgent need to expand domestic minerals output to support supply chain security in the United States. This important Order will help revitalize domestic mineral production by improving the permitting process and providing financial support to qualifying domestic projects.
Importance of Antimony
Antimony is considered a “Critical Mineral” by the United States based on the U.S. Geological Survey’s 2022 list (U.S.G.S. (2022)). “Critical Minerals” are metals and non-metals essential to the economy and national security. Antimony is utilized in all manners of military applications, including the manufacturing of armor piercing bullets, night vision goggles, infrared sensors, precision optics, laser sighting, explosive formulations, hardened lead for bullets and shrapnel, ammunition primers, tracer ammunition, nuclear weapons and production, tritium production, flares, military clothing, and communication equipment. Other uses include technology (semi-conductors, circuit boards, electric switches, fluorescent lighting, high quality clear glass and lithium-ion batteries) and clean-energy storage.
Globally, approximately 90% of the world’s current antimony supply is produced by China, Russia, and Tajikistan. Beginning on September 15, 2024, China, which is responsible for nearly half of all global mined antimony output and dominates global refinement and processing, announced that it will restrict antimony exports. In December-2024, China explicitly restricted antimony exports to the United States citing its dual military and civilian uses, which further exacerbated global supply chain concerns. (Lv, A. and Munroe, T. (2024)) The U.S. Department of Defense (“DOD”) has designated antimony as a “Critical Mineral” due to its importance in national security, and governments are now prioritizing domestic production to mitigate supply chain disruptions. Projects exploring antimony sources in North America play a key role in addressing these challenges.
Perpetua Resources Corp. (“Perpetua”, NASDAQ:PPTA, TSX:PPTA) has the most advanced domestic gold-antimony project in the United States. Perpetua’s project, known as Stibnite, is located in Idaho approximately 130 km northeast of NevGold’s Nutmeg Mountain and Zeus projects. Positive advancements at Stibnite including the technical development and permitting has led to US$75 million in Department of Defense (“DOD”) awards, and over $1.8 billion in indicative financing from the Export Import Bank of the United States (“US EXIM”) (see Perpetua Resources News Release from April 8, 2024) (Perpetua Resources. (2025))
Drillhole Orientation Details
Hole ID | Target Zone | Easting | Northing | Elevation (m) | Length (m) | Azimuth | Dip |
LB119 | CV | 665171 | 4415453 | 2026 | 269.7 | 130 | -75 |
LB155 | CV | 664635 | 4414684 | 2058 | 304.8 | 0 | -90 |
LB-141 | CV | 664995 | 4415167 | 2020 | 163.1 | 120 | -70 |
LIM-18 | CV | 665421 | 4415694 | 2034 | 219.5 | 0 | -90 |
LB22-007 | CV | 665211 | 4415453 | 2031 | 403.5 | 254 | -86 |
LB22-006 | CV | 664692 | 4414921 | 2042 | 379.8 | 144 | -77 |
LB22-019 | CV | 664433 | 4414318 | 2096 | 335.3 | 116 | -66 |
LB054 | CV | 665323 | 4415090 | 2059 | 157.0 | 0 | -90 |
Figure 5 – Limousine Butte Land Holdings and District Exploration Activity To view image please click here
Grant of Options
The Company also announces that it has granted an aggregate of 2,600,000 stock options of the Company (each, a “Stock Option”) to certain directors, officers and consultants of the Company. Each Stock Option entitles the holder to acquire one common share of the Company at an exercise price of $0.33 per share at varying expiry dates between June 12, 2027 and June 12, 2030. The Stock Options were issued pursuant to the terms of the Company’s stock option plan. The Stock Options granted to directors, officers, and consultants of the Company vest immediately, and the Stock Options granted to investor relations service providers vest in the amount of 25% every three months following the date of grant over a 12-month period.
ON BEHALF OF THE BOARD
“Signed”
Brandon Bonifacio, President & CEO
For further information, please contact Brandon Bonifacio at bbonifacio@nev-gold.com, call 604-337-4997, or visit our website at www.nev-gold.com.
Historical Data Validation
NevGold QA/QC protocols are followed on the Project and include insertion of duplicate, blank and standard samples in all drill holes. A 30g gold fire assay and multi-elemental analysis ICP-OES method was completed by ISO 17025 certified American Assay Labs, Reno.
The Company’s Qualified Person (“QP”), Greg French, Vice President, Exploration has completed a review of the historical data in this press release. The historic data collection chain of custody procedures and analytical results by previous operators appear adequate and were completed to industry standard practices. For the Newmont and US Gold data a 30g gold fire assay and multi-elemental analysis ICP-OES method MS-41 was completed by ISO 17025 certified ALS Chemex, Reno or Elko Nevada.
Geochemical ICP (5g) analysis for the Wilson, Christianson and Tingey report was completed by Geochemical Services Inc. and the XRF analyses (glass disk or pellets) by Brigham Young University.
Technical information contained in this news release has been reviewed and approved by Greg French, CPG, the Company’s Vice President, Exploration, who is NevGold’s Qualified Person under National Instrument 43-101 and responsible for technical matters of this release.
About the Company
NevGold is an exploration and development company targeting large-scale mineral systems in the proven districts of Nevada and Idaho. NevGold owns a 100% interest in the Limousine Butte and Cedar Wash gold projects in Nevada, and the Nutmeg Mountain gold project and Zeus copper project in Idaho.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Cautionary Note Regarding Forward Looking Statements
This news release contains forward-looking statements that are based on the Company’s current expectations and estimates. Forward-looking statements are frequently characterized by words such as “plan”, “expect”, “project”, “intend”, “believe”, “anticipate”, “estimate”, “suggest”, “indicate” and other similar words or statements that certain events or conditions “may” or “will” occur. Forward-looking statements include, but are not limited to, the proposed work programs at Limousine Butte, and the exploration potential at Limousine Butte. Such forward-looking statements involve known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results implied or expressed in such forward-looking statements. Such risks include, but are not limited to, general economic, market and business conditions, and the ability to obtain all necessary regulatory approvals. There is some risk that the forward-looking statements will not prove to be accurate, that the management’s assumptions may not be correct or that actual results may differ materially from such forward-looking statements. Accordingly, readers should not place undue reliance on the forward-looking statements. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.
Keep reading...Show less
12 June
Drilling continues to return significant high-grade mineralisation
Wia Gold Limited (ASX: WIA) (Wia or the Company) is pleased to report further positive assay results for thirty-six (36) Reverse Circulation (RC) drillholes and nine (9) diamond drillholes (DD), totalling 9,349 metres, aiming to upgrade inferred resources and support resource growth at the 2.12Moz1 Kokoseb Gold Project (Kokoseb) in Namibia.
Highlights:
- Deep diamond drilling successfully returns high-grade gold mineralisation under the MRE pit shell, including:
- 26m at 7.90 g/t Au from 444.0m, including 13.3m at 13.39 g/t Au in KDD055
- 10.5m at 16.72 g/t Au from 427.5m, including 2.0m at 84.68 g/t Au in KDD059
- Shallow Reverse circulation (RC) drilling at Central Zone near KRC3312 positively extends this high-grade shoot with significant intercepts, including:
- 16m at 2.96 g/t Au from 198m, including 6m at 6.18 g/t Au in KRC389
- 28m at 3.44 g/t Au from 192m, including 8m at 8.40 g/t Au in KRC396
- Infill drilling for shallow resource conversion at NW and Northern Zones confirm the strong continuity in gold mineralisation, including the following intercepts:
- 21m at 1.50 g/t Au from 82.9m in KDD062
- 23m at 1.69 g/t Au from 208.0m in KDD063
- 45m at 1.13 g/t Au from 66m in KRC371
- 28m at 1.06 g/t Au from 127m in KRC373
- 20m at 1.13 g/t Au from 51m in KRC375
- None of the drilling results of the high-grade zone beneath the pit shell, the high-grade shoot (both in the Central Zone), or infill drilling at NW or Northern Zones, are included in the current Mineral Resource Estimate (MRE) – an updated MRE is expected in the coming weeks
- Drilling continues with one RC rig and three DD rigs at Kokoseb
Commenting on the results, Wia Executive Chairman, Josef El-Raghy, said:
“Kokoseb continues to show consistency in gold mineralisation at depth and along strike, with some excellent results from within and outside of the current pit shell outline. The accelerated drilling programme, with three DD rigs targeting the high-grade shoots at depth, and one RC rig focussing on infill drilling to improve our understanding of the current 2.12m oz Au resource, is bearing fruit with results to be included in the updated MRE due in the next few weeks.”
Figure 1 – Drill hole locations, focused at the northern area of Kokoseb, location of the cross sections of this announcement, and significant intercepts on drill holes reported in this announcement3 (DD drillholes purple background, RC drillholes white background)
Click here for the full ASX Release
This article includes content from WIA Gold, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Keep reading...Show less
Latest News
Sign up to get your FREE
Manuka Resources Investor Kit
and hear about exciting investment opportunities.
- Corporate info
- Insights
- Growth strategies
- Upcoming projects
GET YOUR FREE INVESTOR KIT
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00