GoviEx Provides Annual Letter to Stakeholders

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx" or "Company") today provides a letter to stakeholders from the Executive Chairman, Govind Friedland and the Chief Executive Officer, Daniel Major.

To Our Fellow Stakeholders,

We enter 2022 following yet another unprecedented year. Whilst still adapting to a global pandemic, we are all, more than ever, faced with the reality of climate change and its devastating impact. COP26 has come and gone whilst governments remain unsure how to tackle the climate crisis. With increased energy prices and shortened supply of economically available low carbon energy sources, nuclear energy is coming into increased focus as a key part of the solution.

Despite all of its challenges, 2021 provided GoviEx with increased clarity and opportunity to execute our long-term strategy. With uranium prices improving, we can take greater confidence on our path to become a uranium producer.

Uranium prices rose 39% in 2021, trading at just under $46 per pound today.(1)Higher demand from new market participants has contributed to increases in spot prices, as the Sprott Physical Uranium Trust ("SPUT") alone now owns nearly 43 million pounds of uranium(1), which is approximately a third of the global annual supply. Whilst SPUT and other financial investors have helped to accelerate the increase in spot prices, the long-term fundamentals remain self-evident. Every year, more uranium is consumed than produced, and higher incentive prices are required to support new supply.

The recent crisis in Kazahkstan has highlighted the potential risk to output especially given the concentration of supply and this underlines the need for increased regional diversification that GoviEx's projects can provide.

Demand for uranium is forecast to increase as China looks to reduce its dependency on coal by pledging to build 150 new nuclear reactors by 2060. Nuclear power may be included in the EU's Sustainable Taxonomy Regulation and this could impact the industry by bringing investment towards nuclear, which is already Europe's largest single source of low carbon energy and forecast to grow.

The outlook for uranium has become increasingly positive and we have worked diligently to position ourselves to take full advantage as a new entrant to the market. In April we updated our pre-feasibility study for our flagship Madaouela project in Niger ("Madaouela"), reducing capex by 15% and opex by 20% in the first few years of mining.(2) Madaouela is fully permitted, benefits from well-established local infrastructure in a jurisdiction with a nearly a 50-year history of uranium exports. We are currently on track to finish our feasibility study by mid-2022 with a target to start construction in 2023 with first commercial uranium production in 2025.

In order to develop an optimum financing solution for Madaouela, last September we appointed Endeavour Financial, which is providing us with support on debt advisory, offtake finance and technical and environmental guidance. Endeavour Financial's track record in mine financing speaks for itself and their decision to work with GoviEx underlines the quality of Madaouela.

Whilst the development of Madaouela is our main focus for 2022, we also have two very promising assets which set us apart from other companies. The mine-permitted Mutanga project in Zambia is forecast to start production in 2027 and could be the lowest capital intensive uranium project in Africa.(3) In 2021 the team completed an initial infill drilling campaign at the Dibwe East deposit with positive results as we work towards upgrading mineral resources from an inferred to an indicated category. During 2022 we plan to complete infill drilling of the resource at Dibwe East as well as to upgrade the previously completed process test work to a feasibility study level of confidence.

Our Falea project in Mali remains a fascinating exploration project with great potential. It currently contains an indicated resource of 17.4Mlb U3O8, 24.4 Mlb copper and 16.1 Mlb silver, and an inferred resource of 13.4Mlb U3O8, also with copper and silver mineralization.(4) Work completed in 2021 has highlighted a number of geophysical exploration targets associated with the same structures that control the current mineral resources, but with the addition of gold mineralization. We look forward to drilling these Falea targets in 2022.

In 2021, we further strengthened our Board and management team by bringing in two additional directors; Salma Seetaroo and Erik Kraft, and appointing Chris Lewis as our Chief Uranium Marketing to spearhead our commercial offtake sales.

In 2021 we continued to deliver on our ESG strategy for the benefit of all our stakeholders. As we transition to becoming a producer, expanding our ESG mindset presents us with an opportunity to build an operation that can deliver economically as well as socially and environmentally. As our ESG plans develop, we seek compliance with a number of reporting standards, including IFC and ISO.

In summary, we believe GoviEx is in an excellent position to benefit from a strengthening uranium market. We have two mine permitted projects and an exciting exploration play. We have a plan in place to potentially become a producer in 2025, and a strong Board and management team ready to deliver on that plan. And finally we have you, our stakeholders, to support us on this journey.

We are truly grateful for the work completed by our teams in Niger, Zambia and Mali, and for the continuous support from the neighboring communities and all levels of government in these countries.

On behalf of management and the Board, thank you for your support. We appreciate your confidence in our 2021 accomplishments and our long-term strategy going forward and look to the future with confidence.

Sincerely, Govind Friedland & Daniel Major

Qualified Person
The scientific and technical information in this release has been reviewed and approved by Dr. Rob Bowell, a chartered chemist of the Royal Society of Chemistry, a chartered geologist of the Geological Society of London, and a Fellow of the Institute of Mining, Metallurgy and Materials, who is an independent Qualified Person under the terms of NI 43-101 for uranium deposits. Mr. Bowell has verified the data disclosed in this news release.
Notes:
(1) As at 11 January 2022
(2) See the technical report titled, "An Updated Integrated Development Plan for the Madaouela Project, Niger" has an effective date of August 11, 2015, and a revision date of August 20, 2015, that is available at GoviEx's profile on SEDAR at www.sedar.com.
(3) See the technical report titled, "NI 43-101 Technical Report on a Preliminary Economic Assessment of the Mutanga Uranium Project in Zambia", dated November 30, 2017 (the "PEA"). The PEA was prepared by Qualified Persons from SRK Consulting (UK) Limited.
The PEA is considered preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. Mineral Resources that are not Mineral Reserves have not yet demonstrated economic viability. Due to the uncertainty that may be attached to Inferred Mineral Resources, it cannot be assumed that all, or any part of an Inferred Mineral Resource, will be upgraded to an Indicated or Measured Mineral Resource as a result of continued exploration or Mineral Reserves once economic considerations are applied; therefore, there is no certainty that the production profile concluded in the PEA will be realized.

(4) See the technical report titled, "Technical Report on the Falea Uranium, Silver and Copper Deposit, Mali, West Africa" prepared by Roscoe Postle Associates Inc. for Denison Mines Corp., October 26, 2015.

Neither the TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

About GoviEx Uranium Inc.
GoviEx is a mineral resource company focused on the exploration and development of uranium properties in Africa. GoviEx's principal objective is to become a significant uranium producer through the continued exploration and development of its flagship mine-permitted Madaouela Project in Niger, its mine-permitted Mutanga Project in Zambia, and its multi-element Falea Project in Mali.

Contact Information
Isabel Vilela
Head of Investor Relations and Corporate Communications
Tel: +1-604-681-5529
Email: info@goviex.com
Web: www.goviex.com

Cautionary Statement Regarding Forward-Looking Statements
This news release may contain forward-looking information within the meaning of applicable securities laws. All information and statements other than statements of current or historical facts contained in this news release are forward-looking information.

Forward-looking statements are subject to various risks and uncertainties concerning the specific factors disclosed here and elsewhere in GoviEx's periodic filings with Canadian securities regulators. When used in this news release, words such as "will", "could", "plan", "estimate", "expect", "intend", "may", "potential", "should," and similar expressions, are forward-looking statements. Information provided in this document is necessarily summarized and may not contain all available material information.

Forward-looking statements include those related to: (i) the Company's ability to publish the feasibility study on the Madaouela Project by mid-2022; (ii) the method and timing of any exploration, development and/or mining operations at any of GoviEx's projects; (iii) the potential of upgrading mineral resources at GoviEx's Mutanga project from an inferred to an indicated category; and (iv) GoviEx's ability to benefit from a strengthening uranium market.

Although the Company believes the expectations reflected in such forward-looking statements are based on reasonable assumptions, it can give no assurances that its expectations will be achieved. Such assumptions, which may prove incorrect, include the following: (i) that the Company will be successful in its exploration and development plans for all its projects; (ii) that projected low capital expenditures for the mine-permitted projects will remain unchanged or improve; (iii) that the planned exploration and development programs on GoviEx's projects will be completed as planned and meet GoviEx's objectives; (iv) that the Company will be able to complete its planned ESG work as planned ;and (v) that the price of uranium will remain sufficiently high and the costs of advancing the Company's projects will remain sufficiently low so as to permit GoviEx to implement its business plans in a profitable manner.

Factors that could cause actual results to differ materially from expectations include (i) the inability of the Company to successfully complete the exploration and development plans; (ii) potential delays due to COVID-19 restrictions; (iii) the failure of the Company's projects, for technical, logistical, labour-relations, or other reasons; (iv) a decrease in the price of uranium below what is necessary to sustain the Company's operations; (v) an increase in the Company's operating costs above what is necessary to sustain its operations; (vi) accidents, labour disputes, or the materialization of similar risks; (vii) a deterioration in capital market conditions that prevents the Company from raising the funds it requires on a timely basis; and (viii) generally, the Company's inability to develop and implement a successful business plan for any reason.

In addition, the factors described or referred to in the section entitled "Risks Factors" in the MD&A for the year ended December 31, 2020, of GoviEx, which is available on the SEDAR website at www.sedar.com, should be reviewed in conjunction with the information found in this news release.

Although GoviEx has attempted to identify important factors that could cause actual results, performance, or achievements to differ materially from those contained in the forward-looking statements, there can be other factors that cause results, performance, or achievements not to be as anticipated, estimated, or intended. There can be no assurance that such information will prove to be accurate or that management's expectations or estimates of future developments, circumstances, or results will materialize. As a result of these risks and uncertainties, no assurance can be given that any events anticipated by the forward-looking information in this news release will transpire or occur, or, if any of them do so, what benefits that GoviEx will derive therefrom. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements in this news release are made as of the date of this news release, and GoviEx disclaims any intention or obligation to update or revise such information, except as required by applicable law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/109887

News Provided by Newsfile via QuoteMedia

GXU:CA,GVXXF
The Conversation (0)
GoviEx Uranium Statement on Recent Coup in Niger

GoviEx Uranium Statement on Recent Coup in Niger

In light of the recent coup d'état in Niger, GoviEx Uranium Inc. (TSXV: GXU) (OTCQB: GVXXF) wishes to assure its stakeholders, partners, and the people of Niger of the following:

GoviEx's operations in Niger remain unaffected by the current situation. We are committed to ensuring that our activities continue as normal, both at our Project site and our office in Niamey.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GoviEx Announces Substantial Increase of Open-Pit Mineral Resources at Its 100% Owned Muntanga Uranium Project in Zambia

GoviEx Announces Substantial Increase of Open-Pit Mineral Resources at Its 100% Owned Muntanga Uranium Project in Zambia

  • Measured & Indicated resources nearly tripled, now representing 74% from 29% of total resources.
  • Total in-pit constrained resources increased 18%.
  • Grade improvement in all mineral categories.
  • Current drilling targeting further potential in pit resource upgrade to measured and/or indicated.
  • Results fully support continued feasibility study.

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx or the "Company") is pleased to announce an updated Mineral Resource Estimate ("MRE") for its wholly owned, mine permitted Muntanga Uranium Project in Zambia (the "Muntanga Project"). The Muntanga Project consists of three mining permits that cover some 720km2, and contains five deposits: Dibbwi, Dibbwi East, Muntanga, Gwabi and Njame.

Daniel Major, CEO of GoviEx commented: "Our drilling campaigns in 2021 and 2022 have led to a significant update in the Muntanga mineral resource estimate. This progress is characterized by a notable growth in in-pit resources, a substantial conversion of inferred resources into the Indicated category, and an overall rise in uranium grades. What's more exciting is that this upward trajectory in resource growth persists even under lower uranium prices, such as the USD50/lb used in our Preliminary Economic Assessment( PEA)1. There is also additional potential for further upgrading of inferred resources, thereby expanding the resources that can be included in the feasibility study. These are very promising results and will be integrated into our ongoing feasibility study."

The 2023 updated MRE is the result of extensive infill drilling, including 8,010 metres drilled in 2021 and a further 19,990 metres drilling in 2022, predominately on the Dibbwi East deposit, to further delineate the deposit and convert inferred resources to the indicated category. The mineral resource update included a comprehensive reassessment of previous work and a revised correlation between down-hole radiometric probe data and chemical assays used to convert down-hole radiometric data into equivalent uranium grades (eU3O8) for mineral resource estimation.

Table 1.0 Comparison between 2017 & 2023 Constrained Mineral Resource Estimates

Constrained Mineral Resource Constrained Mineral Resource % Change
20172023
Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb) Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb) Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb)
Measured & Indicated 16.1735312.5942.5935933.7163%2%168%
Inferred 38.8229425.1614.9533010.88-61%12%-57%

 

Based on the USD50/lb U3O8, used to define the mining schedule in the 2017 PEA, constrained total pit resources are 36.5 Mlb eU3O8, comprising 34 Mt at 374 ppm eU3O8 for 28.4 Mlb in measured and indicated and 11 Mt at 348 ppm eU3O8 for8.1 Mlb of inferred, highlighting the robustness of the mineral resources at Muntanga. With the quality of the resource estimate improved, higher M&I, higher grade and a notable increase in estimated resources within the constrained open-pit area, we are optimistic that the updated MRE will be favourable to the project economics previously estimated for Muntanga in the PEA, and especially as the ongoing drilling is targeting conversion of more inferred resources into indicated resources.

As per the regulations applicable in 2017 when the Company released its NI 43-101 Technical Report1, the MRE reported did not need to be constrained by pit shells based on any particular uranium price, as almost all mineralisation at the time occurred within 125 m of surface with uranium grades that were, in general, considered to have a reasonable prospect for eventual economic extraction ("RPEEE") by open pit mining. The cut-off grade used for reporting the 2017 MRE was 100 ppm eU3O8.

The 2023 MRE is disclosed including an additional constraint applied to comply with the RPEEE and is accordingly reported within a constraining open-pit shell based on a uranium selling price of USD70/lb U3O8 and a 100 ppm eU3O8 cut-off grade. The updated 2023 MRE is presented in Table 3.0.

To facilitate a comparison between the 2023 and 2017 MRE, Table 2.0 below provides an assessment on the impact of a constraining open-pit shell based on uranium selling price of USD70/lb U3O8 and a 100 ppm eU3O8 cut-off grade on the 2017 MRE.

Table 2.0 Comparison of 2017 unconstrained and constrained mineral resources

Unconstrained Mineral Resource
2017
Constrained Mineral Resource
2017
Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb) Tonnes (Mt)eU3O8 Grade (ppm)eU3O8 (Mlb)
Measured & Indicated21.631815.116.235312.6
Inferred74.627344.938.829425.2

 

The 2017 constrained mineral resources are based on a fixed uranium price, and should uranium prices increase, a conversion of additional material into a constrained mineral resource would be anticipated.

Based on the drilling completed in 2021 and 2022, an updated mineral resource estimate has been prepared by SRK Consulting (Canada) Inc. ("SRK"). The Mineral Resource is that portion of the resource estimate which has been constrained within an open-pit shell, considering reasonable mining, processing and general and administrative cost, geotechnical parameters and processing recoveries. SRK considers that the material reported as a Mineral Resource fulfils the requirement by the CIM Guidelines of having a RPEEE through open pit mining.

A summary of the Mineral Resources for all deposits comprising the Muntanga Project are presented in Table 3.0 below.

Table 3.0Mineral Resource Statement*, Muntanga Uranium Project, Zambia, effective date of March 31, 2023

ClassificationDepositTonnesU3O8 GradeU3O8
(Mt)(ppm)Mlb
MeasuredGwabi1.12540.6
Njame2.23741.8
IndicatedMuntanga7.53605.9
Dibbwi3.12551.8
Dibbwi East25.237420.8
Gwabi2.73742.2
Njame0.83210.6
     Total M&I42.635933.7
InferredMuntanga4.03192.8
Dibbwi0.62500.3
Dibbwi East9.13446.9
Gwabi0.22790.1
Njame1.13260.8
     Total Inferred15.033010.9

 

*Notes:

  1. The effective date of the mineral resource statement is March 31, 2023. The QP for the estimate is Cliff Revering, P.Eng., an employee of SRK Consulting (Canada) Inc.
  2. Mineral resources are prepared in accordance with CIM Definition Standards (CIM, 2014) and the CIM estimation of Mineral Resources and Mineral Reserves Best Practise Guidelines (CIM, 2019).
  3. Mineral Resources are reported at a cut-off grade of 100 ppm eU3O8.
  4. Mineral resources are constrained within an optimized pit shell using a uranium price of USD70/lb U3O8, mining costs of USD2.90/t, processing costs of USD8.00/t ore, additional ore mining costs of USD0.50/t ore, G&A costs of USD1.50/t ore, royalty of 5% on U3O8 price and a discount rate of 8%.
  5. Mineral resources are not mineral reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the mineral resources will be converted into mineral reserves in the future.
  6. All figures have been rounded to reflect the relative accuracy of the estimate.

Analysis of the open-pit shell used to constrain the MRE highlights that there are still inferred category mineral resources that have the potential to be converted to indicated resources with additional drilling. That would enable them to be included in the economics related to any future feasibility study, as the examples below indicate. This work is currently under way as part of this year's previously announced drilling program.

Figures 1&2: Sections from Dibbwi East showing resource classification and MRE Shell

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_001.jpg

Fig 1

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_001full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_002.jpg

Fig 2

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_002full.jpg

Figure 3 - Dibbwi East drillhole and cross-section location map

Cannot view this image? Visit: https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_003.jpg

Fig 3

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/5017/173744_44a688c3142f4895_003full.jpg

In conclusion, the updated MRE for the Muntanga Project is a testament to GoviEx's strategic focus and commitment to maximizing the potential of its vast resource base. As the only uranium developer with two African projects ready to begin development and near-term production, GoviEx is well placed to benefit from future growth.

Qualified Person Statement
The technical information and associated data in this release has been reviewed, verified and approved by Cliff Revering, P.Eng., who is an independent Qualified Person under the terms of NI 43-101 for uranium deposits.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

About GoviEx Uranium Inc.
|GoviEx is a mineral resource company focused on the exploration and development of uranium properties in Africa. GoviEx's principal objective is to become a significant uranium producer through the continued exploration and development of its flagship mine-permitted Madaouela Project in Niger, its mine-permitted Mutanga Project in Zambia, and its multi-element Falea Project in Mali.

Contact Information
Isabel Vilela, Head of Investor Relations and Corporate Communications
Tel: +1-604-681-5529
Email: info@goviex.com Web: www.goviex.com

Cautionary Statement Regarding Forward-Looking Statements
This news release contains forward-looking information within the meaning of applicable securities laws. All information and statements other than statements of current or historical facts contained in this news release are forward-looking information.

Forward-looking statements are subject to various risks and uncertainties concerning the specific factors disclosed here and elsewhere in GoviEx's periodic filings with Canadian securities regulators. When used in this news release, words such as "will", "could", "plan", "estimate", "expect", "intend", "may", "potential", "should," and similar expressions, are forward-looking statements. Information provided in this document is necessarily summarized and may not contain all available material information.

Although the Company believes the expectations reflected in such forward-looking statements are based on reasonable assumptions, it can give no assurances that its expectations will be achieved. Such assumptions, which may prove incorrect, include the following: (i) that the Company will be successful in its exploration and development plans for all its projects; (ii) that projected low capital expenditures for the mine-permitted projects will remain unchanged or improve; (iii) that the planned exploration and development programs on GoviEx's projects will be completed as planned and meet GoviEx's objectives; and (iv) that the price of uranium will remain sufficiently high and the costs of advancing the Company's projects will remain sufficiently low so as to permit GoviEx to implement its business plans in a profitable manner.

Factors that could cause actual results to differ materially from expectations include (i) the risk that the Company may not be able to fully realize the anticipated benefits of the updated MRE and the conversion of inferred resources to indicated resources; (ii) the risk that the ongoing feasibility study may not yield the expected results; (iii) the risk that the current drilling program may not result in further potential resource upgrades; (iv) potential delays or changes in the Company's development plans due to various factors, including COVID-19 restrictions; (v) the failure of the Company's projects, for technical, logistical, labour-relations, or other reasons; (vi) a decrease in the price of uranium below what is necessary to sustain the Company's operations; (vii) an increase in the Company's operating costs above what is necessary to sustain its operations; (viii) accidents, labour disputes, or the materialization of similar risks; (ix) a deterioration in capital market conditions that prevents the Company from raising the funds it requires on a timely basis; and (x) generally, the Company's inability to develop and implement a successful business plan for any reason.

In addition, the factors described or referred to in the section entitled "Risks Factors" in the MD&A for the year ended December 31, 2022, of GoviEx, which is available on the SEDAR website at www.sedar.com, should be reviewed in conjunction with the information found in this news release.

Although GoviEx has attempted to identify important factors that could cause actual results, performance, or achievements to differ materially from those contained in the forward-looking statements, there can be other factors that cause results, performance, or achievements not to be as anticipated, estimated, or intended. There can be no assurance that such information will prove to be accurate or that management's expectations or estimates of future developments, circumstances, or results will materialize. As a result of these risks and uncertainties, no assurance can be given that any events anticipated by the forward-looking information in this news release will transpire or occur, or, if any of them do so, what benefits that GoviEx will derive therefrom. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements in this news release are made as of the date of this news release, and GoviEx disclaims any intention or obligation to update or revise such information, except as required by applicable law.


News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GoviEX Uranium Files Annual Information Form

GoviEX Uranium Files Annual Information Form

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx" or the "Company"), a mineral resource company specializing in uranium exploration and development in Africa, announces that further to the filing of its audited consolidated financial statements and management's discussion and analysis for the year ended December 31, 2022, it has today voluntarily filed its Annual Information Form for the year ended December 31, 2022. These filings can be found on the Company's website at www.goviex.com and under the Company's SEDAR profile at www.sedar.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GoviEx Sponsors Barefoot College International's Solar Project in Niger to Support Local Communities

GoviEx Sponsors Barefoot College International's Solar Project in Niger to Support Local Communities

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx" or the "Company") is proud to announce its sponsorship of Barefoot College International's Solar Project in Niger.

This groundbreaking initiative is dedicated to empowering rural women without formal education through comprehensive training in solar technology installation and maintenance, livelihoods development and a holistic women's empowerment curriculum. By fostering self-sufficiency, promoting livelihood development, and ensuring environmental sustainability, the Solar Project aims to enhance the quality of life for individuals living in rural areas.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GoviEx Uranium Provides Update on the Sale of the Falea Exploration Project

GoviEx Uranium Provides Update on the Sale of the Falea Exploration Project

GoviEx Uranium Inc. (TSXV: GXU) (OTCQX: GVXXF) ("GoviEx" or the "Company"), a mineral resource company specializing in uranium exploration and development in Africa, announces that the agreement with African Energy Metals Inc. ("AEM") for AEM's acquisition of all the issued and outstanding shares of GoviEx's wholly-owned Malian subsidiary, Delta Exploration Mali SARL ("Delta"), which holds the Falea project in Mali, has been terminated due to the fact that AEM was unable to complete its obligations for closing.

In light of this development, GoviEx retains ownership of the Falea project. GoviEx's primary focus is to concentrate its resources on the development of its two advanced-stage mine-permitted projects, namely Madaouela in Niger and Muntanga in Zambia.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
ASX symbol with uranium ore.

Top 5 ASX Uranium Stocks of 2024

Uranium has broken out, with the spot price rising to a 16-year high of US$106 per pound in early 2024. Despite a pullback, uranium prices in April still remain 30 percent higher than last year's average.

Although the market's turnaround has taken time, experts are predicting a bright future as countries around the world pursue clean energy goals. Against that backdrop, some ASX-listed uranium companies have been making moves in 2024.

Below the Investing News Network has listed the top uranium stocks on the ASX by year-to-date gains. Data was gathered using TradingView's stock screener on April 10, 2024, and all companies included had market caps above AU$50 million at the time. Read on to learn more about these firms and what they've been up to so far this year.

Keep reading...Show less
Nuclear power plants.

Top 10 Uranium-producing Countries (Updated 2024)

Output from the top uranium-producing countries rose steadily for a decade, peaking at 63,207 metric tons (MT) in 2016. However, global uranium production has noticeably declined in the years since then.

Decreased numbers across the world are related to the persistently low spot prices the uranium market has experienced in the wake of the Fukushima disaster; COVID-19 and Russia's war against Ukraine have also had an impact on output.

Now uranium prices have begun to rebound significantly, buoyed by increasingly positive sentiment about the role of nuclear power in the energy transition, and investment demand via new uranium-based funds.

Keep reading...Show less
Tisdale Clean Energy Appoints Jordan Trimble to Advisory Board

Tisdale Clean Energy Appoints Jordan Trimble to Advisory Board

TISDALE CLEAN ENERGY CORP. (“ Tisdale ” or the “ Company ”) (TSX.V: TCEC, OTCQB: TCEFF , FSE: T1KC ) , is pleased to announce the appointment of Jordan Trimble to its newly constituted Advisory Board.

Mr. Trimble is the President and CEO of Skyharbour Resources, a uranium explorer and prospect generator in the Athabasca Basin and Tisdale’s project partner at the South Falcon East Project. He brings significant experience in the uranium sector and will provide vital insight to the Company in his advisory role.

Keep reading...Show less
Victory Resources (CSE:VR)

Victory Announces Private Placements

NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES

Victory Battery Metals Corp. (CSE:VR)(FRA:VR6) (OTC PINK:VRCFF) ("Victory" or the "Company") announces today that it will undertake a non-brokered private placement of up to $500,000 by the issuance of 10,000,000 units at $0.05, each unit consisting of one share and one half a warrant. Each whole warrant entitles the holder to additional share for 2 years at a price of $0.10.

Keep reading...Show less
Toro Energy

Toro Energy


Keep reading...Show less
Uranium ore and periodic symbol.

Uranium Price Update: Q1 2024 in Review

The uranium spot price displayed volatility in Q1, rising to a high unseen since 2007 before ending the quarter below US$90 per pound. U3O8 values shed 3.96 percent over the three month period, but experts believe fundamentals remain strong and expect the sector to benefit from various tailwinds in the months ahead.

Supply remains a key factor in the uranium landscape, with a deficit projected to grow amid production challenges. With annual output well below the current demand levels, the supply crunch is expected to be a long-term price driver.

“Supply-side fragility continued to be one of the key themes in Q1, especially the news out of Kazakhstan that production would be significantly lower than expected in 2024 than previously thought,” Ben Finegold, associate at London-based investment firm Ocean Wall, told the Investing News Network in an interview.

Keep reading...Show less