Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to announce its consolidated production and cost guidance as well as its capital and exploration budgets for 2022. All dollar amounts are in US dollars (US$).

2022 Production and Cost Guidance Highlights

In 2022, silver production is expected to range from 4.2 to 4.8 million ounces (oz) and gold production is anticipated to be between 31,000 oz and 35,000 oz. Silver equivalent production is forecasted to total between 6.7 million and 7.6 million oz at an 80:1 silver:gold ratio.

Consolidated cash costs 2 and all-in sustaining costs 2 ("AISC") in 2022 are estimated to be $9.00-$10.00 per oz silver and $20.00-21.00 per oz silver, respectively, net of gold by-product credits. The Company's 2022 cost outlook is higher than the prior year as inflation, royalties and mining duties are expected to increase in 2022.

"Our operations outperformed last year with Guanacevi's production bolstered by higher than anticipated mined ore grades," stated Dan Dickson, Endeavour's CEO. "In 2022, our production outlook is on par with the average of the last three years as we anticipate the grade at Guanacevi to be more in line with our estimated reserves and we remove the small annual contribution from our El Compas mine, which closed last August."

Mr. Dickson added, "This year, the team is focused on managing costs in order to offset the inflationary pressures we are seeing across the industry. Equally important will be expanding resources and advancing our exceptional growth pipeline. Terronera will move from the funding and approval phase through to construction. As well, we will initiate a preliminary economic assessment at Parral and define a current resource at Pitarrilla following the closing of this acquisition in the first half of the year."

2022 Guidance Summary

Guanacevi Bolanitos Consolidated
Tonnes per day tpd 1,100 - 1,200 1,000 - 1,200 2,100 - 2,400
Silver production M oz 3.8 - 4.2 0.4 - 0.6 4.2 - 4.8
Gold production k oz 10.0 - 12.0 21.0 - 23.0 31.0 - 35.0
Silver Eq production 1 US$/oz 4.6 - 5.2 2.1 - 2.4 6.7 - 7.6
Cash costs, net of gold by-product credits 2 US$/oz $9.00 - $10.00
AISC, net of gold by-product credits 2 US$/oz $20.00 - $21.00
Sustaining capital 2 budget US$M $34.3
Development budget US$M $11.5
Exploration budget US$M $13.0

Operating Mines

At Guanaceví, 2022 production will range from 1,100 tonnes per day (tpd) to 1,200 tpd and average 1,165 tpd from the Milache, SCS and P4E orebodies. A significant portion of production will be mined from the Porvenir Cuatro extension on the El Curso concessions. The El Curso concessions were leased from a third party with no upfront costs but with significant royalty payments on production. Compared to 2021, ore grades are expected to decrease slightly with similar recoveries. Cash costs per ounce and direct operating costs per tonne are expected to increase in 2022, primarily due to the impact of inflation on power costs, re-agent costs and salaries as well as higher estimated royalty and mining duty payments.

In 2022, production at Bolañitos is expected to range from 1,000 tpd to 1,200 tpd and average 1,080 tpd from the Plateros-La Luz, Lucero-Karina and Bolanitos-San Miguel vein systems. Ore grades and recoveries are expected to be similar to 2021. Cash costs per oz and direct costs per tonne are expected to increase primarily due to inflationary impact on power costs and salaries.

Operating Costs

In 2022, cash costs, net of gold by-product credits, are expected to be $9.00-$10.00 per oz of silver produced. Consolidated cash costs on a co-product basis 2 are anticipated to be $13.00-$14.00 per oz silver and $1,100-$1,200 per oz gold.

All-in sustaining costs, net of gold by-product credits, in accordance with the World Gold Council standard, are estimated to be $20.00-$21.00 per oz of silver produced. When non-cash items such as stock-based compensation and accretion are excluded, AISC are forecast to be in the $19.00-$20.00 range.

Direct costs 2 per tonne are estimated to be $95-$100 with inflationary pressures expected to continue in 2022. Direct operating costs 2 , which includes royalties and special mining duties are estimated to be in the range of $120-$125 per tonne.

Management made the following assumptions in calculating its 2022 cost forecasts: $22 per oz silver price, $1,760 per oz gold price, and 20:1 Mexican peso per US dollar exchange rate.

2022 Capital Budget

Mine
Development
Other
Capital
Sustaining
Capital
Growth
Capital
Total
Capital
Guanaceví $10.3 million $10.1 million $20.4 million - $20.4 million
Bolañitos $8.4 million $3.8 million $12.2 million - $12.2 million
Terronera - - - $9.5 million $9.5 million
Corporate - - $1.7 million $2.0 million $3.7 million
Total $18.7 million $13.9 million $34.3 million $11.5 million $45.8 million

Sustaining Capital Investments

In 2022, Endeavour plans to invest $34.3 million in sustaining capital, including $32.6 million at its two operating mines and $1.7 million to maintain exploration concessions and cover corporate infrastructure. At current metal prices, the sustaining capital investments are expected to be paid out of operating cash flow.

At Guanacevi, $20.4 million will be invested in capital projects, the largest of which is the development of 5.7 kilometres of mine access at the Milache, SCS and the P4E orebodies for an estimated $10.3 million. The additional $10.1 million will go to upgrade the mining fleet, support site infrastructure and expand the tailings dam.

At Bolañitos, $12.2 million will be invested in capital projects, including $8.4 million for 5.5 kilometres of mine development to access resources in the Plateros-La Luz, Lucero-Karina, Bolanitos-San Miguel and Belen vein systems. The additional $3.8 million will go to upgrade the mining fleet, support site infrastructure, raise the tailings dam and commence a new portal to access the Belen ore body.

At Terronera, $9.5 million is budgeted for the first quarter of 2022 to continue with final detailed engineering, early earth works, critical contracts and procurement of long lead items. The Company intends to make a formal construction decision, subject to completion of a financing package and receipt of amended permits, in the coming months, at which time the budget for the remainder of 2022 for the project will be determined.

The capital budget presented above does not include the $70 million acquisition cost associated with the Company's recently announced acquisition of the Pitarrilla Project ( see January 13, 2022 news release ) in Durango State, Mexico from SSR Mining Inc. The transaction is expected to be completed in the first half of 2022.

2022 Exploration Budget

Project 2022 Activity Drill Metres Expenditures
Guanaceví Drilling 11,000 $1.8 million
Bolañitos Drilling 10,000 $1.5 million
Terronera Drilling 11,000 $1.9 million
Parral Drilling/Economic Study 7,000 $1.7 million
Chile - Aida Drilling 3,000 $1.5 million
Chile - Other Evaluation - $0.9 million
Bruner Drilling/Evaluation 3,000 $1.9 million
Pitarrilla Drilling/Evaluation 5,000 $1.8 million
Total 50,000 $13.0 million

In 2022, the Company plans to spend $13.0 million drilling 50,000 metres across its properties.

At the Guanacevi and Bolanitos mines, 21,000 metres of drilling are planned at a cost of $3.3 million to replace reserves and expand resources.

At the Terronera development project, 11,000 metres are planned to test multiple regional targets identified in 2021 to expand resources within the district.

At the Parral project in Chihuahua state, 7,000 metres are planned at a cost of $1.7 million to delineate existing resources, expand resources and test new targets. In the second half of the year, the Company expects to initiate a preliminary economic assessment.

In Chile, management intends to invest $1.5 million to test the Aida exploration project located in the northern Chile Region II along the Argentina border accessible by paved highway and dirt road. The Company plans to drill 3,000 metres to test a manto target with significant silver-manganese-lead-zinc anomaly at surface in the second half of 2022. Additionally, the Company plans to advance mapping, sampling and surface exploration on its other exploration projects in Chile, estimated to cost $0.9 million including administration costs in the country.

At the Bruner project management plans to invest $1.9 million to evaluate and verify historical data to define a current resource, map and sample new targets and drill 3,000 metres verifying historical data and testing new targets.

Similarly, subject to closing the Pitarrilla acquisition, management plans to invest $1.8 million for drilling to verify the historical data and define a current resource in 2022. Management plans to release a more detailed exploration and evaluation plan for the Pitarrilla project following closing of the transaction.

About Endeavour Silver – Endeavour Silver Corp. is a mid-tier precious metals mining company that operates two high-grade underground silver-gold mines in Mexico. Endeavour is currently advancing the Terronera mine project towards a development decision, pending financing and final permits and exploring its portfolio of exploration and development projects in Mexico, Chile and the United States to facilitate its goal to become a premier senior silver producer.  Our philosophy of corporate social integrity creates value for all stakeholders.

SOURCE Endeavour Silver Corp.

Contact Information
Trish Moran
Interim Head of Investor Relations
Tel: (416) 564-4290
Email: pmoran@edrsilver.com
Website: www.edrsilver.com

Follow Endeavour Silver on Facebook , Twitter , Instagram and LinkedIn

Endnotes

1 Silver equivalent is calculated using an 80:1 silver:gold ratio.

2 Non-IFRS Financial Measures

The Company has included certain performance measures that are not defined under International Financial Reporting Standards ("IFRS"). The Company believes that these measures, in addition to conventional measures prepared in accordance with IFRS, provide investors an improved ability to evaluate the underlying performance of the Company. The non-IFRS measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers.

Cash costs and cash costs per ounce

Cash costs per ounce is a non-IFRS measure. In the silver mining industry, this metric is a common performance measure that does not have a standardized meaning under IFRS. Cash costs include direct costs (including smelting, refining, transportation and selling costs), royalties and special mining duty and changes in finished goods inventory net of gold credits. Cash costs per ounce is based on ounces of silver produced and is calculated by dividing cash costs by the number of ounces of silver produced.

Cash costs on a co-product and cash costs on a co-product per ounce

Silver co-product cash costs and gold co-product cash costs include mining, processing (including smelting, refining, transportation and selling costs), and direct overhead costs allocated on pro-rated basis of realized metal value. Cash costs on a co-product per ounce is based on the number of either silver or gold ounces produced.

Direct operating costs and direct costs

Direct operating costs per tonne include mining, processing (including smelting, refining, transportation and selling costs) and direct overhead at the operation sites. Direct costs per tonne include all direct operating costs, royalties and special mining duty.

All-in sustaining costs ("AISC") and AISC per ounce

This measure is intended to assist readers in evaluating the total cost of producing silver from operations. While there is no standardized meaning across the industry for AISC measures, the Company's definition conforms to the definition of AISC as set out by the World Gold Council and used as a standard of the Silver Institute. The Company defines AISC as the cash costs (as defined above), plus reclamation cost accretion, mine site expensed exploration, corporate general and administration costs and sustaining capital expenditures. AISC per ounce is based on ounces of silver produced and is calculated by dividing AISC by the number of ounces of silver produced.

Sustaining capital

Sustaining capital is defined as the capital required to maintain operations at existing levels. This measurement is used by management to assess the effectiveness of an investment program.

For further information on reconciliations of Non-GAAP measures, refer to the Non-IFRS Measures section of the Company's Management's Discussion & Analysis for the three and nine months ending September 30, 2021, beginning on page 19.

Cautionary Note Regarding Forward-Looking Statements

This news release contains "forward-looking statements" within the meaning of the United States private securities litigation reform act of 1995 and "forward-looking information" within the meaning of applicable Canadian securities legislation. Such forward-looking statements and information herein include but are not limited to statements regarding Endeavour's anticipated performance in 2022 including changes in mining operations and forecasts of production levels, anticipated production costs and all-in sustaining costs, the timing and results of various activities and the impact of the COVID 19 pandemic on operations. The Company does not intend to and does not assume any obligation to update such forward-looking statements or information, other than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, production levels, performance or achievements of Endeavour and its operations to be materially different from those expressed or implied by such statements. Such factors include but are not limited to the ultimate impact of the COVID 19 pandemic on operations and results, changes in production and costs guidance, national and local governments, legislation, taxation, controls, regulations and political or economic developments in Canada and Mexico; financial risks due to precious metals prices, operating or technical difficulties in mineral exploration, development and mining activities; risks and hazards of mineral exploration, development and mining; the speculative nature of mineral exploration and development, risks in obtaining necessary licenses and permits, and challenges to the Company's title to properties; as well as those factors described in the section "risk factors" contained in the Company's most recent form 40F/Annual Information Form filed with the S.E.C. and Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to: the continued operation of the Company's mining operations, no material adverse change in the market price of commodities, mining operations will operate and the mining products will be completed in accordance with management's expectations and achieve their stated production outcomes, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or information, there may be other factors that cause results to be materially different from those anticipated, described, estimated, assessed or intended. There can be no assurance that any forward-looking statements or information will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.



Primary Logo

News Provided by GlobeNewswire via QuoteMedia

EDR:CA,EXK
The Conversation (0)
Endeavour Silver Announces 2024 Annual General Meeting Voting Results

Endeavour Silver Announces 2024 Annual General Meeting Voting Results

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to announce that shareholders voted in favour of all items of business at the Company's 2024 Annual General Meeting ("AGM") held on May 28, 2024 in Vancouver. A total of 104,090,503 votes were cast or represented by proxy at the AGM, representing 43.31% of the outstanding common shares as of the record date. The following is a tabulation of the votes submitted by proxy:

DIRECTORS

NUMBER   OF   SHARES PERCENTAGE   OF   VOTES   CAST
FOR WITHHELD/
ABSTAIN
FOR WITHHELD
Rex J. McLennan 50,212,585 11,699,944 81.10% 18.90%
Margaret M. Beck 61,370,134 542,396 99.12% 0.88%
Ricardo M. Campoy 61,455,874 456,656 99.26% 0.74%
Daniel Dickson 61,461,186 451,345 99.27% 0.73%
Amy Jacobsen 61,364,651 547,879 99.12% 0.88%
Kenneth Pickering 53,516,716 8,395,815 86.44% 13.56%
Mario D. Szotlender 61,428,282 484,248 99.22% 0.78%
Angela Johnson 61,333,538 578,992 99.06% 0.94%

All director nominees were re-elected, including the addition of Angela Johnson to the Board of Directors (see news release dated April 18, 2024 ) to fill vacancy left by the retirement of Christine West.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Endeavour Silver Highlights Progress on its Three-Year Sustainability Strategy in 2023 Sustainability Report

Endeavour Silver Highlights Progress on its Three-Year Sustainability Strategy in 2023 Sustainability Report

Endeavour Silver Corp. ("Endeavour" or the "Company") (TSX: EDR, NYSE: EXK) made further progress executing its 2022-2024 Sustainability Strategy as outlined in the Company's 2023 Sustainability Report released today.

Entitled "Transformation in Motion", the report provides insights into Endeavour's sustainability performance and approach over 2023, including second-year progress highlights against the strategy.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Boab Metals Limited

Corporate Presentation December 2024

Boab Metals Limited (ASX: BML) (“Boab” or “Company”) is pleased to present its investor presentation.


Keep reading...Show less
Alex Wallis, vice president of exploration at Silver47 Exploration.

Silver47 Beefs Up Drilling Plans to Expand Resource at Red Mountain Polymetallic Project

Following release of the final results from Silver47 Exploration's (TSXV:AGA) 2024 exploration program, the company is beefing up plans for a more expansive and targeted drill campaign in the new year at its flagship Red Mountain project in Alaska. Alex Wallis, vice president of exploration, said the aim is to “increase both the grade and the tonnage."

“With the modern drilling and the recoveries we saw this year, we have a really good chance to increase just from infilling the historic zones to really bulk that resource out as well,” he said.

Approximately 20 percent of future drilling efforts will focus on fresh exploration targets like Galleon and Horseshoe, according to Wallis. The company is eyeing more than 15 exploration targets at Red Mountain that have never been drill tested with geochemical and geophysical targeting.

Keep reading...Show less
  Unico Silver Limited

Cerro Leon drill results

Further high-grade mineralisation identified at the Karina prospect

Unico Silver Limited (“USL” or the “Company”) is pleased to announce first assay results from ongoing drilling at the Cerro Leon project, located in the Santa Cruz province of Argentina.

Keep reading...Show less

First Majestic Announces Mailing of Materials for Special Meeting

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce that it has commenced mailing of its meeting materials for the special meeting of the Company's shareholders (the "Special Meeting") that will be held on Tuesday, January 14, 2025 at 11:00 a.m. (Pacific Time) at the offices of Bennett Jones LLP, located at Suite 2500 - 666 Burrard Street, Vancouver, British Columbia V6C 2X8.

At the Special Meeting, pursuant to the requirements of the rules of the Toronto Stock Exchange and the New York Stock Exchange, First Majestic shareholders will be asked to approve an ordinary resolution (the "Share Issuance Resolution") approving the issuance of up to 190,000,000 common shares of First Majestic ("First Majestic Shares") to stockholders of Gatos Silver, Inc. ("Gatos") in connection with the previously announced acquisition by First Majestic of all of the shares of common stock of Gatos (the "Transaction"). First Majestic's Board of Directors unanimously recommends that the Company's shareholders vote FOR the Share Issuance Resolution.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Pan American Silver Provides Annual Exploration Update

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") provides an annual exploration update and releases new exploration drill results for its Jacobina, El Peñon, La Colorada, Huaron, Minera Florida and Timmins mines, as well as its La Colorada Skarn project.

"The success of our exploration program highlights the potential for long-term organic growth at many of our assets," said Christopher Emerson, Vice President of Exploration and Geology at Pan American. "Based on the results we were achieving in exploration this year, we increased our drill budget to over 450,000 metres for 2024. This exploration update highlights these results, and showcases the ongoing discovery of new mineralized structures in and around our existing mining operations."

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Boab Metals

Boab Metals Limited (ASX: BML) – Trading Halt

Boab Metals Limited (ASX:BML) (the “Company”) hereby requests a trading halt of its securities be granted by the ASX effective immediately, pending a release of an announcement regarding an Offtake and Project Finance Agreement. The trading halt will last until the earlier of commencement of trading on Wednesday, 11 December 2024 or the release to the market of an announcement as specified above. The Company is not aware of any reason why the trading halt should not be granted or of any other information necessary to inform the market about the trading halt. This request was authorised for release by the Board of the Company.

Keep reading...Show less

Latest Press Releases

Related News

×