August 06, 2023
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) announces that the Abra Base Metals Mine (“Abra” or the “Mine”) has updated its JORC Code 2012 Mineral Resource Estimate (“July 2023 Resource” or “MRE”). This update is the first MRE annual update including all underground diamond drilling up to 5 May 2023, and all underground geological mapping, and mining and processing up to 30 June 2023.
HIGHLIGHTS
- Revised total Abra MRE of 33.4Mt at 7.1% Pb and 17g/t Ag (5% Pb cut-off grade):
- Measured 0.3Mt at 7.3% Pb and 32g/t Ag,
- Indicated 16.2Mt at 7.3% Pb and 19g/t Ag,
- Inferred 16.9Mt at 6.9% Pb and 15g/t Ag.
- No material difference from the previous MRE (April 2021), supporting Abra’s long-term mining plans.
- Includes 26,277m (163 holes) of underground diamond drilling, geology mapping associated with 7,319m underground development, and includes mining depletion.
- Identification and understanding of potential new lead and silver mineralisation associated with Carbonatic Dome structures within the Apron Zone and strong conversion of Inferred Mineral Resources to Indicated Mineral Resources in the eastern end of the mine.
Managing Director, Tony James commented, “The updated Abra MRE reflects substantial work achieved at Abra over the last 12-months, greatly improving the understanding of the deposit. Importantly, it shows no material difference from the April 2021 MRE, and therefore continues to support our long-term mining plans. The Resource update work also confirms that mining and processing grades seen during Abra’s commissioning and ramp-up, which is dominated by mine development, are not representative of the total MRE at Abra. As mining areas open- up, grades through the mill continue to improve, particularly as we move away from the upper northern margin near the Abra Fault.”
SUMMARY
Since June 2022, 26,277m (163 holes) of underground diamond NQ drilling has been completed and during commissioning and ramp-up of the mine, 325,924 tonnes at 4.8% lead and 20g/t silver has been mined and processed (note the early stages of mining is development focussed with 244,332t (75%) associated with development which is subject to a mining cut-off grade of 3.3% lead). Material mined and processed also includes both high-grade and sub-grade material produced during commissioning and early stages of ramp-up. A total of 7,319m of underground development has also been completed to 30 June 2023 in the Apron Zone section of the ore body allowing access for detailed mapping and geological interpretation.
The 2023 Mineral Resource estimate (MRE) takes into account the ore losses seen on the upper- northern margin of the orebody, as outlined in April 2023 (see Galena ASX announcement of 20 April 2023).
To complete and update the 2023 MRE with the latest technical understanding and confidence, drilling data was cut-off on 5 May 2023 and mine production data cut-off on 30 June 2023. Table 1 (below) states the Abra July 2023 Resource at a 5.0% lead cut-off grade, as at 30 June 2023. The July 2023 Resource has been independently reviewed by Snowden Optiro Pty Ltd (“Snowden Optiro”).

Notes: 1. Calculated using ordinary kriging method at a 5.0% lead cut-off grade. Tonnages are rounded to the nearest 100,000t, lead grades to one decimal place and silver to the nearest gram. Rounding errors may occur when using the above figures.
The previously published MRE is dated April 2021 (5% lead cut-off grade) based entirely on surface drilling and interpretation, and comprised a total of 34.5Mt at 7.2% lead and 16g/t silver (see Galena ASX announcement of 28 April 2021).
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
12 December 2022
Abra Construction At 97% Complete – First Ore Stockpiled For January Processing
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion... Keep Reading...
16 November 2022
Abra Construction At 92% Complete – Reaches First Ore Underground
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November... Keep Reading...
13 November 2022
Abra Mine Reaches Ore
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station... Keep Reading...
31 October 2022
Galena Mining Activities Report For Quarter Ended 30 September 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western... Keep Reading...
24 October
Ed Steer: Silver Rally Now Unstoppable, Price to Hit Triple Digits
Ed Steer of Ed Steer's Gold and Silver Digest shares his thoughts on silver's run past US$50 per ounce, saying that in his view the bull market is just getting started. "One way or another we're going to run into a supply/demand brick wall, and when that day happens we could see triple-digit... Keep Reading...
22 October
Gianni Kovacevic: Silver, Oil to Break US$100, but This is the Real Speculation
Investor and author Gianni Kovacevic discusses silver's price pullback, saying that in the long term he sees the white metal reaching triple digits. He expects oil prices to reach that level too, but emphasized that he sees lithium as the truly contrarian play for the rest of 2025 and into next... Keep Reading...
21 October
BP Silver Finalizes Targets for Upcoming Drill Program at its Cosuño Silver Project, Bolivia
BP Silver Corp. (TSXV: BPAG) ("BP Silver" or the "Company") announces that it has finalized targets for initial drill testing and has selected Maldonado Exploraciones, a premier Bolivian drilling contractor, to carry out the upcoming drill program at its Cosuño Silver Project ("Cosuño") in... Keep Reading...
21 October
Silver Hammer Enters into Option Agreement to Acquire 100% Interest in a Strategic and Prospective Silver Project in the Silver Valley of Idaho
Silver Hammer Mining Corp. (CSE: HAMR) (the "Company" or "Silver Hammer") is pleased to announce it has entered into an option agreement (the "Option Agreement") on October 20, 2025 with Fahey Group Mines, Inc. ("Fahey"), pursuant to which the Company has been granted the right (the "Option") to... Keep Reading...
20 October
Top 5 Canadian Silver Stocks of 2025
Silver's strong performance in 2025 is drawing attention to silver-mining companies.During Q3, the silver price closed in on all-time highs, reaching a quarterly high of US$46.92 per ounce on September 29. It has continued to soar since then, breaking US$50 and setting a new all-time high of... Keep Reading...
Latest News
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00