- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
![Galena Mining](https://investingnews.com/media-library/galena-mining.png?id=34179518&width=1200&height=800)
Activities Report For The Quarter Ended 30 June 2023
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 June 2023 (the “Quarter”), primarily focused on the ongoing production ramp-up of both the underground mine and the processing plant to achieve steady-state production in the second half of 2023, at its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.
HIGHLIGHTS
- Strong recovery achieved with May and June physicals following limited activities in April due to rainfall events. Ore mined of 194,644t at 5.4% Pb grade and 16.9g/t Ag grade and processed 190,258t at 5.1% Pb grade and 19.0g/t Ag grade for the Quarter.
- Second and third in-specification lead concentrate shipments of ~5kt each completed in the Quarter, doubling revenue from the previous quarter to ~A$20.4 million.
- July month to date on track to achieve first positive monthly operating cash flows with over 90% of the next ~9-10kt concentrate shipment produced and committed shipment set for loading between 28 July and 4 August.
- Underground development achieved 1,583m advance during the Quarter with the decline reaching 1,234mRL (312m vertically below the surface). Underground stope production achieved 81,592t at 6.3% Pb grade. Pb grade is slowly improving and will continue to do so in the coming months as new work areas are established and the ratio of stoping ore to development ore increases to required production levels.
- Cash balance at Quarter-end of A$19.3 million.
- Galena completed an oversubscribed placement to provide additional working capital funding for the Abra ramp-up.
- September quarter mining plans set to achieve over 2,000m development and over 250,000t stope production expecting to process over 300,000t of ore as next quarter ramp-up milestones. Targeting ~25-30kt of lead concentrate shipments expected to generate positive operating cash flows.
Managing Director, Tony James commented, “We made a strong recovery from no production in April to set new project highs in both May and June, and we expect to achieve first positive operating cash flows in July. The plant is showing its capacity to process everything put in front of it so far and the focus remains on increasing mine production levels. The key to the mine reaching the levels required is good planning and execution. With the mine plans at 90% grade control status through to January 2024 we see the pathway well laid out to achieve our targets. Some very strong technical work has been completed to increase our confidence in hitting our targets.”
ABRA BASE METALS MINE (60%-OWNED)
Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena and 40% owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.
Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment achieved in March 2023.
Review of operations
Notes:
1. Total Recordable Injury Frequency Rate (“TRIFR”) and Notifiable Incident Frequency Rate (“NIFR”) are the 12-month moving average at the end of each quarter calculated per million work hours.
2. Concentrate sales and average lead price received initially based on provisional invoices and subsequently updated with final invoices, including final assays and quotational period adjustments.
3. Payable lead and silver based on 95% metal payability subject to standard deductions (i.e., 3 units for lead and 50g/t for silver).
4. C1 costs include mining costs, processing costs, site general and administration costs, transport, logistics and shipping costs, and treatment and refining charges, adjusted for inventory movements and net of silver by-product credits.
5. All-in sustaining costs include C1 Costs plus royalties, corporate general and administration costs, sustaining capital and capitalised mine development costs. All-in sustaining costs exclude growth capital and exploration costs.
6. Abra Project construction works were completed by the end of the December 2022 quarter (see Galena ASX announcements of 10 January 2023 and 13 January 2023).
During the Quarter, new quarter high mining and processing production levels were achieved. This achievement also takes into account the limited activities in April 2023 due to the rainfall issues affecting access to the Abra mine site.
In June, a mine development record was set with 646m of lateral and vertical development achieved during the month. A third Jumbo commenced in the mine in June with the aim of increasing the mine’s monthly development rates to 800m per month during the September quarter.
The mine delivered 194,644t (April: 31,915t, May: 81,014t and June: 81,715t) at 5.4% Pb grade to the plant during the Quarter, including stope production ore of 81,592t at 6.3% Pb grade. The higher development ore during the Quarter is consistent with the ramp-up of mine production as new stoping areas are established. In general, mine production in the Quarter was also affected by congestion in the available work areas, production delays associated with upgrading secondary ventilation networks and loader availability. These impediments were continually rectified during the quarter.
The plant effectively processed all the ore delivered from the mine during the Quarter with 190,258t processed (April: Nil, May: 102,719t and June: 87,539t). 12,468t of concentrate was produced containing 8,070t Pb and 63,122oz Ag. Plant availability in May was 99% and in June 86%. A flotation blower (compressor) breakdown caused the lower availability in June. The plant was able to operate consistently at the 150dmt/hr level during the Quarter.
The mine call grade for ore processed during the Quarter was estimated at 5.4% Pb, which is approximately 0.3% Pb higher than the reconciled processing grade of 5.1% Pb.
Considerable technical improvements were achieved during the Quarter with detailed resource modelling and mine planning work completed. A new Mineral Resource Estimate (“MRE”) is expected to be finalised in the coming weeks which will include all the recent underground drilling and revised geological modelling. This work will lead into a new Ore Reserve estimate and 2024 budget completion in the December quarter. Three month rolling mine plans have been established and the mine planning for the remainder of 2023 is well advanced with 90% of that plan built on grade control drilling down to a 12.5x12.5m spacing.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Galena Mining Investor Kit
- Corporate info
- Insights
- Growth strategies
- Upcoming projects
GET YOUR FREE INVESTOR KIT
Galena Mining
Overview
Galena Mining Limited (ASX:G1A, Galena) owns 60 percent of the Abra base metals mine located in the Gascoyne region of Western Australia - home to one of the largest lead and silver deposits in the world, set to produce the highest-grade, cleanest lead concentrate available globally. The company is capitalizing on its Tier 1 asset in a Tier 1 jurisdiction, strengthened by and leveraging partnerships with Japan's largest zinc and lead smelter, as well as with one of the top base metals trading firms in the world.
The company also owns 100 percent of the Jillawarra Project, which covers 76 kilometers of strike extension directly to the west of Abra. The Jillawarra Project contains several large-scale analogous exploration targets including the Woodlands Complex, Quartzite Well and Copper Chert areas.
Galena's major partnerships include Toho Zinc (TSE:5707), Japan's largest zinc and lead smelter, and IXM SA, one of the world's top three base metals trading firms. Toho provided AU$90 million project equity and has a long-term offtake agreement to purchase 40 percent of Abra's production; while IXM has entered into a 10-year take-or-pay offtake contract to purchase the remaining 60 percent.
The company's management team brings decades of experience in the mining and base metals industry and has a proven track record of success throughout all stages of exploration, from development to production.
In November 2020, Galena put in place US$110 million in finalized debt facilities arranged by Taurus Funds Management. The facilities include a US$100-million project finance facility plus a US$10-million cost overrun facility.
The project finance facility consists of a 69-month term loan primarily to fund capital expenditures for the development of Abra. Key terms include:
- Fixed interest of 8 percent per annum on drawn amounts, payable quarterly in arrears.
- 1.125 percent net smelter return royalty.
- No mandatory hedging.
- Early repayment allowed without penalty.
- 15 quarterly repayments commencing on 31 December 2023.
The cost overrun facility is a loan to finance identified cost overruns on the project in capital expenditure and working capital. Fixed interest of 10 percent per annum applies to amounts drawn under the cost overrun facility.
The Taurus debt facilities have been fully drawn and are secured against Abra Project assets and over the shares that each of Galena and Toho own in Abra.
Company Highlights
- Positioned to realize value for shareholders:
- Abra mine construction completed in December 2022, on time and on budget.
- First in-specification concentrate shipment achieved in March 2023.
- Abra is one of the largest and cleanest lead-silver deposits in the world (high-grade, high-value concentrate 1/10th typical deleterious elements).
- Exciting exploration ground and known copper-gold mineralisation below the Abra lead-silver deposit.
- JV between Galena (60 percent) and Japan's largest zinc and lead smelter Toho Zinc (40 percent) underpins long mine life (10+ years) in an exciting new mineral province in Western Australia.
- Galena has a 10-year offtake agreement with IXM, one of the world’s largest base metals traders.
- Annual steady-state guidance:
- Mill throughput of more than 1.3 million tonnes per annum (Mtpa), producing +90,000 tonnes per annum lead and +550,000 ounces per annum silver.
- Annual average lead C1 direct cash cost of US$0.55 to US$0.65/lb.
- Annual average EBITDA (earnings before interest, taxes, depreciation, and amortization) of AU$90 million to $100 million.
- The Abra mine is located in the Gascoyne Region of Western Australia, home to one of the largest undeveloped lead deposits in the world and the highest-grade lead concentrate available, globally.
- The Abra mine carries a JORC mineral resource estimate (July 2023) of 16.2 million tons (Mt) at 7.3 percent lead and 19 grams per ton (g/t) silver in the indicated category, and 16.9 Mt at 6.9 percent lead and 15 g/t silver in the inferred category.
- Abra has been named the world's lowest-cost primary lead mine by Wood Mackenzie, a leading mining research and consultancy group.
- US$110 million of project financing debt facilities from leading mining-specialist lending fund Taurus Funds Management.
- Galena's management team brings decades of experience in the mining and base metals industry and has a proven track record of success throughout all stages of exploration, from development to production.
Key Projects
Abra Mine
The Abra Mine is a 60:40 joint venture between Galena and Japanese lead producer Toho Zinc. It is a globally significant lead-silver project located in the Gascoyne region of Western Australia, between the towns of Newman and Meekatharra approximately 110 kilometers from the DeGrussa copper mine owned by Sandfire Resources (ASX:SFR).
Abra Mine Site Location
The Abra mine carries a total JORC mineral resource estimate published in July 2023 of 33.4 Mt at 7.1 percent lead and 17 g/t silver (5 percent Pb cut-off grade), which includes 0.3 Mt at 7.3 percent lead and 32 g/t silver in the measured category; 16.2 Mt at 7.3 percent lead and 19 g/t silver in the indicated category; and 16.9 Mt at 6.9 percent lead and 15 g/t silver in the inferred category.
All permits for the Abra project have been obtained from the appropriate Western Australian regulatory bodies. The project is also subject to an existing land use and heritage agreement with the Jidi Jidi Aboriginal Corporation. The Abra property is well-serviced by public roads and highways, and all the necessary infrastructure has been developed to transport lead-sulphide concentrates to the Port of Geraldton, Abra's primary export port.
Abra Processing Plant
A final investment decision to complete the Abra Project was made in June 2021 and construction was completed in December 2022, on time and on budget. Several important milestones were achieved in the March 2023 quarter, including the commissioning of the processing plant, first ore fed into the plant and first concentrate produced in January 2023.
The processing plant achieved in-specification concentrate production from the commencement of concentrate production and during the 2023 calendar year, 967,622 tons of ore was processed and 61,800 tons of lead concentrate was produced.
The company is currently undertaking detailed technical work to develop an updated production plan for 2024 production targets and guidance.
Jillawarra Project
Exploration and growth associated with the 100 percent Galena-owned Jillawarra Project covers a highly prospective elongated tenement package covering approximately 76 kilometers of continuous strike length and 508 square kilometers directly to the west of Abra.
The Jillawarra Project hosts many base metals prospects which have had limited shallow exploration work completed since the 1970s by various companies. The bulk of the exploration work was completed by Amoco, Geopeko, Apex Minerals and Abra Mining Limited. The work completed to date has identified several base metals, manganese and gold prospects, of which the Woodlands Complex, Quartzite Well, Manganese Range, Copper Chert, TP and 46-40 were subject to early-stage exploration. Most of the drilling completed within the Jillawarra Project investigated the first 100 to 200-meter depth which, based on recent knowledge of Abra, may not have reached the depths required.
The main prospective corridor within the Jillawarra Project lies within the margins of the Quartzite Well – Lyons River Fault zones which extend east-west along the entire tenement package. Also, the contact between the dolomitic sediments of Irregully Formation and the lower sedimentary unit, polymictic conglomerate, of the Kiangi Creek Formation represents an important marker for the occurrence of base metal mineralisation as seen at Abra.
The Woodlands Complex is an Australian scaled geophysical anomaly which represents a significant target area with the anomaly being 12 kilometers long and 10 kilometers wide. Limited work and technical evaluation have occurred at Woodlands which presents a great opportunity for Galena in the years to come. Ongoing geophysical and exploration drilling will occur concurrently with the development of Abra. The knowledge and understanding of Abra due to its development will provide a significant exploration advantage at Jillawarra.
Management Team
Tony James – Managing Director and CEO
Tony James is a mining engineer with over 30 years’ mine operating and project development experience predominantly in Western Australia. He also has previous experience at managing director level of three ASX-listed companies with two of those companies successfully guided through a merger and takeover process benefiting the shareholders. He has a strong mine operating background (examples being the Kanowna Belle gold mine and the Black Swan nickel mine) and a strong feasibility study / mine development background (examples being the Pillara zinc/lead mine and the Trident/Higginsville gold mine).
Adrian Byass – Non-executive Chairman
Adrian Byass has more than 25 years of experience in the mining industry both in listed and unlisted entities globally. He has served as non-executive and executive director of various listed and unlisted mining entities, which have successfully transitioned to production in bulk, precious and specialty metals around the world. He currently serves on the boards of ASX gold, base metals and lithium companies.
Neville Gardiner – Non-executive Director
Neville Gardiner has over 30 years of experience advising boards on mergers and acquisitions,
equity and debt capital markets, transaction structuring, capital allocation and complex
commercial arrangements. His career achievements include senior executive leadership
roles in Deloitte, Torridon Partners, and at Bank of America Merrill Lynch, where he spent five years as the head of its Australian Natural Resources Team. He also spent nine years with Macquarie Bank, where he had responsibility for its Western Australian Corporate Finance business and its Australian Oil and Gas Advisory business. He has a very strong experience and knowledge base associated with the resources sector in Australia.
Stewart Howe – Non-executive Director
Stewart Howe has more than 40 years of experience in the global resource industry including 18 years in mining. He was chief development officer at Zinifex, one of the world’s largest miners and smelters of lead and zinc. He led the spin-off of Zinifex’s smelters to create Nyrstar NV, and restarted the development of the Dugald River mine.
Craig Barnes – Chief Financial Officer
Craig Barnes has over 25 years of experience in senior finance and financial management within the mining industry and previously the financial services industry. He has considerable experience in project financing, mergers and acquisitions, joint ventures, treasury and implementation of accounting controls and systems.
Before joining Galena, he held the position of CFO of Paladin Energy for more than five years and was part of the team that successfully completed the company's capital restructuring in 2018. Prior to that, he was the chief financial officer of DRDGOLD (NYSE and JSE:DRD) and its affiliated subsidiaries for more than seven years.
Aida Tabakovic – Company Secretary
Aida Tabakovic has over 11 years of experience in the accounting profession, which includes financial accounting reporting, company secretarial services, ASX and ASIC compliance requirements. She has been involved in listing several junior exploration companies on the ASX and is currently company secretary for numerous ASX-listed companies
Abra Construction At 97% Complete – First Ore Stockpiled For January Processing
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.
Managing Director, Tony James commented, “Record underground development in November with delivery of the first 9,000t of ore to the ROM pad along with successful plant commissioning to date puts Abra on the verge of a quick transition into production. Recruitment and other operational readiness activities are well advanced in preparation for January production”.
Figure 1 – First material being tipped into the crusher during commissioning (Photo 26 November).
Figure 2 – Crushing and screening plant commissioning (Photo 26 November).
The following link will show a short video of the Abra crusher commissioning. https://youtube.com/shorts/iSG58MiW_3o
Update on Abra Project progress
Overall progress continues as planned, with first concentrate production expected in Q1 CY2023, following ore commissioning in January 2023. Practical completion of the processing plant is now expected ahead of schedule in December 2022. The processing plant engineering, procurement and construction has reached 99% complete. Piping and electrical works have made significant progress and at the end of November were 96% and 92% complete, respectively. Mechanical items installation is almost complete at 99%.
In November, the first material was crushed and screened as part of the staged commissioning process. The crushing plant ran at design capacity and all commissioning milestones were successfully achieved. Dry commissioning also progressed in most areas of the plant including water and air services, tailings and concentrate thickening, grinding and reagents. Dry commissioning of the remaining areas will be completed in December. Water commissioning commenced in the tailings and concentrate thickening areas of the plant and the remaining areas are expected to be wet commissioned by the end of December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Abra Construction At 92% Complete – Reaches First Ore Underground
Managing Director, Tony James commented, “Reaching first ore underground is extremely rewarding for everyone involved in the project. To see for the first time what we have predicted and interpreted as the Abra orebody delivers a significant step forward for the project. Record development metres in October has taken the mine to the ore and we continue to establish key underground infrastructure with the completion of the 6m diameter surface rise that will be the primary return airway.”
Update on Abra Project progress
Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 97% complete. Structural steel has been completed in October and mechanical installations are at 96% complete. Piping at 80% and electrical at 71% complete continue to progress quickly.
Pacific Energy’s Hybrid 10MW LNG/solar power station completed full integration with the solar power supply, dry commissioning of the crushing and screening areas was completed in early November and first rock crushing is scheduled for late November. Grinding section dry and wet commissioning will commence in the second half of November and is planned for completion by mid-December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.
Mine decline development continued during October. A total of 311m was developed with the decline reaching 1,284mRL. October represents the highest individual development month since the first cut was fired in the portal in October 2021. The decline location is 266m vertically below the surface and is 29m vertically below the original top of the orebody (1313mRL). Underground drilling has now identified mineralisation as high as 1330mRL which is currently being reviewed for potential extraction. The 1300mRL ore access drive reached first ore in early November (See ASX announcement 14 November 2022).
The 1290mRL horizon is a significant work area for development as underground infrastructure for pumping, ventilation, second means of egress and power are all distributed from this level outwards into the development network. All this infrastructure is currently being established and will result in an increased focus on lateral development and lower decline development in the short term.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Abra Mine Reaches Ore
Managing Director, Tony James commented, “Reaching first ore underground delivers another significant step in bringing the Abra project on-line. The first cut in the portal was taken in October 2021, and now 2,949m later and 250m below surface we have reached the orebody. Special acknowledgement needs to be given to Byrnecut and the Abra mining team for achieving this milestone, and everyone involved should be very proud of what they have achieved. It’s also important to acknowledge Pacific Energy and the Abra project team for the faultless commissioning of the power station and completing the full integration of the solar system”.
First ore heading underground has been reached on the 1300mRL access drive. Project to date (PTD) underground development to this point in time was 2,949m and first ore is 250m below the surface. Figure 2 below shows the mine development completed to the end of October 2022. The second underground development Jumbo has commenced at Abra in line with multiple headings being established and underground development is expected to increase accordingly. Underground grade control drilling continues and the 6m diameter return airway shaft drilling has been completed in November through to the surface.
On 20 October, the site changed over to mains power station with the commissioning of the Pacific Energy hybrid 10MW gas/solar/BESS power station. On the 10 November the system was fully integrated with the successful integration of the 6MW solar panels. The mine and general site infrastructure is running on mains power and plant commissioning to date includes the energisation of the crushing/screening sections.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Galena Mining Activities Report For Quarter Ended 30 September 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.
Highlights
- Abra Project 87% complete at end of the Quarter (14% of construction works completed during the Quarter). Project focus remains on underground access to the orebody and completion of the processing plant and remaining surface infrastructure.
- Underground development achieved 771m advance during the Quarter remaining on schedule with the decline reaching 1,300mRL. The decline is 13m below the top of the orebody and 250m below the surface.
- Overall processing plant construction has reached 93% complete. Plant engineering and drafting work is 100% complete and site construction work is 90% complete.
- All key overseas supplied equipment has arrived on site.
- Completed oversubscribed placement to raise A$17.2M.
- US$25M final debt drawdown was completed under the Taurus Debt Facilities.
- Cash balance at Quarter-end A$60.5M.
ABRA BASE METALS MINE (60%-OWNED)
Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.
Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Chen Lin: Silver's Move to US$50 Will be Quick, How I'm Investing Now
Speaking to the Investing News Network, Chen Lin of Lin Asset Management shared his outlook for silver, explaining that the white metal could move quickly to the US$50 per ounce level once market participants realize how large the divide between supply and demand really is.
When asked about the most important drivers for silver right now, he pointed to the solar industry, noting that two to three years ago it was consuming 100 million ounces of silver; that amount rose to 200 million ounces last year.
This year, the Silver Institute is projecting a further 40 million ounces of solar demand, but Lin thinks the sector may end up requiring an extra 100 million ounces, bringing its total usage to 300 million ounces for 2024.
"From all the data I get, it's 100 million ... so from 200 million to 300 million," he said. A new report out of Germany has an even higher projection, forecasting that the solar market could consume 400 million ounces of silver this year.
"My point is that once investors see the huge deficit, they truly see the huge deficit in silver, silver will go to US$50 just like that — just in a heartbeat," Lin said, adding that so far most market participants haven't gotten there.
When asked how he's getting exposure to silver, Lin said he's heavily exposed in the future market. However, he doesn't recommend that path for everyone as the leverage involved can be highly risky.
He's also looking at silver miners, which he believes are cheap. "Silver miners are going to have a huge Q2 — gold miners too, but silver in particular," he said, noting that the average silver price will be much higher than it was in Q1.
"If they are not making money at US$20 (silver), at US$30 suddenly there's a huge profit," he said.
Watch the interview above for more from Lin on his outlook for silver and ways to invest.
Don't forget to follow us @INN_Resource for real-time updates!
Securities Disclosure: I, Charlotte McLeod, hold no direct investment interest in any company mentioned in this article.
Editorial Disclosure: The Investing News Network does not guarantee the accuracy or thoroughness of the information reported in the interviews it conducts. The opinions expressed in these interviews do not reflect the opinions of the Investing News Network and do not constitute investment advice. All readers are encouraged to perform their own due diligence.
Diversifying with Precious Metals: Top Strategies for Silver Investment
Like gold, silver is considered a safe haven for investors and has long been viewed as a hedge against inflation. In addition to its precious metal status, silver has numerous industrial applications, making it an attractive investment target.
Investing in silver offers a plethora of advantages, including portfolio diversification and protection against inflation. Silver's industrial demand, stemming from its exceptional conductivity and utility in various sectors, bolsters its value beyond mere ornamentation. Moreover, its relative affordability compared to gold makes it accessible to a broader range of investors.
Ways to invest in silver
For both long-term and short-term investors, investing in silver can offer several advantages. When currency values decrease, the value of silver often increases. It can also diversify investment portfolios, providing a balance against stocks and bonds, which might perform poorly under certain economic conditions.
Silver has a wide range of industrial applications, including in electronics, solar panels and medical devices. This industrial demand can drive the price up, adding to its investment appeal. Demand also fluctuates based on technological advancements and changes in manufacturing processes.
Investors looking at this precious metal will benefit from a deeper understanding of the different avenues for investing in silver and the pros and cons of each option.
Mining stocks
While silver itself is a valuable commodity, silver mining stocks offer a different avenue for potential growth. One of the main benefits of investing in silver mining companies is the leverage they can offer. As the price of silver increases, mining companies can potentially see a significant rise in profits, which may be reflected in the stock price. Additionally, mining stocks often come with the possibility of dividend payments, providing an income stream for investors.
However, there are also risks to consider. Mining companies are subject to operational risks, such as the cost of operations and potential disruptions. Moreover, their performance is not only tied to the price of silver but also to the success of their individual operations and management decisions. Market volatility can also affect mining stocks, making them a potentially riskier investment compared to holding physical silver.
For those interested in exploring silver mining stocks, companies like Pan American Silver (TSX:PAAS,NASDAQ:PAAS) and Hecla Mining (NYSE:HL) are notable examples. These companies have established operations and a history in the market. It's important to conduct thorough research and consider the stability and growth potential of any company before investing.
Silver coins and bars
Silver is generally more affordable than gold, making it accessible to a wider range of investors, including those who are just starting out. Tangible assets like bullion, coins and bars can be particularly appealing in times of economic uncertainty or market volatility. Unlike financial instruments, physical silver doesn't depend on another party's solvency, and can be bought and sold privately.
However, tangible silver requires secure storage, which can be costly. Insurance also adds to the investment's overall cost. The sale of such silver is often subject to capital gains tax, and the tax treatment can be less favorable compared to other investment vehicles. In some jurisdictions, silver is taxed at higher rates.
Investors should be aware that selling large quantities of physical silver can be challenging and time consuming. Finding a buyer at the desired price may take time, and this investment requires active management from storage to selling. Coins, like the American Silver Eagle or Canadian Maple Leaf, are recognized worldwide, enhancing their liquidity.
ETFs and mutual funds
Silver exchange-traded funds (ETFs) can be a gleaming prospect for those looking to diversify their portfolio with precious metals. Silver ETFs offer a convenient way to gain exposure to the silver market without the need to physically hold the metal. The Motley Fool recommends considering ETFs that provide exposure to a broad array of silver companies.
The iShares Silver Trust (ARCA:SLV), Global X Silver Miners ETF (ARCA:SIL) and Amplify Junior Silver Miners ETF (ARCA:SILJ) are names to consider.
One of the main advantages of silver ETFs is the ease of trade. Unlike physical silver, ETFs can be bought and sold like stocks on major exchanges, providing liquidity and flexibility.
Royalties and streaming companies
Royalty companies provide upfront capital to mining companies in exchange for a percentage of the revenue generated from the mine. Streaming companies, on the other hand, receive physical silver at a predetermined price, providing a steady supply and a hedge against silver price volatility.
One of the main advantages is risk reduction. Unlike traditional mining companies, royalty and streaming companies are not directly exposed to the operational challenges of mining. This translates to lower operational costs and reduced risks such as labor disputes or geopolitical complications. Companies like Franco-Nevada (TSX:FNV,NYSE:FNV) and Wheaton Precious Metal (TSX:WPM,NYSE:WPM) have established themselves as leading players in the industry, offering investors stability and exposure to multiple mining operations.
Silver Crown Royalties has positioned itself as a notable player in the silver investment landscape. As a revenue-generating, silver-only royalty company, Silver Crown Royalties has demonstrated strategic growth initiatives aimed at maximizing shareholder value.
“We're the only company that is a pure silver proxy that's an equity vehicle. So unlike investing in silver metals, because we have organic growth, we have exploration upside, we have all the things that a company would have. We also aim to pay a dividend. There's no other vehicle out there that has that,” Peter Bures, founder, chairman and CEO of Silver Crown Royalties said of his company’s value proposition.
Founded by industry veterans, Silver Crown Royalties is a pre-IPO stage company, focusing on silver as byproduct credits. The company's recent amalgamation agreement and upsizing of its royalty in the Elk Gold Mine underscore its commitment to expanding its portfolio and enhancing its revenue streams.
Investor takeaway
Investing in silver can be a wise decision for those looking to diversify their portfolio and protect against economic uncertainties. With various avenues available, from physical silver to silver streaming companies, investors have the flexibility to choose the path that best aligns with their investment strategy and risk tolerance.
This INNSpired article is sponsored by Silver Crown Royalties. This INNSpired article provides information which was sourced by the Investing News Network (INN) and approved by Silver Crown Royaltiesin order to help investors learn more about the company. Silver Crown Royaltiesis a client of INN. The company’s campaign fees pay for INN to create and update this INNSpired article.
This INNSpired article was written according to INN editorial standards to educate investors.
INN does not provide investment advice and the information on this profile should not be considered a recommendation to buy or sell any security. INN does not endorse or recommend the business, products, services or securities of any company profiled.
The information contained here is for information purposes only and is not to be construed as an offer or solicitation for the sale or purchase of securities. Readers should conduct their own research for all information publicly available concerning the company. Prior to making any investment decision, it is recommended that readers consult directly with Silver Crown Royalties and seek advice from a qualified investment advisor.
Sorby Hills Project FEED Study
Boab Metals Limited (ASX: BML) (“Boab” or the “Company”) is pleased to announce the results of its Front-End Engineering & Design (“FEED”) Study for its 75% owned Sorby Hills Lead-Silver- Zinc Project (“Sorby Hills” or “the Project”), located in the Kimberley Region of Western Australia. The FEED Study augments and enhances the Sorby Hills Definitive Feasibility Study (“DFS”) released by the Company in January 2023.
HIGHLIGHTS
Project updates (excluding any change in macroeconomic assumptions) have delivered an increase of +A$73M Net Cash Flow and +A$41M NPV8 compared to the DFS.
Key Base Case Project Metrics include upfront Capital Expenditure of A$264M, average C1 Cost of US$ 0.36/lb payable Lead (including silver credits), pre-tax NPV8 of A$411M, pre-tax IRR of 37%, and average annual EBITDA of A$126M.
Importantly, the net change to pre-production Capital Expenditure is limited and project pre- tax cash flows over the initial 5 years of production have improved by +A$150M providing a stronger profile to support debt financing.
Assuming current spot pricing1 for Lead, Silver, Exchange Rate and current Benchmark Lead Treatment and Silver Refining Charges results in an NPV8 of A$596M, pre-tax IRR of 47% and average annual EBITDA of A$160M.
Key Project updates include:
- Updated post FEED pricing for the Process Plant EPC Contract provided by GR Engineering Service (“GRES”).
- Updated mining schedule bringing forward mining of the high-grade Norton Deposit.
- Updated metal recovery and concentrate grades for the Norton Deposit based on new metallurgical testwork on core recovered during the Phase VII drilling program.
- Updated pricing for the Mining and Earthworks Contracts provided on a bundled basis and based on the optimised site layout and mining schedule.
- Updated tailings strategy with above-ground tailings disposal being employed for the Life of Mine as opposed to in-pit deposition previously adopted in the DFS.
Boab Managing Director and CEO, Simon Noon, stated:
“Following the DFS, we identified clear opportunities to optimise and de-risk the Project both technically and economically. Over the past year, we have pursued these opportunities in conjunction with completing Front End Engineering & Design on our Process Plant with GRES.
We are pleased to present the results of our work during this period in the form of this FEED Study. We now look forward to accelerating our engagement with financiers and further advancing Sorby Hills toward a Final Investment Decision.”
Click here for the full ASX Release
This article includes content from Boab Metals, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Top Stories This Week: Expert Calls for US$50 Silver, Paladin Offers C$1.14 Billion for Fission
Strength in the US dollar briefly pushed the gold price below US$2,300 per ounce midway through the week, but the yellow metal soon bounced back, finishing Friday (June 28) at the US$2,325 level.
The latest US Personal Consumption Expenditures (PCE) price index data came out that day, and it shows that in May core PCE was up 0.1 percent month-on-month and 2.6 percent year-on-year — in line with expectations.
PCE is the US Federal Reserve's preferred measure of inflation, and can help shed light on its interest rate plans.
“The lack of surprise in today’s PCE number is a relief and will be welcomed by the Fed,” Seema Shah, chief global strategist at Principal Asset Management, told CNBC after the new numbers were released.
Even so, the Fed's path forward isn't yet clear. "A further deceleration in inflation, ideally coupled with additional evidence of labor market softening, will be necessary to pave the way for a first rate cut in September," she added.
Currently CME Group's (NASDAQ:CME) FedWatch tool shows about a 58 percent likelihood of a cut in September.
Silver continued to trade below US$30 per ounce this week, although some experts believe the white metal has much further to go. The Investing News Network recently heard from Chen Lin of Lin Asset Management, who explained that it could move quickly to US$50 once market participants realize how large the divide between supply and demand really is.
Here's how he explained it:
"My point is once investors see the huge deficit, they see truly the huge deficit in silver, silver will go to US$50 just like that — just in a heartbeat. So I hope while you're enjoying the summer you don't miss one of the greatest runs of silver" — Chen Lin, Lin Asset Management
Bullet briefing — Victoria Gold shares drop, Paladin to buy Fission
Heap leach pad fails at Eagle gold mine
Shares of Victoria Gold (TSX:VGCX,OTC Pink:VITFF) fell over 80 percent this week after a heap leach pad failure and landslide at its Eagle gold mine in Canada's Yukon. No injuries were reported at the site, but Trevor Ellis, mayor of the nearby Mayo community, described the situation as "catastrophic" in an interview with CBC.
The company has suspended operations at Eagle as it works to assess the situation, but questions are unsurprisingly being raised about the mine's future, and about how the incident may impact Yukon's mining sector.
Paladin Energy to acquire Fission Uranium
Australia's Paladin Energy (ASX:PDN,OTCQX:PALAF) revealed plans to acquire Fission Uranium (TSX:FCU,OTCQX:FCUUF) in a deal valued at C$1.14 billion. Announced on Monday (June 24), the move will give Paladin ownership of Fission's Patterson Lake South project in Saskatchewan's Athabasca Basin, a well-known uranium hotspot.
Paladin's main asset is its 75 percent owned Langer Heinrich uranium mine in Namibia, where it recently restarted production. The company also has a portfolio of exploration and development assets in Canada and Namibia.
The companies are aiming to complete the transaction in the September quarter, although it remains to be seen whether it will be voted through. Some analysts have suggested that shareholders may want to see a better offer.
Want more YouTube content? Check out our expert market commentary playlist, which features interviews with key figures in the resource space. If there's someone you'd like to see us interview, please send an email to cmcleod@investingnews.com.
And don't forget to follow us @INN_Resource for real-time updates!
Securities Disclosure: I, Charlotte McLeod, hold no direct investment interest in any company mentioned in this article.
Editorial Disclosure: The Investing News Network does not guarantee the accuracy or thoroughness of the information reported in the interviews it conducts. The opinions expressed in these interviews do not reflect the opinions of the Investing News Network and do not constitute investment advice. All readers are encouraged to perform their own due diligence.
Thomson Project Sold for $200,000 Plus 1.5% Net Smelter Royalty
Divestment of non-core asset will streamline Eastern Metals’ asset portfolio, enabling it to focus on exploration of its high-potential Cobar and Arunta projects
Eastern Metals Ltd (ASX: EMS) (“Eastern Metals” or “the Company”) is pleased to announce that it has signed a binding Heads of Agreement (“HoA”) for the sale of the Thomson Project in New South Wales to Legacy Minerals Holdings Ltd (ASX: LGM, “Legacy Minerals”) for $200,000 in cash and a 1.5% Net Smelter Royalty (“NSR”).
- Eastern Metals has finalised a binding agreement to sell its Thomson Project in NSW to Legacy Minerals Holdings Ltd (ASX:LGM) for $200,000 in cash plus a 1.5% royalty.
- The cash sale allows Eastern Metals to focus its funds and human resources on the exploration of the Cobar and Arunta Projects.
- Approvals process is underway to drill newly identified high-priority targets at the Cobar Project in NSW, with work programs also progressing at the Arunta Project in the NT following the recent award of a co-funding grant from the NTGS1.
The sale will streamline Eastern Metals’ asset portfolio, enabling the Company to focus its funds and resources on the high-potential, advanced base metals Cobar Project in New South Wales and Arunta Project in the Northern Territory.
Eastern Metals’ Chief Executive Officer Ley Kingdom said: “The sale of the Thomson Project to Legacy Minerals represents a great outcome for Eastern Metals, providing the Company with an all- cash consideration of $200,000 plus a 1.5% NSR, while enabling us to prioritise our efforts on the more advanced assets within our portfolio.
“The prioritisation of time and funds is vital for successful exploration companies. With our prospective portfolio of tenements, we are constantly evaluating which projects have the best potential for exploration success and shareholder growth. In the near future, this includes continuing to progress Browns Reef and Home of Bullion through target generation and drilling. We wish Legacy Minerals all the best with the acquisition, which represents a complementary land position to their existing projects in NSW where they are actively exploring on a number of fronts.”
Click here for the full ASX Release
This article includes content from Eastern Metals, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Investor Presentation Gold Coast Investment Showcase
Eastern Metals Ltd (ASX:EMS) (“Eastern Metals” or “the Company”) is pleased to advise that its Chief Executive Officer, Ley Kingdom, will be presenting at Vertical Events’ Gold Coast Investment Showcase on Thursday 20 June 2024 at 11:30am AEST.
Investors can register to watch a livestream of the conference at: https://www.goldcoastinvestmentshowcase.com.au/livestreamingregistration
A copy of the conference presentation is provided below.
Click here for the full ASX Release
This article includes content from Eastern Metals, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Latest News
Galena Mining Investor Kit
- Corporate info
- Insights
- Growth strategies
- Upcoming projects
GET YOUR FREE INVESTOR KIT
Latest Press Releases
Related News
TOP STOCKS
Investing News Network websites or approved third-party tools use cookies. Please refer to the cookie policy for collected data, privacy and GDPR compliance. By continuing to browse the site, you agree to our use of cookies.