Galena Mining

Activities Report For The Quarter Ended 30 June 2023

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 June 2023 (the “Quarter”), primarily focused on the ongoing production ramp-up of both the underground mine and the processing plant to achieve steady-state production in the second half of 2023, at its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS

  • Strong recovery achieved with May and June physicals following limited activities in April due to rainfall events. Ore mined of 194,644t at 5.4% Pb grade and 16.9g/t Ag grade and processed 190,258t at 5.1% Pb grade and 19.0g/t Ag grade for the Quarter.
  • Second and third in-specification lead concentrate shipments of ~5kt each completed in the Quarter, doubling revenue from the previous quarter to ~A$20.4 million.
  • July month to date on track to achieve first positive monthly operating cash flows with over 90% of the next ~9-10kt concentrate shipment produced and committed shipment set for loading between 28 July and 4 August.
  • Underground development achieved 1,583m advance during the Quarter with the decline reaching 1,234mRL (312m vertically below the surface). Underground stope production achieved 81,592t at 6.3% Pb grade. Pb grade is slowly improving and will continue to do so in the coming months as new work areas are established and the ratio of stoping ore to development ore increases to required production levels.
  • Cash balance at Quarter-end of A$19.3 million.
  • Galena completed an oversubscribed placement to provide additional working capital funding for the Abra ramp-up.
  • September quarter mining plans set to achieve over 2,000m development and over 250,000t stope production expecting to process over 300,000t of ore as next quarter ramp-up milestones. Targeting ~25-30kt of lead concentrate shipments expected to generate positive operating cash flows.

Managing Director, Tony James commented, “We made a strong recovery from no production in April to set new project highs in both May and June, and we expect to achieve first positive operating cash flows in July. The plant is showing its capacity to process everything put in front of it so far and the focus remains on increasing mine production levels. The key to the mine reaching the levels required is good planning and execution. With the mine plans at 90% grade control status through to January 2024 we see the pathway well laid out to achieve our targets. Some very strong technical work has been completed to increase our confidence in hitting our targets.”

ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena and 40% owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment achieved in March 2023.

Review of operations

Notes:

1. Total Recordable Injury Frequency Rate (“TRIFR”) and Notifiable Incident Frequency Rate (“NIFR”) are the 12-month moving average at the end of each quarter calculated per million work hours.

2. Concentrate sales and average lead price received initially based on provisional invoices and subsequently updated with final invoices, including final assays and quotational period adjustments.

3. Payable lead and silver based on 95% metal payability subject to standard deductions (i.e., 3 units for lead and 50g/t for silver).

4. C1 costs include mining costs, processing costs, site general and administration costs, transport, logistics and shipping costs, and treatment and refining charges, adjusted for inventory movements and net of silver by-product credits.

5. All-in sustaining costs include C1 Costs plus royalties, corporate general and administration costs, sustaining capital and capitalised mine development costs. All-in sustaining costs exclude growth capital and exploration costs.

6. Abra Project construction works were completed by the end of the December 2022 quarter (see Galena ASX announcements of 10 January 2023 and 13 January 2023).

During the Quarter, new quarter high mining and processing production levels were achieved. This achievement also takes into account the limited activities in April 2023 due to the rainfall issues affecting access to the Abra mine site.

In June, a mine development record was set with 646m of lateral and vertical development achieved during the month. A third Jumbo commenced in the mine in June with the aim of increasing the mine’s monthly development rates to 800m per month during the September quarter.

The mine delivered 194,644t (April: 31,915t, May: 81,014t and June: 81,715t) at 5.4% Pb grade to the plant during the Quarter, including stope production ore of 81,592t at 6.3% Pb grade. The higher development ore during the Quarter is consistent with the ramp-up of mine production as new stoping areas are established. In general, mine production in the Quarter was also affected by congestion in the available work areas, production delays associated with upgrading secondary ventilation networks and loader availability. These impediments were continually rectified during the quarter.

The plant effectively processed all the ore delivered from the mine during the Quarter with 190,258t processed (April: Nil, May: 102,719t and June: 87,539t). 12,468t of concentrate was produced containing 8,070t Pb and 63,122oz Ag. Plant availability in May was 99% and in June 86%. A flotation blower (compressor) breakdown caused the lower availability in June. The plant was able to operate consistently at the 150dmt/hr level during the Quarter.

The mine call grade for ore processed during the Quarter was estimated at 5.4% Pb, which is approximately 0.3% Pb higher than the reconciled processing grade of 5.1% Pb.

Considerable technical improvements were achieved during the Quarter with detailed resource modelling and mine planning work completed. A new Mineral Resource Estimate (“MRE”) is expected to be finalised in the coming weeks which will include all the recent underground drilling and revised geological modelling. This work will lead into a new Ore Reserve estimate and 2024 budget completion in the December quarter. Three month rolling mine plans have been established and the mine planning for the remainder of 2023 is well advanced with 90% of that plan built on grade control drilling down to a 12.5x12.5m spacing.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Chen Lin, silver bars.

Chen Lin: Silver's Move to US$50 Will be Quick, How I'm Investing Now

Speaking to the Investing News Network, Chen Lin of Lin Asset Management shared his outlook for silver, explaining that the white metal could move quickly to the US$50 per ounce level once market participants realize how large the divide between supply and demand really is.

When asked about the most important drivers for silver right now, he pointed to the solar industry, noting that two to three years ago it was consuming 100 million ounces of silver; that amount rose to 200 million ounces last year.

This year, the Silver Institute is projecting a further 40 million ounces of solar demand, but Lin thinks the sector may end up requiring an extra 100 million ounces, bringing its total usage to 300 million ounces for 2024.

"From all the data I get, it's 100 million ... so from 200 million to 300 million," he said. A new report out of Germany has an even higher projection, forecasting that the solar market could consume 400 million ounces of silver this year.

Keep reading...Show less
Miner holding silver.

Diversifying with Precious Metals: Top Strategies for Silver Investment

Like gold, silver is considered a safe haven for investors and has long been viewed as a hedge against inflation. In addition to its precious metal status, silver has numerous industrial applications, making it an attractive investment target.

Investing in silver offers a plethora of advantages, including portfolio diversification and protection against inflation. Silver's industrial demand, stemming from its exceptional conductivity and utility in various sectors, bolsters its value beyond mere ornamentation. Moreover, its relative affordability compared to gold makes it accessible to a broader range of investors.

Keep reading...Show less
Boab Metals

Sorby Hills Project FEED Study

Boab Metals Limited (ASX: BML) (“Boab” or the “Company”) is pleased to announce the results of its Front-End Engineering & Design (“FEED”) Study for its 75% owned Sorby Hills Lead-Silver- Zinc Project (“Sorby Hills” or “the Project”), located in the Kimberley Region of Western Australia. The FEED Study augments and enhances the Sorby Hills Definitive Feasibility Study (“DFS”) released by the Company in January 2023.

Keep reading...Show less
Hands shaking with Paladin Energy and Fission Uranium logos.

Top Stories This Week: Expert Calls for US$50 Silver, Paladin Offers C$1.14 Billion for Fission

Strength in the US dollar briefly pushed the gold price below US$2,300 per ounce midway through the week, but the yellow metal soon bounced back, finishing Friday (June 28) at the US$2,325 level.

The latest US Personal Consumption Expenditures (PCE) price index data came out that day, and it shows that in May core PCE was up 0.1 percent month-on-month and 2.6 percent year-on-year — in line with expectations.

PCE is the US Federal Reserve's preferred measure of inflation, and can help shed light on its interest rate plans.

Keep reading...Show less
Eastern Metals

Thomson Project Sold for $200,000 Plus 1.5% Net Smelter Royalty

Divestment of non-core asset will streamline Eastern Metals’ asset portfolio, enabling it to focus on exploration of its high-potential Cobar and Arunta projects

Eastern Metals Ltd (ASX: EMS) (“Eastern Metals” or “the Company”) is pleased to announce that it has signed a binding Heads of Agreement (“HoA”) for the sale of the Thomson Project in New South Wales to Legacy Minerals Holdings Ltd (ASX: LGM, “Legacy Minerals”) for $200,000 in cash and a 1.5% Net Smelter Royalty (“NSR”).

Keep reading...Show less
Eastern Metals

Investor Presentation Gold Coast Investment Showcase

Eastern Metals Ltd (ASX:EMS) (“Eastern Metals” or “the Company”) is pleased to advise that its Chief Executive Officer, Ley Kingdom, will be presenting at Vertical Events’ Gold Coast Investment Showcase on Thursday 20 June 2024 at 11:30am AEST.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×