Galena Mining

Abra Construction 78% Complete at End of July

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 78% complete as of 31 July 2022. New milestones have been achieved with the commencement of the installation of the ball-mill components and total underground development passing 2km in early August.


Managing Director, Tony James commented, “Construction activities have progressed past 78% complete. Most of the concrete work has been completed and structural steel installation increased to 352 tonnes (72% complete). Plant construction work is quickly progressing into the mechanical, piping, and electrical fit out stages. It’s also pleasing to see the progress being made with the operational readiness activities including first fills and critical spares, with orders placed for over 75% of the items”.

Figure 1 – Abra ball mill installation (photo: 10 August).

Three other announcements were released by the company between this monthly update and the previous monthly update dated 18 July 2022. The first was “Re-release: Abra Initial Production Guidance” (ASX: 25 July 2022). The second was “Galena Successfully Raises

$17 Million” (ASX: 26 July 2022) and “Diggers and Dealers Investor Presentation” (ASX: 1 August 2022).

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 85% complete. As previously advised, the remaining items on the key equipment order list shown in Table 1 below which are currently not received are the flotation cells and the regrind mill. The flotation cells and drive mechanisms are currently in shipment with 2 separate shipments delivering the flotation equipment to Fremantle. The flotation cells (bulk shipment) are currently expected to arrive by the 2nd September and the flotation drive mechanisms (container shipment) has arrived in Perth. The regrind mill is currently shipping from Germany and is now expected to arrive in Melbourne by 20th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. These revised arrival dates do not affect the project construction timelines.

Table Notes – All items with strike through have been delivered (1) Flotation equipment shipped in 2 separate parts. Flotation cells ETA now 2 September and Flotation drive mechanisms have arrived in Perth. (2) Regrind Mill ETA Melbourne 17 August for final assembly by Glencore Technology.

Table 1 – Key equipment order and delivery schedule from overseas suppliers.

Mine decline development continued in the East Decline and the 1,375mRL diamond drill drive during July. A total of 243 metres was developed during July with the East decline reaching 1,360mRL. During July the second leg of the mines escape way system was drilled (1.5-meter raise bore) down to 1,400mRL (150m below surface). By the end of July, 16 underground diamond drill holes have been completed.

Figure 2 - Progress of the Abra underground mine development to 31 July (yellow).

In surface bulk earthworks, good progress continued with the tailing’s storage facility (“TSF”) passing 50% completion. The final works package associated with the remaining non- processing infrastructure is progressing as planned with the power station reaching 81% complete.

Owners' costs and contingencies remain within budget.

Figure 3 – Abra TSF construction.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)

Galena Mining

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
Closeup of multiple US$100 bills in a row.

Silver X Secures US$50 Million to Expand Peru Project

Silver X Mining (TSXV:AGX,OTCQB:AGXPF) has tapped investor demand for exposure to the rising silver price, closing a US$50.4 million financing to fund expansion at its flagship project in Peru.It completed an oversubscribed brokered private placement of secured convertible debentures on... Keep Reading...
Vox Royalty Announces Inclusion in MVIS Global Junior Gold Miners Index and VanEck Junior Gold Miners ETF

Vox Royalty Announces Inclusion in MVIS Global Junior Gold Miners Index and VanEck Junior Gold Miners ETF

DENVER, CO / ACCESS Newswire / March 16, 2026 / Vox Royalty Corp. (NASDAQ:VOXR)(TSX:VOXR) ("Vox" or the "Company"), a returns-focused mining royalty and streaming company, is pleased to announce that it has been added to the MVIS® Global Junior Gold Miners Index ("MVGDXJ"), the underlying... Keep Reading...
Ted Butler, silver bars.

Ted Butler: Silver Blow-Off Top Years Away, How to Play Volatility

Precious metals analyst Ted Butler shares his thoughts on where the silver price will go next after running into triple digits and then pulling back. He expects a period of consolidation, but emphasized that the white metal's bull run isn't over. "I maintain that we are still relatively early in... Keep Reading...
Nine Mile Metals

Nine Mile Metals Announces Certified Assays from DDH-WD-25-01 of 3.83% CuEq Over 22.65 Meters (39.52 g/t Ag, 0.96 g/t Au, 0.99% Cu, 2.25% Pb, 1.61% Zn) and 4.33% CuEq Over 17.65 Meters (42.5 g/t Ag, 1.01 g/t Au, 1.2% Cu, 2.62% Pb, 2.05% Zn) Including 1.21 g/t Au and 50.33 g/t Ag Over 13.00 Meters

NINE MILE METALS LTD. (CSE: NINE) (OTC Pink: VMSXF) (FSE: KQ9) (the "Company" or "Nine Mile") is pleased to announce it has received certified assays for drill hole WD-25-01 at the Wedge Mine situated in the renowned Bathurst Mining Camp, New Brunswick (BMC).WD-25-01 HIGHLIGHTS:DDH WD-25-01 was... Keep Reading...
John Feneck, gold bars.

John Feneck: Gold, Silver to Retest Highs, "Don't Get Off the Horse"

John Feneck, portfolio manager and consultant at Feneck Consulting, explains why he expects gold and silver prices to retest January's highs, noting that he sees investors beginning to rotate away from the tech sector and toward commodities. "My suggestion is don't get off the horse, right?" he... Keep Reading...
Silver bars on shiny metallic surface.

Silver Stocks: 5 Biggest Silver-mining Companies in 2026

Silver mining companies are being supported by a silver price bull run in 2026. After climbing through 2025, silver broke its all-time high set in 1980 in October before reaching a new high of US$121.62 per ounce on January 29.The factors driving the metal's rise remain, most notably tightening... Keep Reading...

Interactive Chart

Latest Press Releases

Related News