Galena Mining

Abra Construction 78% Complete at End of July

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 78% complete as of 31 July 2022. New milestones have been achieved with the commencement of the installation of the ball-mill components and total underground development passing 2km in early August.


Managing Director, Tony James commented, “Construction activities have progressed past 78% complete. Most of the concrete work has been completed and structural steel installation increased to 352 tonnes (72% complete). Plant construction work is quickly progressing into the mechanical, piping, and electrical fit out stages. It’s also pleasing to see the progress being made with the operational readiness activities including first fills and critical spares, with orders placed for over 75% of the items”.

Figure 1 – Abra ball mill installation (photo: 10 August).

Three other announcements were released by the company between this monthly update and the previous monthly update dated 18 July 2022. The first was “Re-release: Abra Initial Production Guidance” (ASX: 25 July 2022). The second was “Galena Successfully Raises

$17 Million” (ASX: 26 July 2022) and “Diggers and Dealers Investor Presentation” (ASX: 1 August 2022).

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 85% complete. As previously advised, the remaining items on the key equipment order list shown in Table 1 below which are currently not received are the flotation cells and the regrind mill. The flotation cells and drive mechanisms are currently in shipment with 2 separate shipments delivering the flotation equipment to Fremantle. The flotation cells (bulk shipment) are currently expected to arrive by the 2nd September and the flotation drive mechanisms (container shipment) has arrived in Perth. The regrind mill is currently shipping from Germany and is now expected to arrive in Melbourne by 20th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. These revised arrival dates do not affect the project construction timelines.

Table Notes – All items with strike through have been delivered (1) Flotation equipment shipped in 2 separate parts. Flotation cells ETA now 2 September and Flotation drive mechanisms have arrived in Perth. (2) Regrind Mill ETA Melbourne 17 August for final assembly by Glencore Technology.

Table 1 – Key equipment order and delivery schedule from overseas suppliers.

Mine decline development continued in the East Decline and the 1,375mRL diamond drill drive during July. A total of 243 metres was developed during July with the East decline reaching 1,360mRL. During July the second leg of the mines escape way system was drilled (1.5-meter raise bore) down to 1,400mRL (150m below surface). By the end of July, 16 underground diamond drill holes have been completed.

Figure 2 - Progress of the Abra underground mine development to 31 July (yellow).

In surface bulk earthworks, good progress continued with the tailing’s storage facility (“TSF”) passing 50% completion. The final works package associated with the remaining non- processing infrastructure is progressing as planned with the power station reaching 81% complete.

Owners' costs and contingencies remain within budget.

Figure 3 – Abra TSF construction.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)

Galena Mining

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
Prince Reports 27.43 Metres Grading 93.7 g/t Silver, 12.0% Mn, 2.29% Pb and 2.48% Zn at Its Prince Silver Project in Nevada;

Prince Reports 27.43 Metres Grading 93.7 g/t Silver, 12.0% Mn, 2.29% Pb and 2.48% Zn at Its Prince Silver Project in Nevada;

Mobilizes Third RC Drill Rig to Accelerate Ongoing 9,000-metre Drill Program

Prince Silver Corp. (CSE: PRNC) (OTCQX: PRNCF) (FSE: T130) ("Prince Silver" or the "Company") is pleased to announce additional assay results from its ongoing 9,000-metre reverse circulation ("RC") drilling program at the Company's Prince Silver Project ("Prince" or the "Prince Project"),... Keep Reading...
Three wooden blocks with black letters "M&A" rest on a computer keyboard.

Elemental Secures Panuco Silver-Gold Royalty in US$239 Million Vizsla Deal

Elemental Royalty (TSX:ELE,NASDAQ:ELE) has inked a US$239 million deal to acquire Vizsla Royalties (TSXV:VROY,OTCQX:VROYF), securing long-life exposure to the Panuco silver-gold project. The acquisition grants Elemental an uncapped 2 to 3.5 percent net smelter return royalty on the Mexico-based... Keep Reading...
A metallic paper airplane rests on a smooth light gray surface.

Record Silver Price a Key Q1 Tailwind for Miners

Following an unprecedented first quarter that saw silver prices break into triple digits before sharply correcting, the sector’s top producers registered massive cash generation and bolstered balance sheets. Silver achieved a historic milestone early in the first quarter, surging past US$100 an... Keep Reading...
Silver bars on shiny metallic surface.

Silver Stocks: 5 Biggest Silver-mining Companies in 2026

Silver mining companies are being supported by a silver price bull run in 2026. After climbing through 2025, silver broke its all-time high set in 1980 in October before reaching a new high of US$121.62 per ounce on January 29.The factors driving the metal's rise remain, most notably tightening... Keep Reading...
Lynette Zang, gold and silver bars.

Lynette Zang: Silver Fuse, Gold Anchor — This Currency Lifecycle is Ending

Lynette Zang, founder and CEO of Zang International, explains what gold and silver are saying about the world today, noting that while spot prices for the precious metals are down, they are on track to eventually assume their true fundamental value. "What I really want people to understand is... Keep Reading...

Interactive Chart

Latest Press Releases

Related News