Galena Mining

Abra Construction 78% Complete at End of July

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 78% complete as of 31 July 2022. New milestones have been achieved with the commencement of the installation of the ball-mill components and total underground development passing 2km in early August.


Managing Director, Tony James commented, “Construction activities have progressed past 78% complete. Most of the concrete work has been completed and structural steel installation increased to 352 tonnes (72% complete). Plant construction work is quickly progressing into the mechanical, piping, and electrical fit out stages. It’s also pleasing to see the progress being made with the operational readiness activities including first fills and critical spares, with orders placed for over 75% of the items”.

Figure 1 – Abra ball mill installation (photo: 10 August).

Three other announcements were released by the company between this monthly update and the previous monthly update dated 18 July 2022. The first was “Re-release: Abra Initial Production Guidance” (ASX: 25 July 2022). The second was “Galena Successfully Raises

$17 Million” (ASX: 26 July 2022) and “Diggers and Dealers Investor Presentation” (ASX: 1 August 2022).

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 85% complete. As previously advised, the remaining items on the key equipment order list shown in Table 1 below which are currently not received are the flotation cells and the regrind mill. The flotation cells and drive mechanisms are currently in shipment with 2 separate shipments delivering the flotation equipment to Fremantle. The flotation cells (bulk shipment) are currently expected to arrive by the 2nd September and the flotation drive mechanisms (container shipment) has arrived in Perth. The regrind mill is currently shipping from Germany and is now expected to arrive in Melbourne by 20th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. These revised arrival dates do not affect the project construction timelines.

Table Notes – All items with strike through have been delivered (1) Flotation equipment shipped in 2 separate parts. Flotation cells ETA now 2 September and Flotation drive mechanisms have arrived in Perth. (2) Regrind Mill ETA Melbourne 17 August for final assembly by Glencore Technology.

Table 1 – Key equipment order and delivery schedule from overseas suppliers.

Mine decline development continued in the East Decline and the 1,375mRL diamond drill drive during July. A total of 243 metres was developed during July with the East decline reaching 1,360mRL. During July the second leg of the mines escape way system was drilled (1.5-meter raise bore) down to 1,400mRL (150m below surface). By the end of July, 16 underground diamond drill holes have been completed.

Figure 2 - Progress of the Abra underground mine development to 31 July (yellow).

In surface bulk earthworks, good progress continued with the tailing’s storage facility (“TSF”) passing 50% completion. The final works package associated with the remaining non- processing infrastructure is progressing as planned with the power station reaching 81% complete.

Owners' costs and contingencies remain within budget.

Figure 3 – Abra TSF construction.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less

Endeavour Silver Announces Q1 2024 Financial Results; Earnings Call at 10AM PDT Today

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) announces its financial and operating results for the three months ended March 31, 2024. All dollar amounts are in US dollars ($).

"We are pleased to report a solid start to the year with consolidated production and operating costs meeting expectations," stated Dan Dickson, CEO of Endeavour Silver. "Guanacevi continues to perform well, generating operating cash flow which we are reinvesting in the business. The higher precious metal prices will further enhance our cash flow, as we advance Terronera towards commissioning in late 2024."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Pan American Silver Announces Results of Annual General and Special Meeting

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") announces the voting results from its annual general and special meeting of shareholders held on May 8, 2024, in Vancouver, British Columbia (the "Meeting"). Each of the matters voted upon at the Meeting are described in detail in the Company's Management Information Circular dated March 14, 2024, which is available on the Company's website at https://www.panamericansilver.com/invest/financial-reports-and-filings/ .

A total of 239,393,813 common shares were represented at the meeting, being 65.65% of the Company's issued and outstanding common shares as at the record date. Shareholders voted in favour of all matters brought before the meeting, including setting the number of directors at nine, the election of management's nominees as directors, the appointment of auditors for the ensuing year, and the acceptance of the Company's approach to executive compensation, known as "say-on-pay".

News Provided by Business Wire via QuoteMedia

Keep reading...Show less

Pan American Silver Reports First Quarter 2024 Results

All amounts expressed in U.S. dollars unless otherwise indicated. Unaudited tabular amounts are in millions of U.S. dollars and thousands of shares, options, and warrants, except per share amounts, unless otherwise noted.

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") reports unaudited results for the quarter ended March 31, 2024 ("Q1 2024").

News Provided by Business Wire via QuoteMedia

Keep reading...Show less

First Majestic Announces Financial Results for Q1 2024 and Quarterly Dividend Payment

First Majestic Silver Corp. (NYSE: AG) (TSX: FR) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the unaudited condensed interim consolidated financial results of the Company for the first quarter ended March 31, 2024. The full version of the financial statements and the management's discussion and analysis can be viewed on the Company's website at www.firstmajestic.com or on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.govedgar. All amounts are in U.S. dollars unless stated otherwise.

FIRST QUARTER HIGHLIGHTS

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Fortuna reports financial results for the first quarter of 2024

(All amounts are expressed in US dollars, tabular amounts in millions, unless otherwise stated)

Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) ("Fortuna" or the "Company") today reported its financial and operating results for the first quarter of 2024.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Two silver bars weighing 1000 grams in front of price charts.

Should You Invest in Silver Bullion? (Updated 2024)

Investing in silver bullion has pros and cons, and what’s right for one investor may not work for another.

Interest in the silver market tends to flourish whenever the silver price increases, with investors beginning to wonder if it is the right time to add physical silver to their investment portfolios. While silver can be volatile, the precious metal is also seen as a safe-haven asset, similar to its sister metal gold. Safe-haven investments can offer protection in times of uncertainty, and with tensions running high, they could be a good choice for those looking to preserve their wealth in difficult times.

With those factors in mind, let’s look at the pros and cons of buying silver bullion.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×