Galena Mining

Abra Construction 78% Complete at End of July

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 78% complete as of 31 July 2022. New milestones have been achieved with the commencement of the installation of the ball-mill components and total underground development passing 2km in early August.


Managing Director, Tony James commented, “Construction activities have progressed past 78% complete. Most of the concrete work has been completed and structural steel installation increased to 352 tonnes (72% complete). Plant construction work is quickly progressing into the mechanical, piping, and electrical fit out stages. It’s also pleasing to see the progress being made with the operational readiness activities including first fills and critical spares, with orders placed for over 75% of the items”.

Figure 1 – Abra ball mill installation (photo: 10 August).

Three other announcements were released by the company between this monthly update and the previous monthly update dated 18 July 2022. The first was “Re-release: Abra Initial Production Guidance” (ASX: 25 July 2022). The second was “Galena Successfully Raises

$17 Million” (ASX: 26 July 2022) and “Diggers and Dealers Investor Presentation” (ASX: 1 August 2022).

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 85% complete. As previously advised, the remaining items on the key equipment order list shown in Table 1 below which are currently not received are the flotation cells and the regrind mill. The flotation cells and drive mechanisms are currently in shipment with 2 separate shipments delivering the flotation equipment to Fremantle. The flotation cells (bulk shipment) are currently expected to arrive by the 2nd September and the flotation drive mechanisms (container shipment) has arrived in Perth. The regrind mill is currently shipping from Germany and is now expected to arrive in Melbourne by 20th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. These revised arrival dates do not affect the project construction timelines.

Table Notes – All items with strike through have been delivered (1) Flotation equipment shipped in 2 separate parts. Flotation cells ETA now 2 September and Flotation drive mechanisms have arrived in Perth. (2) Regrind Mill ETA Melbourne 17 August for final assembly by Glencore Technology.

Table 1 – Key equipment order and delivery schedule from overseas suppliers.

Mine decline development continued in the East Decline and the 1,375mRL diamond drill drive during July. A total of 243 metres was developed during July with the East decline reaching 1,360mRL. During July the second leg of the mines escape way system was drilled (1.5-meter raise bore) down to 1,400mRL (150m below surface). By the end of July, 16 underground diamond drill holes have been completed.

Figure 2 - Progress of the Abra underground mine development to 31 July (yellow).

In surface bulk earthworks, good progress continued with the tailing’s storage facility (“TSF”) passing 50% completion. The final works package associated with the remaining non- processing infrastructure is progressing as planned with the power station reaching 81% complete.

Owners' costs and contingencies remain within budget.

Figure 3 – Abra TSF construction.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Joe Mazumdar, open-pit mine.

Joe Mazumdar: Silver and Rare Earths Stocks, Plus Low-risk Gold Exposure

Speaking to the Investing News Network, Joe Mazumdar, editor of Exploration Insights, explained how he's getting low-risk exposure to the gold sector as the metal's price continues to move.

Given that inflation remains an issue for miners, he's focusing on small gold royalty companies. "That's what I've been trying to do to invest in a rising gold price and some growth, but without the creep of costs," he said.

Mazumdar also discussed two recent site visits, one of which was to see AbraSilver Resource's (TSXV:ABRA,OTCQX:ABBRF) Diablillos silver-gold project in Argentina. He is optimistic about the country's recent change in government, which has made it a better environment for foreign direct investment in the mining sector.

Keep reading...Show less
Eastern Metals

Eastern Metals Granted $910,750 in Junior Minerals Exploration Incentive Tax Credits

Refundable tax offsets / franking credits available for potential distribution to eligible shareholders for the 2024-25 financial year

Eastern Metals Ltd (ASX: EMS) (“Eastern Metals” or “the Company”) is pleased to advise that it has been successful in its application to participate in the Australian Government’s Junior Minerals Exploration Incentive (“JMEI”) for the 2024-25 income tax year, and has been awarded an allocation of $910,750 in exploration credits.

Keep reading...Show less
Lobo Tiggre, gold and silver bars.

Lobo Tiggre: Shopping for Silver Stocks, Watching "Powerful" Gold Mover

Lobo Tiggre, CEO of IndependentSpeculator.com, shared his updated thoughts on gold, silver and uranium.

When it comes to gold, he pointed to a "powerful mover" that he thinks could be in play — a change in global portfolio allocations to the yellow metal. Historically the allocation has been 2 percent, but more recently it's been 0.5 percent.

"I think that what we're seeing is that changing. And maybe it doesn't go back to 2 percent, but if it just goes back to 1 percent, that doubles the investment demand for gold from where we are now," he said.

Keep reading...Show less

MAG Silver Publishes Third Annual Sustainability Report

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG" "MAG Silver" or the "Company") is pleased to announce the publication of its third annual Sustainability Report, which underscores MAG's fundamental commitment to transparency with its stakeholders while providing a comprehensive overview of the Company's environmental, social and governance (" ESG ") commitments, practices, and performance for the 2023 year. The 2023 Sustainability Report is supported by the MAG Silver Climate Action Statement and the 2023 ESG Performance Data Table. The 2023 Sustainability Report and ESG Data Table are available on the MAG Silver website at the following link: https:magsilver.comesgreports .

Jim Mallory, MAG's Chief Sustainability Officer stated: "The development of MAG Silver's Climate Action Management Plan (" CAMP ") is our most significant climate change achievement during 2023. We are focusing our efforts in the areas of energy, water and community relations at the Deer Trail and Larder projects as a starting point for this journey, and to further develop our own awareness."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

First Majestic Produces 5.3 Million AgEq Oz in Q2 2024 Consisting of 2.1 Million Silver Ounces and 39,339 Gold Ounces; Announces Updated 2024 Production and Cost Guidance and Conference Call Details

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") announces that total production in the second quarter of 2024 from the Company's three producing mines in Mexico, the Santa Elena SilverGold Mine, the San Dimas SilverGold Mine, and the La Encantada Silver Mine, reached 5.3 million silver equivalent ("AgEq") ounces, consisting of 2.1 million silver ounces and 39,339 gold ounces. The Company's financial results for the second quarter of 2024 are scheduled to be released on Thursday, August 1, 2024.

Q2 2024 HIGHLIGHTS

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×