Galena Mining

Abra Construction 78% Complete at End of July

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 78% complete as of 31 July 2022. New milestones have been achieved with the commencement of the installation of the ball-mill components and total underground development passing 2km in early August.


Managing Director, Tony James commented, “Construction activities have progressed past 78% complete. Most of the concrete work has been completed and structural steel installation increased to 352 tonnes (72% complete). Plant construction work is quickly progressing into the mechanical, piping, and electrical fit out stages. It’s also pleasing to see the progress being made with the operational readiness activities including first fills and critical spares, with orders placed for over 75% of the items”.

Figure 1 – Abra ball mill installation (photo: 10 August).

Three other announcements were released by the company between this monthly update and the previous monthly update dated 18 July 2022. The first was “Re-release: Abra Initial Production Guidance” (ASX: 25 July 2022). The second was “Galena Successfully Raises

$17 Million” (ASX: 26 July 2022) and “Diggers and Dealers Investor Presentation” (ASX: 1 August 2022).

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 85% complete. As previously advised, the remaining items on the key equipment order list shown in Table 1 below which are currently not received are the flotation cells and the regrind mill. The flotation cells and drive mechanisms are currently in shipment with 2 separate shipments delivering the flotation equipment to Fremantle. The flotation cells (bulk shipment) are currently expected to arrive by the 2nd September and the flotation drive mechanisms (container shipment) has arrived in Perth. The regrind mill is currently shipping from Germany and is now expected to arrive in Melbourne by 20th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. These revised arrival dates do not affect the project construction timelines.

Table Notes – All items with strike through have been delivered (1) Flotation equipment shipped in 2 separate parts. Flotation cells ETA now 2 September and Flotation drive mechanisms have arrived in Perth. (2) Regrind Mill ETA Melbourne 17 August for final assembly by Glencore Technology.

Table 1 – Key equipment order and delivery schedule from overseas suppliers.

Mine decline development continued in the East Decline and the 1,375mRL diamond drill drive during July. A total of 243 metres was developed during July with the East decline reaching 1,360mRL. During July the second leg of the mines escape way system was drilled (1.5-meter raise bore) down to 1,400mRL (150m below surface). By the end of July, 16 underground diamond drill holes have been completed.

Figure 2 - Progress of the Abra underground mine development to 31 July (yellow).

In surface bulk earthworks, good progress continued with the tailing’s storage facility (“TSF”) passing 50% completion. The final works package associated with the remaining non- processing infrastructure is progressing as planned with the power station reaching 81% complete.

Owners' costs and contingencies remain within budget.

Figure 3 – Abra TSF construction.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)
Galena Mining Director & CEO Tony James

Galena Mining

Galena Mining CEO Tony James: On Track for Commercial Production in 2023youtu.be

Galena Mining (ASX:G1A) announced that construction at its Abra base metals mine is already 78 percent complete as of July 31, 2022. CEO Tony James said the company has done a great job building the project.

James commented, “The project's 80 percent complete. I think a lot of people have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job, and people will suddenly realise that everything's on track.”

The Abra base metals mine is a high-grade lead-silver mine located in the highly prospective Edmund sedimentary basin in the Gascoyne region of Western Australia. The project is under full construction in 2022 and remains on target for first commercial production in January 2023.


The activities that have progressed include concrete works and structural steel installation, as well as the mechanical, piping and electrical fit-out stages. The flotation cells and drive mechanisms are currently in shipment and are expected to arrive by September. The mine’s regrind mill has been shipped from Germany to Melbourne.

In July 2022, Galena raised a AU$17 million buffer for Abra’s critical initial commissioning and ramp-up stages.

“We raised some money in late July, which serves as our reserve facility. It’s been put in place by the joint venture partners to look after our working cap and risk period, which is the first initial commissioning period of the project. We don't believe we need to raise any more money at this stage.”

“I think we've done a great job building this project, I think we're on top of our risk profile. And this project is going to go ahead. We'll start producing concentrate in January and start supplying the market. We're very confident.”

Watch the full interview of Galena Mining CEO Tony James above.

Disclaimer: This interview is sponsored by Galena Mining (ASX:G1A). This interview provides information which was sourced by the Investing News Network (INN) and approved by Galena Mining in order to help investors learn more about the company. Galena Mining is a client of INN. The company’s campaign fees pay for INN to create and update this interview.

INN does not provide investment advice and the information on this profile should not be considered a recommendation to buy or sell any security. INN does not endorse or recommend the business, products, services or securities of any company profiled.

The information contained here is for information purposes only and is not to be construed as an offer or solicitation for the sale or purchase of securities. Readers should conduct their own research for all information publicly available concerning the company. Prior to making any investment decision, it is recommended that readers consult directly with Galena Mining and seek advice from a qualified investment advisor.

This interview may contain forward-looking statements including but not limited to comments regarding the timing and content of upcoming work programs, receipt of property titles, etc. Forward-looking statements address future events and conditions and therefore involve inherent risks and uncertainties. Actual results may differ materially from those currently anticipated in such statements. The issuer relies upon litigation protection for forward-looking statements. Investing in companies comes with uncertainties as market values can fluctuate.

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Silver bars on pile of $100 bills and green chart going up.

Could the Silver Price Really Hit $100 per Ounce?

Will the First Majestic Silver (TSX:FR,NYSE:AG) CEO’s silver price prediction of over US$100 per ounce come true?

The silver spot price has surged nearly 40 percent in the first eight months of 2025 to reach a 14 year high, breaking through the US$40 per ounce mark in early September. The white metal has rallied on growing economic uncertainty amid ongoing geopolitical tensions and US President Donald Trump’s escalating trade war.

Well-known figure Keith Neumeyer, CEO of First Majestic, has frequently said he believes the white metal could climb even further, hitting the US$100 mark or even reaching as high as US$130 per ounce.

Keep reading...Show less
Silver and copper bars with "5 Top Canadian Mining Stocks" text overlay.

Top 5 Canadian Mining Stocks This Week: Carlton Precious Gains 78 Percent

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX, TSXV and CSE, starting with a round-up of Canadian and US news impacting the resource sector.

Statistics Canada released its August jobs numbers on Friday (September 5). The report indicates a loss of 66,000 jobs in the Canadian economy and an increase in the unemployment rate to 7.1 percent from the 6.9 percent recorded in July.

The losses were primarily felt in the professional, scientific and technical services sector with a decrease of 26,000 jobs, followed by losses of 23,000 jobs in the transportation and warehousing sector and 19,000 jobs in manufacturing.

Keep reading...Show less
Silver bars in front of newspaper showing high price performance.

What Was the Highest Price for Silver?

Like its sister metal gold, silver has been attracting renewed attention as a safe-haven asset.

Although it continues to exhibit its hallmark volatility, many silver investors believe that a bull market is starting up for the precious metal. Experts are optimistic about the future, and as a result, some market watchers are looking for price forecasts and asking, “What was the highest price for silver?”

The answer reveals how much potential there is for the silver price to rise. Read on for a look at silver's historical moves, and what they could mean for both the price of silver today and the white metal’s price in the future.

Keep reading...Show less
Silver bars and US$100 bills with a rising chart overlay.

Silver Price Surges Above US$40 for First Time Since 2011

The silver price surged on Tuesday (September 2), breaking US$40 per ounce to rise as high as US$40.93.

Silver was last above US$40 in 2011, peaking that year at US$47.94 in April.

Many of the same factors that drove the silver price to that level in 2011 are present in today’s market, including significant uncertainty around the economy, a global debt crisis and a dovish US Federal Reserve policy.

Keep reading...Show less
Silver bars on shiny metallic surface.

Silver Stocks: 5 Biggest Companies in 2025

Silver has built on previous gains in 2025, soaring above US$40 per ounce in early September.

The metal's rise has been driven by several factors, most notably tightening supply and demand fundamentals, resulting from higher demand from industrial sectors and its use in photovoltaics.

Additionally, prices have found tailwinds from safe-haven investors who find silver's lower entry price compared to gold appealing. They have moved toward silver on the back of uncertainty in global financial markets as the US implements tariff policies, as well as escalating tensions in the Middle East and the unresolved conflict between Russia and Ukraine.

Keep reading...Show less

Latest Press Releases

Related News

×