Vertex Minerals Limited  Reward Gold Mine Project Update

Vertex Minerals Limited Reward Gold Mine Project Update

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX) (OTCMKTS:VTXXF) is pleased to announce that the underground mining operation is on track to be producing high grade gold feed to the recently commissioned gravity gold plant early this quarter.

Vertex's Technical Director and Geologist, Tully Richards commented: "It is very exciting to be involved in the opening of the next chapter of what is a legendary gold field. I'm particularly pleased to see the enthusiasm of all those involved in wanting to make this chapter a success"

HIGHLIGHTS:

- VTX remains on track to deliver first underground high grade gold ore to the Gravity Gold plant in early Q3 2025, with commissioning and underground mine readiness ramp- up activities progressing as planned.

- Underground Gold Mining Readiness

- First underground miners onboarded under owner operator model

- TD1 Jumbo (for development and production) commissioned and operating underground

- Primary ventilation installed

- First stope development dewatering completed

- Explosive Magazine constructed

- Water feed installed

- Air lines installed and operational

- 11kva power installation underway

- Revised mine plan and schedule received and being implemented

- Underground Ore trialled through gravity plant

- Trail of 90 tonnes of development material with some reef quartz through the gravity plant

- Throughput exceeding expectation and beyond the nameplate plant flow sheet value.

- Pulse Mining System Installed and Implemented

- INX Software Installed and Implemented

- INX Software and site access kiosks to go live at mine site in June.

- INX will improve overall safety framework with real time risk mitigation focus.

- INX strengthens site access controls for employees, contractors and visitors.

- Sand Stack facility fully operational

- Facility fully functioning with return water pump station installed and operational (water recycling)

- 57 Megalitre Turon River water licence purchased for back up water supply

- Environmental & Compliance Implementation

- Multiple monitoring systems installed, and real time monitored (Dust, noise, vibration).

- Underground diamond drilling site ("drill cuddy") being established

- This location will be used for Reward Gold Mine resource development as well as mine corridor exploration diamond drilling

A batch of hard rock material, taken from the Reward Gold Mine - Amalgamated Vein, was trial processed through the Gravity Gold Plant and TOMRA sorter. Vertex engineers and operators were extremely pleased with the throughput rate and its sorting amenability.

As previously announced the new mine schedule for the Reward underground mine proposes mining two stope blocks consisting of 2,075 tonnes at 17.8 g/t Au and 700 tonnes at 42.5 g/t Au. The planned stope width is the same as the interpretation of the mineralisation. (Refer to Table 1 in Appendices 1) (VTX ASX announcement 26/06/23).

This stope can be exploited as soon as services have been established. Vertex mining crews are actively developing the adit to make room for the 11kva cable, water and air lines ("services").

Drill Cuddy (location for underground diamond drill rig)

A drill cuddy is being developed by Vertex airleg miners and will be completed mid-June. The drill cuddy will be mined up to 6m in height and 7m depth to cater for the Vertex LM90 drill rig. The rig will drill circa 7 holes in this location designed by the Vertex geologists, targeting the stacked veins below and above the Amalgamated adit. The LM 90 will be operated by Vertex drillers and will drill continuously going forward. The aim is to build gold inventory, convert inferred resource to indicated and to help with stope design.

Vertex have now fully installed and implemented a closed water system at the Reward Gold Mine. The water from the gravity process plant mixed with the waste sand material is decanted at the sand stack area. The decanted water is then pumped back to the process plant for re-use. Make-up water is sourced from the Reward Gold Mine where mine water is used to meet the water requirements for the gravity plant. Water use is minimised in the process because the ore is mostly processed by ore sorting which doesn't use water. Further the water is not polluted because the Reward Ore and country rock has no sulphide minerals and the plant process does not use chemicals (Cyanide or reagents).
*To view tables and figures, please visit:
https://abnnewswire.net/lnk/8HMS51NW



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited



Contact:
Roger Jackson
Executive Chairman

Tully Richards
Technical Director
tully@vertexminerals.com.au

News Provided by ABN Newswire via QuoteMedia

VTX:AU
The Conversation (0)
Reward Gold Mine Production Update

Reward Gold Mine Production Update

youtu.be Vertex Minerals (VTX:AU) has announced Reward Gold Mine Production UpdateDownload the PDF here. Keep Reading...
Underground Production Commences Reward Gold Mine Project

Underground Production Commences Reward Gold Mine Project

Vertex Minerals (VTX:AU) has announced Underground Production Commences Reward Gold Mine ProjectDownload the PDF here. Keep Reading...
Quarterly Activities and Cash Flow Reports 30 June 2025

Quarterly Activities and Cash Flow Reports 30 June 2025

Vertex Minerals (VTX:AU) has announced Quarterly Activities and Cash Flow Reports 30 June 2025Download the PDF here. Keep Reading...
UPDATE Fully Developed Stope Block Announcement (28/04/25)

UPDATE Fully Developed Stope Block Announcement (28/04/25)

Vertex Minerals (VTX:AU) has announced UPDATE Fully Developed Stope Block Announcement (28/04/25)Download the PDF here. Keep Reading...
A$11m Capital Raising to Accelerate Mining at Hill End

A$11m Capital Raising to Accelerate Mining at Hill End

Vertex Minerals (VTX:AU) has announced A$11m Capital Raising to Accelerate Mining at Hill EndDownload the PDF here. Keep Reading...
Finlay announces expanded 2026 PIL Drill Program with increase to 4,400 meters

Finlay announces expanded 2026 PIL Drill Program with increase to 4,400 meters

finlay minerals ltd. (TSXV: FYL,OTC:FYMNF | OTCQB: FYMNF) ("Finlay" or the "Company") is pleased to announce that the 2026 drill program at its PIL Property has been increased by 1,600 meters, bringing the planned program to 4,400 meters, with the additional drilling funded by Freeport-McMoRan... Keep Reading...
Cygnus Metals Limited: Drilling Results Update

Cygnus Metals Limited: Drilling Results Update

Chibougamau Copper-Gold Project, Canada HIGHLIGHTS: Results from Copper Rand come from step out drilling surrounding the historic mine which produced 14.9Mt at 3.9% CuEq for 268kt Cu and 1.3Moz Au1 Copper Rand sits within the Chibougamau North Camp which also hosts the Cedar Bay and Golden Eye... Keep Reading...
Steadright Provides Second Bi-Weekly MCTO Status Update

Steadright Provides Second Bi-Weekly MCTO Status Update

(TheNewswire) August 27, 2026 TheNewswire - Muskoka, Ontario Steadright Critical Minerals Inc. (CSE: SCM,OTC:SCMNF) ("Steadright" or the "Company"), is providing this bi-weekly update on the status of the management cease trade order (the "MCTO") granted by its principal regulator, the Ontario... Keep Reading...
Bold Reports Positive Results of Induced Polarization Survey at Joutel - Signs Investor Awareness Agreement

Bold Reports Positive Results of Induced Polarization Survey at Joutel - Signs Investor Awareness Agreement

Bold Ventures Inc. (TSXV: BOL) (OTCQB: BVLDF) (the "Company" or "Bold") is pleased to announce the results from a Spring 2026 Induced Polarization (IP) Survey at its Joutel Property (the "Property" or the "Project"), located 140 km northwest of Val d'Or, Québec. The survey targeted Versatile... Keep Reading...
Cygnus Metals Limited: CAML H1 Filings

Cygnus Metals Limited: CAML H1 Filings

Cygnus Metals Limited (ASX: CY5, TSXV: CYG,OTC:CYGGF, OTCQB: CYGGF) (Cygnus) announces that the unaudited interim results for the six months ended June 30, 2026 (H1 Interim Report) of Central Asia Metals PLC (CAML), together with the associated management's discussion and analysis (collectively,... Keep Reading...
Getty Copper Defines Seven New Exploration Targets in the Highland Valley Copper District

Getty Copper Defines Seven New Exploration Targets in the Highland Valley Copper District

Highlights Seven new exploration targets identified across the Getty Project, expanding the exploration pipeline beyond Getty North and Getty South resource targets New 1,805 hectare mineral claim further expands the Company's land position Multiple targets considered drill-ready for the planned... Keep Reading...

Interactive Chart

Latest Press Releases

Related News