Pilot Plant Ponds Under Construction, Drilling Campaign Accelerated & New Geophysics Commences - HMW Project Update

Galan Lithium Limited (ASX: GLN) (Galan or the Company) is pleased to provide a progress update report for its 100% owned Hombre Muerto West (HWM) Project (the Project) in Catamarca Province, Argentina. The Project has no third party royalty or offtake commitments.


Highlights:

  • Construction of pilot plant ponds started - operational in Q1 2022
  • New Hombre Muerto West camp to be operational early January
  • Galan signs new contract to accelerate HMW drilling
  • Rotary rig currently drilling at Rana de Sal with second rig due in early January
  • Access to an available third rig, if required
  • The HMW drilling campaign aims to deliver key data for expanding the resource base and develop the Feasibility Study
  • A comprehensive geophysical survey, over all HMW tenements underway
  • The geophysical data will complement previous geophysical surveys with an aim to generate new drill targets
  • Feasibility Study contract award imminent

As planned, ponds construction for the pilot plant has commenced and progressing well with the aim for the pilot ponds system to be operational in Q1 2022. The ponds will be filled with HMW’s brine to continue with the tests of the evaporation process targeting high-grade lithium concentrations of 6% Li and low impurities.

The construction of the new temporary camp at HMW is well advanced and it should be operational early January. Once completed, Galan will have access to two fully functional camps (the other at Candelas) to support the ongoing activities associated with the HMW studies. A larger, permanent camp will be completed during 2022.

Click here for the full ASX Release

This article includes content from Galan Lithium, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

GLN:AU
Galan Lithium

Galan Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galan Lithium

Galan Lithium


Keep reading...Show less
Drilling Commences at the Barra Lithium Project in Brazil

Drilling Commences at the Barra Lithium Project in Brazil

Summit Minerals Limited (ASX:SUM) (“Summit” or the “Company”) is pleased to announce that Summit’s maiden drilling program has commenced at the recently acquired 100% owned Barra Lithium Project (“Barra”).

The Barra Lithium Project consists of four recently acquired tenements that are located within close proximity to the existing operating Miranda Lithium mine that is within the Borborema Pegmatitic Province (“BPP”) in northeast Brazil.

Keep reading...Show less
Lithium Universe

Lithium Universe


Keep reading...Show less
CleanTech Lithium (AIM:CTL)

Issue of Equity and TVR


Keep reading...Show less
Lithium-ion batteries.

Rio Tinto Shares Initial Resources and Ore Reserves for Rincon Lithium Project

Rio Tinto ( ASX:RIO,NYSE:RIO,LSE:RIO) released an initial mineral resources and ore reserves report for its 100 percent owned Argentina-based Rincon project on Wednesday (December 4).

Mineral resources inclusive of ore reserves comprise 1.54 million tonnes of lithium carbonate equivalent in the measured category, with 7.75 million tonnes in the indicated category and 2.29 million tonnes in the inferred category.

Probable ore reserves are made up of 2.07 million tonnes of lithium carbonate equivalent.

Keep reading...Show less
Galan Lithium

Galan Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×