Fortuna provides construction update at its Séguéla gold Project in Côte d´Ivoire

Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) is pleased to provide an update on construction activities at its Séguéla gold Project located in Côte d'Ivoire. In September of 2021, the Company made a construction decision to proceed to build a 3,750 tonnes per day open pit mine at Séguéla, with first gold pour expected in mid-2023 (refer to Fortuna news release dated September 29, 2021 ). All references to dollar amounts in this news release are expressed in US dollars.

Paul Criddle, Chief Operating Officer - West Africa, commented, "The Séguéla Project is advancing on schedule following the construction decision at the end of the third quarter of 2021." Mr. Criddle continued, "The Project is successfully transitioning from detailed engineering design to construction and remains on budget and on schedule to pour gold by mid-2023."

Construction Highlights

  • The overall project is 32% complete as of January 31, 2022
  • Approximately $48.9 million of the $173.5 million initial capital budget accrued as of December 31, 2021
  • Approximately $124.5 million committed
  • Major equipment packages secured
  • Major construction contracts executed
  • Tender process and selection of the preferred mining contractor completed
  • First gold pour remains on target for mid-2023

Accommodation Camp

The 156-person accommodation camp is complete and ready for occupancy. Initially, this camp will support the project's development and house the owner's and contractors' construction personnel with surplus personnel residing in the nearby town of Séguéla. The camp is approximately two kilometers from the processing plant area and is complete with kitchen and mess, recreational facilities, water and sewage treatment plants, laundry services and high-speed internet. The camp management contract has been tendered and awarded to Allterrain Services.

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/33aab07c-59d1-4c52-abb4-23562b9c7fab

Processing Plant

De Simone was awarded the process plant bulk earthworks contract and activities are ongoing with excavation for ground improvement in the mill/carbon-in-leach circuit, thickener and crusher areas complete. Rock backfill in these areas is well advanced and on-track to be completed ahead of the mobilization of the engineering procurement and construction contractor in March 2022.

Lycopodium was awarded the guaranteed maximum price contract for the engineering, procurement and construction of the gold processing facility. As of December 31, 2021 engineering activities were 55 percent complete, procurement activities 44 percent complete and construction activities are on-track to commence early in the second quarter of 2022. Of note, the SAG mill purchase order has been placed and remains on-track to be delivered to site in the third quarter of 2022. Detailed engineering for the SAG mill is complete and manufacturing of core components such as shell, heads and trunnions and gear and pinion has commenced.

Site Bulk Earthworks

Contracts have been awarded for the site bulk earthworks contract for the construction of the tailings storage facility (TSF), water storage dam (WSD) and sediment control structure (SCS). Bush clearing and topsoil stripping of the TSF footprint has been completed. Bush clearing of the WSD commenced in early January and is on-track to be completed by the middle of the second quarter of 2022, ahead of the upcoming wet season and will be capable of storing raw water for the commissioning, ramp-up and operation of the processing plant. Procurement of materials required for the TSF, WSD and SCS construction is underway with the TSF high density polyethylene liner already secured and expected to be delivered to site by the end of the first quarter of 2022.

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/e8ff98a2-7850-47c3-859b-bec163295908

Grid Connection

Contracts for the supply and installation of the 90 kV grid connection transmission line and 33 kV transmission line diversion have been awarded. Likewise, contracts for the supply and construction of the substation have been awarded. Delivery and installation of the transmission lines is expected to commence this month. Similarly, civil works for the substation are also expected to commence this month. Transformers are expected to be shipped to site by March 2022. Works is on-track to provide power to the site by the end of the fourth quarter of 2022 ahead of commissioning activities at the processing plant.

Mining

Contract negotiations with a preferred bidder are ongoing, targeting contract execution and the placement of orders for long lead equipment in March 2022.

Cost

As of December 31, 2021, $124.5 million of the total approved budget of $173.5 million, including $8.9 million contingency, has been committed. Approximately $108 million of total commitments to date include contracts for a guaranteed maximum price for $87 million, fixed price contract for $7.5 million and earthworks bill of quantity/schedule of rates for $13.5 million, mitigating risk to volatile market conditions and price escalations. Remaining commitments include the onboarding of key operational personnel, pre-production mining, equipment first fills and spare parts, mobile equipment and the implementation of livelihood restoration programs.

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/6be39cea-4d00-426c-ae14-23dae81a8c88

Schedule

Construction at Séguéla is tracking on schedule with the project's next major milestones below:

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/acca53ed-8993-46bb-a7cb-f94bc3eaa525

Qualified Person

Paul Criddle, FAusIMM, Chief Operating Officer, West Africa for Fortuna, is a Qualified Person as defined by National Instrument 43-101, Standards of Disclosure for Mineral Projects, and has reviewed and approved the scientific and technical information pertaining to the Séguéla gold Project contained in this news release and has verified the underlying data.

About Fortuna Silver Mines Inc.

Fortuna Silver Mines Inc. is a Canadian precious metals mining company with four operating mines in Argentina, Burkina Faso, Mexico and Peru, and a fifth mine under construction in Côte d'Ivoire. Sustainability is integral to all our operations and relationships. We produce gold and silver and generate shared value over the long-term for our stakeholders through efficient production, environmental protection, and social responsibility. For more information, please visit our website .

ON BEHALF OF THE BOARD

Jorge A. Ganoza
President, CEO, and Director
Fortuna Silver Mines Inc.

Investor Relations:
Carlos Baca | info@fortunasilver.com

Forward looking Statements

This news release contains forward looking statements which constitute "forward looking information" within the meaning of applicable Canadian securities legislation and "forward looking statements" within the meaning of the "safe harbor" provisions of the Private Securities Litigation Reform Act of 1995 (collectively, "Forward looking Statements"). All statements included herein, other than statements of historical fact, are Forward looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward looking Statements. The Forward looking Statements in this news release may include, without limitation, statements about the Company's plans for the construction of an open pit gold mine at the Séguéla gold Project, including the timeline for construction, the costs of constructing the mine, the securing of contracts necessary for the construction of the mine, the signing of the Mining Convention with the Government of Côte d'Ivoire, the ability to sign contracts for outstanding equipment and services in line with the estimates for same, the timing of the first gold pour; the Company's business strategy, plans and outlook; the merit of the Company's mineral properties; mineral resource and reserve estimates; timelines; the future financial or operating performance of the Company; expenditures; approvals and other matters. Often, but not always, these Forward looking Statements can be identified by the use of words such as "estimated", "potential", "open", "future", "assumed", "projected", "used", "detailed", "has been", "gain", "planned", "reflecting", "will", "containing", "remaining", "to be", or statements that events, "could" or "should" occur or be achieved and similar expressions, including negative variations.

Forward looking Statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by the Forward looking Statements. Such uncertainties and factors include, among others, changes in general economic conditions and financial markets; the duration and effects of the COVID-19 pandemic on our operations and workforce and the effects on the global economy and society; changes in prices for silver, gold and other metals; changes in the prices of supplies required for the construction at the Séguéla gold Project such as equipment and services; the ability to sign the Mining Convention on terms currently contemplated and acceptable to the Company; technological and operational hazards in Fortuna's mining and mine development activities; risks inherent in mineral exploration; fluctuations in prices for energy, labor, materials, supplies and services; fluctuations in currencies; uncertainties inherent in the estimation of mineral reserves, mineral resources, and metal recoveries; our ability to obtain all necessary permits, licenses and regulatory approvals in a timely manner; governmental and other approvals; political unrest or instability in countries where Fortuna is active; labor relations issues; as well as those factors discussed under "Risk Factors" in the Company's Annual Information Form. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in Forward looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.

Forward looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including but not limited to that the construction at the Séguéla gold Project will continue on the time line and in accordance with the Budget as planned; that COVID-19 will not have an adverse effect on the construction at the Séguéla gold Project and will not adversely affect the supply chain of materials and equipment for the construction; expected trends in mineral prices and currency exchange rates; that the Company's activities will be in accordance with the Company's public statements and stated goals; that there will be no material adverse change affecting the Company or its properties; that all required approvals will be obtained; that there will be no significant disruptions affecting operations and such other assumptions as set out herein. Forward looking Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward looking Statements, whether as a result of new information, future events or results or otherwise, except as required by law. There can be no assurance that Forward looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on Forward looking Statements.


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

FVI:CA,FSM
The Conversation (0)
Fortuna Announces Pricing of Convertible Senior Notes

Fortuna Announces Pricing of Convertible Senior Notes

Fortuna Silver Mines Inc. (TSX: FVI) (NYSE: FSM) ("Fortuna" or the "Company") announces that it has priced its previously announced offering of convertible senior notes due 2029 (the "Notes") in an aggregate principal amount of US$150 million (the "Offering"). The Company has granted the initial purchasers of the Notes an option for a period of 15 days to purchase up to an additional US$22.5 million aggregate principal amount of Notes. The Notes will be issued at par value.

The Notes will bear cash interest semi-annually at a rate of 3.75% per annum. The initial conversion rate for the Notes will be 151.7220 common shares of Fortuna ("Shares") per US$1,000 principal amount of Notes, equivalent to an initial conversion price of approximately US$6.59 per Share. The initial conversion rate represents a premium of approximately 30% relative to today's closing sale price of the Shares and is subject to adjustment in certain events.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Fortuna's Yaramoko Mine reaches one-million-ounce gold pour milestone

Fortuna's Yaramoko Mine reaches one-million-ounce gold pour milestone

Fortuna Silver Mines Inc. (TSX: FVI) (NYSE: FSM) is pleased to report that the Yaramoko Mine located in Burkina Faso reached the one-million-ounce gold pour milestone on May 19, 2024. Yaramoko started production on May 16, 2016 and Fortuna acquired the mine on July 2, 2021 (refer to Fortuna news release dated July 2, 2021 ).

As of December 31, 2023, Yaramoko has a remaining mine life of two years with Proven and Probable Mineral Reserves of 0.9 Mt at a grade of 7.90 g/t Au and containing 219 koz Au, in addition to Measured and Indicated Mineral Resources, exclusive of Mineral Reserves, of 0.5 Mt at a grade of 2.87 g/t Au and containing 43 koz Au, and Inferred Mineral Resources, exclusive of Mineral Reserves, of 0.16 Mt at a grade of 3.52 g/t Au and containing 18 koz Au (refer to Fortuna news release dated February 15, 2024, " Fortuna reports updated Mineral Reserves and Mineral Resources "). The mine's exploration budget for 2024 is US$6.1 million, which includes 41,450 meters of drilling (refer to Fortuna news release dated January 18, 2024 ).

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Boab Metals Limited

Corporate Presentation December 2024

Boab Metals Limited (ASX: BML) (“Boab” or “Company”) is pleased to present its investor presentation.


Keep reading...Show less
Alex Wallis, vice president of exploration at Silver47 Exploration.

Silver47 Beefs Up Drilling Plans to Expand Resource at Red Mountain Polymetallic Project

Following release of the final results from Silver47 Exploration's (TSXV:AGA) 2024 exploration program, the company is beefing up plans for a more expansive and targeted drill campaign in the new year at its flagship Red Mountain project in Alaska. Alex Wallis, vice president of exploration, said the aim is to “increase both the grade and the tonnage."

“With the modern drilling and the recoveries we saw this year, we have a really good chance to increase just from infilling the historic zones to really bulk that resource out as well,” he said.

Approximately 20 percent of future drilling efforts will focus on fresh exploration targets like Galleon and Horseshoe, according to Wallis. The company is eyeing more than 15 exploration targets at Red Mountain that have never been drill tested with geochemical and geophysical targeting.

Keep reading...Show less
  Unico Silver Limited

Cerro Leon drill results

Further high-grade mineralisation identified at the Karina prospect

Unico Silver Limited (“USL” or the “Company”) is pleased to announce first assay results from ongoing drilling at the Cerro Leon project, located in the Santa Cruz province of Argentina.

Keep reading...Show less

First Majestic Announces Mailing of Materials for Special Meeting

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce that it has commenced mailing of its meeting materials for the special meeting of the Company's shareholders (the "Special Meeting") that will be held on Tuesday, January 14, 2025 at 11:00 a.m. (Pacific Time) at the offices of Bennett Jones LLP, located at Suite 2500 - 666 Burrard Street, Vancouver, British Columbia V6C 2X8.

At the Special Meeting, pursuant to the requirements of the rules of the Toronto Stock Exchange and the New York Stock Exchange, First Majestic shareholders will be asked to approve an ordinary resolution (the "Share Issuance Resolution") approving the issuance of up to 190,000,000 common shares of First Majestic ("First Majestic Shares") to stockholders of Gatos Silver, Inc. ("Gatos") in connection with the previously announced acquisition by First Majestic of all of the shares of common stock of Gatos (the "Transaction"). First Majestic's Board of Directors unanimously recommends that the Company's shareholders vote FOR the Share Issuance Resolution.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Pan American Silver Provides Annual Exploration Update

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") provides an annual exploration update and releases new exploration drill results for its Jacobina, El Peñon, La Colorada, Huaron, Minera Florida and Timmins mines, as well as its La Colorada Skarn project.

"The success of our exploration program highlights the potential for long-term organic growth at many of our assets," said Christopher Emerson, Vice President of Exploration and Geology at Pan American. "Based on the results we were achieving in exploration this year, we increased our drill budget to over 450,000 metres for 2024. This exploration update highlights these results, and showcases the ongoing discovery of new mineralized structures in and around our existing mining operations."

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Boab Metals

Boab Metals Limited (ASX: BML) – Trading Halt

Boab Metals Limited (ASX:BML) (the “Company”) hereby requests a trading halt of its securities be granted by the ASX effective immediately, pending a release of an announcement regarding an Offtake and Project Finance Agreement. The trading halt will last until the earlier of commencement of trading on Wednesday, 11 December 2024 or the release to the market of an announcement as specified above. The Company is not aware of any reason why the trading halt should not be granted or of any other information necessary to inform the market about the trading halt. This request was authorised for release by the Board of the Company.

Keep reading...Show less

Latest Press Releases

Related News

×