ICO on Track for Cobalt Production in Third Quarter 2022

(TheNewswire)



Highlights:

  • Estimated total capital expenditure to bring ICO into production in 2022 revised to US$99.1 million (previously US$92.6 million) construction cost, principally due to market and inflationary pressures in the western United States

  • Schedule substantially unchanged: first ore anticipated August 2022 (previously July 2022), and sustainable commercial production anticipated from December 2022

  • Detailed engineering progress at 64% complete with procurement 55% completed. Commitments are substantially advanced with now over 76% planned dollars committed on purchase orders

  • Mine development has advanced in line with plan for both west and east portals.  Daily advance of approximately 20 feet per day with no critical ground conditions

  • With the construction and commissioning cost and schedule update, RPM Global is now scheduled to visit site in January 2021 with a view to completing the Cost to Complete review for bondholders associated with its role as Independent Engineer for the US$100 million Senior Secured Bonds.  First US$50 million drawdown is anticipated in Q1 2022

  • Once complete, ICO will be the only mine supply of cobalt in the United States, a critical mineral necessary for industry, defense, electric vehicles and energy generation and distribution in a carbon constrained economy

Australia - TheNewswire - 1 5 December 2021 - Jervois Global Limited (" Jervois ") (ASX: JRV) (TSXV:JRV) (OTC:JRVMF) is pleased to update construction progress and results of a reforecast to project cost and schedule at its 100%-owned Idaho Cobalt Operations ( "ICO" ) in Idaho, United States.

Jervois project team and EPCM M3 Engineering have completed a reforecast to schedule and budget based on current site efficiency and price submissions on all equipment and site construction contract work.  In July 2021, the Jervois Board of Directors approved US$92.6 million capital for construction of the mine and process facility with a first ore commissioning date of July 2022.  Based on current pricing from the market for labour and materials, inflationary pressure has resulted in an updated capital cost of  US$99.1 million.  First ore through the mill is now planned for August 2022.  The date for sustainable ore production remains unchanged, during December 2022.

Increases in costs relating to high density polyethylene (" HDPE ") for the waste storage facility, steel and cement supply, camp materials, construction and site labour cost have contributed to inflationary pressure on the project budget, and are incorporated into the revised forecast.

Final commissioning date is now adjusted for the anticipated impact of winter weather conditions and the delays in camp construction.  Update project costs and schedule will underpin a Cost to Complete test by Independent Engineer RPM Global, engaged under the terms of the previously announced US$100 million Senior Secured Bonds.  Subject to the satisfaction of applicable Conditions Precedent, including the Cost to Complete test, the first US$50 million drawdown is now expected to occur in the first quarter of 2022.

Mill and concentrator building erection and civil work continue to progress with SAG and ball mill slabs laid; and foundations to be poured in the coming weeks.


Click Image To View Full Size

SAG and ball mill form work

Flotation building civil work is well underway, and an additional steel erection crew, and two additional cranes have mobilized to site to complete erection.


Click Image To View Full Size

Flotation building progress

The base support for the fine ore bin and mill feed conveyor structure has been erected.


Click Image To View Full Size

Fine ore bin and mill feed conveyor base structure

The water treatment plant (" WTP ") has been water commissioned with final punch list items complete in December 2021.  The pump back system will move water from the portal pump station to the WTP and will be complete and commissioned in December.

The mining advancement for both portals continues in line with plan.  During the month of December both portals will be connected and underground infrastructure will be developed.


Click Image To View Full Size

West Portal development with installed ventilation


Click Image To View Full Size

Portal bench infrastructure

ICO has completed recruiting for substantially all key management positions including finance manager, mill manager and mine manager in advance of full operations.

ICO is a key asset in delivering Jervois' strategy to become a leading independent cobalt and nickel company providing metals and minerals for the world's energy transition through a western supply chain.  When commissioned, ICO will be the United States' only domestic mine supply of cobalt, a critical mineral used in applications across industry, defense, energy and electric vehicles.

On behalf of Jervois

Bryce Crocker, CEO

For further information, please contact:

Investors and analysts:

James May

Chief Financial Officer

Jervois Global

jmay@jervoisglobal.com

Media:

Nathan Ryan

NWR Communications

nathan.ryan@nwrcommunications.com.au

Mob: +61 420 582 887

Forward-Looking Statements

This news release may contain certain "Forward-Looking Statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. When used in this news release, the words "anticipate", "believe", "estimate", "expect", "target, "plan", "forecast", "may", "schedule", "expected" and other similar words or expressions identify forward-looking statements or information. These forward-looking statements or information may relate to the timing construction activities at ICO, the timing of productions at ICO and certain other factors or information. Such statements represent Jervois' current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by Jervois, are inherently subject to significant business, economic, competitive, political and social risks, contingencies and uncertainties. Many factors, both known and unknown, could cause results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements. Jervois does not intend, and does not assume any obligation, to update these forward-looking statements or information to reflect changes in assumptions or changes in circumstances or any other events affections such statements and information other than as required by applicable laws, rules and regulations.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Copyright (c) 2021 TheNewswire - All rights reserved.

News Provided by TheNewsWire via QuoteMedia

JRV:CA,JRVMF
The Conversation (0)
A lithium-ion battery in the foreground with a line of batteries in the background, all surrounded by blue swirls.

ASX Cobalt Stocks: 4 Biggest Companies in 2024

Strong electric vehicle (EV) sales have been driving up demand for key battery raw materials in recent years. EVs require lithium-ion batteries to run, and each battery could contain up to 15 kilograms of cobalt.

This means that as demand for EVs increases, so too will demand for cobalt — and, as one of the top four cobalt-producing countries in the world, Australia finds itself in a position to capitalise on this demand.

About 74 percent of global cobalt output comes from the Democratic Republic of Congo (DRC). However, Australia is proving to be a solid contender; though it is only responsible for 2 percent of the world’s cobalt production, it holds about 15.5 percent of global reserves. Moreover, while the DRC’s labour and mining practices have often been labeled unethical and unsustainable, Australian miners are focused on safer, more environmentally friendly practices.

Keep reading...Show less

Glencore's Lomas Bayas Partners with Ceibo to Accelerate Access to Clean Copper

Following a two-year study, Glencore to scale the use of Ceibo's sulfide leaching technology   that significantly improves copper recovery

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Arrows progressing in a downward fashion.

Cobalt Price Recovery Uncertain as Battery Chemistry Shifts Erode Demand

Cobalt market watchers are warning that a near-term resurgence in prices and demand may not occur.

Cobalt prices have spent most of 2024 on the decline, falling to lows not seen since 2016. Values for the electric vehicle (EV) battery metal have fallen 74 percent from highs set in 2022 (US$81,969.70 per metric ton).

Prices are now sitting at the US$23,383.80 per metric ton level, an eight year low.

Keep reading...Show less
Cobalt periodic symbol over map of the world.

Top 10 Cobalt Producers by Country (Updated 2024)

Battery metal cobalt has been in focus in recent years for its role in lithium-ion batteries, bringing attention to the top cobalt producing countries.

One of the metal’s main catalysts is the electric vehicle roll out. The lithium-ion batteries that power electric vehicles and energy storage require lithium, graphite and cobalt, among other raw materials, and demand for these important commodities is expected to keep rising as the shift toward clean technologies continues at a global scale.

Additionally, the metal is predominantly produced as a by-product of copper and nickel, two other metals that are important for the green transition.

However, supply growth in many of the battery metals has out scaled near-term demand, leading to a price pullback over the last two years. The cobalt market has trended downwards in 2024, with prices falling 10 percent from July to September.

Keep reading...Show less
Electric vehicle with world map behind it.

Cobalt Market Update: Q3 2024 in Review

A contraction continued in the cobalt market during the year's third quarter, with metal values falling from US$27,151.50 per metric ton (MT) on July 1 to US$24,299 by the end of September.

The 10 percent decline is part of a larger 16.56 percent year-to-date contraction.

“This quarter saw minimal pricing movements as the market experienced a prolonged period of low prices,” said Roman Aubry, cobalt pricing analyst at Benchmark Mineral Intelligence.

Keep reading...Show less
High Tech Metals Limited

Quarterly Activities Report and Appendix 5B for the Period Ending 30 September 2024

High-Tech Metals Limited (ASX: HTM) (High-Tech, HTM or the Company), a critical battery minerals exploration Company, is pleased to provide the following report on its activities for the Quarter ending 30 September 2024 (“Quarter”). The Company’s primary activities during the quarter were the desktop review of Werner Lake Project, Canada, (“Werner Lake”).

Keep reading...Show less

Latest Press Releases

Related News

×