Element 25 Limited

Element 25 USA HPMSM Processing Facility Project Execution Update

Element 25 Limited (E25 or Company) (ASX:E25) is pleased to provide an update in relation to the planned construction of the first North American commercial scale battery grade high purity manganese sulphate (HPMSM) processing facility to produce key raw materials for electric vehicle (EV) battery manufacture in the USA. The facility is targeting commissioning in 2025 to produce the first low carbon, ethically sourced HPMSM in the USA (Project or Facility), processing manganese oxide ore from the Company’s 100%-owned Butcherbird Manganese Project in Western Australia (Butcherbird).


Highlights:

  • Front-end Engineering and Design (FEED) completed to optimise HPMSM plant design for preferred Louisiana site.
  • Cost reduction opportunities identified for further assessment during detailed design phase.
  • Detailed project execution schedule finalised with mechanical completion on track for 2025 target.
  • Local engineering and construction firms CDI Engineering Solutions and Universal Plant Services to continue engineering activities.
  • CSRS Inc and subsidiary Fides Consulting to continue to support E25 as the owners engineer/strategic consultant.
  • Local legal firm Roedel Parsons has been engaged to represent E25 as Louisiana legal advisor.
  • Key utility and reagent supply agreements in negotiation.
  • Preferred site offers significant strategic advantage including over the fence supply of sulphuric acid, steam and other key inputs.
  • Site assessments including cultural, environmental and geotechnical surveys completed with no issues or concerns.
  • Project execution plan advancing in line with project development timelines outlined in the FS.
  • All contractual milestones under the General Motors LLC (GM) and Stellantis N.V. (Stellantis) offtake and funding packages on track.
  • Final approvals for Louisiana state government subsidy package received.
  • Industrial Tax Exemption Plan (ITEP) has been submitted.

Element 25 Managing Director Justin Brown said: “E25 aims to be a leading source of high quality, vertically integrated, traceable and ESG and IRA-compliant battery material to the global electric vehicle industry . The construction of our first HPMSM facility in the USA – the first of its kind there – is a key pillar to the strategic plan which aims to position E25 as the industry leading provider of high quality ethically sourced battery grade manganese to support global electrification efforts. The team has made extraordinary progress to date and we will continue to push hard to achieve the project execution plans which are rapidly taking shape for a 2025 commissioning date.”

Project Execution Update

In April 2023, E25 published the detailed Feasibility Study (FS) for the construction of an integrated battery grade high purity manganese sulphate facility in Louisiana USA to produce HPMSM1. HPMSM is a critical raw material used in the construction of various lithium-ion battery cathode precursor materials to power the electrification of the global vehicle fleet. The HPMSM produced in Louisiana will be used in the manufacture of electric vehicle Pre-Cathode Active Materials (pCAM).

The Project is supported by key offtake and funding agreements in place with General Motors LLC (GM) and Stellantis N.V. (Stellantis) which are contributing a combined US$115M in project funding through a combination of equity, pre-payment and senior debt alongside offtake for approximately 65% of the planned HPMSM production from the first production train.

Subsequent to the release of the FS, E25 has continued to engage local engineering firms CSRS Inc (CSRS) and FIDES (a CSRS subsidiary) as owners engineers and CDI Engineering Solutions (CDI) and Universal Plant Services (UPS) as design and construction engineers to continue to refine the engineering and design of the facility prior to commencement of construction targeted for first half 2024. Key focus areas include:

  • Front end Engineering and Design (FEED).
  • Site Assessments and permitting.
  • Inbound and outbound logistics and reagent supply.
  • Project financing.

Engineering/Procurement Services

CSRS, FIDES, CDI and UPS are experienced local engineering contractors in Louisiana a track record of chemical plant design and construction in the Louisiana region. Subsequent to the publication of the FS, E25 engaged CDI (with the support of UPS) to execute front end engineering and design (FEED) for the Project. The FEED programme began in early May 2023 and is now complete.

Figure 1.Plant design based on updated detailed engineering 3D model developed as part of FEED studies.

Figure 2. Render showing plant internal layout – product packaging and distribution warehouse.

FEED work programme covers engineering which is conducted to a greater level of rigor and detail compared to a Feasibility Study. It is an important engineering phase which provides additional engineering and cost estimation detail as a project transitions from conceptual design to an Engineering, Procurement and Construction (EPC) contract.

The FEED study typically precedes a final investment decision phase of a large project such as E25’s planned HPMSM facility in Louisiana. The scope of the study covers a range of engineering disciplines including:

  • Site layout optimisation.
  • Civil and Structural design and layout.
  • Process flow diagrams.
  • Process and instrumentation diagrams.
  • Electrical design.
  • Piping and mechanical design.
  • Material take-offs to inform cost estimation activities.

E25 have commissioned FIDES, CDI and UPS to undertake the next phase of detailed engineering and design which will advance the project through to FID and commencement of construction targeted for Quarter 1, calendar 2024.


Click here for the full ASX Release

This article includes content from Element 25 Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

E25:AU
Element 25 Limited

Element 25 Limited Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Element 25 Limited (ASX:E25)

Element 25 Limited


Keep reading...Show less
Miramar Resources

Goldfields Exploration Update

Miramar Resources Limited (ASX:M2R, “Miramar” or “the Company”) is pleased to provide an update on gold exploration activities within the Company’s strategic Eastern Goldfields project portfolio.

Keep reading...Show less
South32's Groote Eylandt manganese project.

South32 Reports Lower Manganese Output After Cyclone, Says Exports Will Resume in 2025

South32's (ASX:S32,OTC Pink:SHTLF) latest quarterly reportreveals how Tropical Cyclone Megan has impacted its Australian manganese operations in Groote Eylandt, located in the country's Northern Territory.

The company reported a 13 percent decline in saleable production of the metal at the location, amounting to a reduction of 352,000 wet metric tonnes over the nine month period ended in March of this year.

The cyclone, which wreaked havoc on March 16 and 17, unleashed rainfall of 681 millimetres accompanied by powerful wind gusts, marking it as the second strongest cyclone to hit the area in the past two decades.

Keep reading...Show less
Element 25 Limited

March 2024 Quarterly Report

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to present its Quarterly Activities and Cash Flow Report.

Keep reading...Show less
Element 25 Limited

Butcherbird Expansion Project Advances through NAIF Funding Process

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to advise the Northern Australia Infrastructure Facility (NAIF) has completed a strategic assessment of the Butcherbird Stage 2 Expansion Project (Butcherbird or Project). E25 aims to increase Butcherbird’s annual production to 1.1 million tonnes per annum of manganese oxide concentrate in line with the Feasibility Study (FS) announced in January 20241.

Keep reading...Show less
Element 25 Limited

E25 Progresses USA HPMSM Refinery Plans

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to provide an update in relation to it’s planned construction of a high-purity manganese sulphate (HPMSM) refinery in Louisiana USA to supply domestic HPMSM to the US electric vehicle battery industry.

Keep reading...Show less
Element 25 Limited

December 2023 Quarterly Report

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to present its Quarterly Activities and Cash Flow Report.

Keep reading...Show less
Element 25 Limited

Element 25 Limited Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×