Vertex Minerals Limited  Ore Production Update - Reward Gold Mine

Vertex Minerals Limited Ore Production Update - Reward Gold Mine

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) (OTCMKTS:VTXXF) is pleased to announce the establishment of multiple mining fronts in the Reward Underground Mine. The Company is employing multiple mining methods to diversify risk and maximise head grade. These include airleg gallery and shrink stoping, jumbo cut and fill stoping and narrow vein longhole open stoping.

- Stoping of the 1670 airleg stope is well underway with production over the last 5 days of 125 tonnes mined and processed. Today, concentrates from gravity processing are being further concentrated prior to delivery to the gold refinery.

- Commencement of drilling of the 1438 longhole stope commenced on 23 September and the Company expects to be blasting this stope within the next two weeks. Figures 3* and 4* illustrate the stope design targeting production of 660 tonnes at a conservatively estimated grade of 6 g/t Au.

- Preparation for establishment of a cut and fill stope in Decline 3 (1720 Stope) are progressing, with stripping of backs and installation of ground support underway to allow jumbo access for ore production in October.

- The mining team are preparing a development heading on the Amalgamated vein. This is part of the strategy of placing capital access development on veins outside ofthe resource, to quickly advance exploration by mining.

- Electrical power is now distributed to all development and stoping fronts. This has taken longer than planned due to delays in delivery and commissioning of specialised equipment suitable for small development headings.

- Underground radio communication is now installed and operational mine wide. The installation is to best practice reaching all working areas.

- A new Aramine loader was delivered on 23 September 2025 and is now being fitted out for tele-remote operations.

- Reward ore will be processed via the gravity only gold processing plant located at the entry to the mine. No chemicals are used in ore processing to produce gold.

- The underground mine ore will, over time, provide high grade feed to the gravity plant.

- Vertex aims to have developed multiple mining fronts, with over around 400m of strike to achieve continuous feed to the plant. The production ramp up is continuing

The first of these fronts is the 1670 Shrink Stope (airleg), which is now in production. The focus of this stope is low tonnage but high-grade ore.

The second mining front is the establishment of the 1438 Longhole stope, with drilling commencing on 23 September 2025. Figure 3* illustrates an oblique view of the stope while Figure 4* shows a typical drill plan section with the high-grade Mica 1 and Mica 2 veins within the design.

Longhole stoping is a mechanised and highly productive mining method that minimises development requirements. The 1438 includes two high grade veins within the stope which maximises extraction of the resource. The aim of longhole stoping is to provide base load production for gravity processing.

To support longhole stoping the Company has taken delivery of an Aramine 350D loader which is presently being fitted with RCT's remote controlled system, allowing the loader to be remotely piloted for bogging out longhole stopes.

The third mining front is the 1720 cut and fill stope which will utilise jumbo production to mine highgrade Mica and Mica 2 veins. New ground support is presently being installed, and stoping is expected to commence in October 2025.

The fourth mining front is capital development on the Amalgamated Vein as shown in Figure 9. This drive is designed to duplicate and parallel the existing access drive to the Reward Shaft, which will allow the mining of stopes along the existing access drive. It is important to note that capital development is placed on veins outside of the resource and in areas where there is no drilling. This strategy expedites exploration and new discovery through the geological sampling of the developing face and the Company expects that sections of this development will be economic to process and add to gold production. Additional development headings will commence as mine scheduling allows.

Vertex is in the early stages of the underground mine's development. The production ramp up has been delayed largely due to issues in delivery and commissioning of high voltage electrical equipment, however the decision to install 11,000 Volt power distribution will provide outstanding benefit over the entire mine life. Vertex is now into increasing production from the underground mine and anticipates continuous improvement in gold production over the remainder of the year.

The processing of gold ores without the use of chemicals continues to be optimised, with the focus on improving recovery as we switch from processing surface stockpiles to higher grade underground ore.

The Vertex Mining Team aims to exceed the highest safety and environmental standards as we transition to 100% underground mining.

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/728Z10U7



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited



Contact:
Roger Jackson
Executive Chairman

Tully Richards
Technical Director
tully@vertexminerals.com.au

News Provided by ABN Newswire via QuoteMedia

VTX:AU
The Conversation (0)
Reward Gold Mine Production Update

Reward Gold Mine Production Update

youtu.be Vertex Minerals (VTX:AU) has announced Reward Gold Mine Production UpdateDownload the PDF here. Keep Reading...
Underground Production Commences Reward Gold Mine Project

Underground Production Commences Reward Gold Mine Project

Vertex Minerals (VTX:AU) has announced Underground Production Commences Reward Gold Mine ProjectDownload the PDF here. Keep Reading...
Quarterly Activities and Cash Flow Reports 30 June 2025

Quarterly Activities and Cash Flow Reports 30 June 2025

Vertex Minerals (VTX:AU) has announced Quarterly Activities and Cash Flow Reports 30 June 2025Download the PDF here. Keep Reading...
UPDATE Fully Developed Stope Block Announcement (28/04/25)

UPDATE Fully Developed Stope Block Announcement (28/04/25)

Vertex Minerals (VTX:AU) has announced UPDATE Fully Developed Stope Block Announcement (28/04/25)Download the PDF here. Keep Reading...
A$11m Capital Raising to Accelerate Mining at Hill End

A$11m Capital Raising to Accelerate Mining at Hill End

Vertex Minerals (VTX:AU) has announced A$11m Capital Raising to Accelerate Mining at Hill EndDownload the PDF here. Keep Reading...
Metalsource Mining Launches Major Step Out Program With 1.1 km Northern Target to Test Broader Scale of Silver Hill

Metalsource Mining Launches Major Step Out Program With 1.1 km Northern Target to Test Broader Scale of Silver Hill

Phase 2 expands beyond Silver Hill proper while SH26-34 intersects approximately 20 metres of mineralization in drill core, including multiple massive sulphide intervals with assays pending. Surface mineralization and correlated IP anomalies strengthen the case for broader expansion. Metalsource... Keep Reading...
Transition Metals Extends Geochemical Footprint of Haultain Gold System and Identifies New Large-Scale Exploration Targets at Gowganda Project, Ontario

Transition Metals Extends Geochemical Footprint of Haultain Gold System and Identifies New Large-Scale Exploration Targets at Gowganda Project, Ontario

Key Highlights:Recent MMI soil geochemical survey confirms new anomalous gold trend extensions beneath cover and beyond previously tested areas, highlighting large system scale targets for follow-up surface work and drilling.1,300+ B-horizon soil samples collected across approximately 2.5 by 1.5... Keep Reading...
Noble Minerals Prepares for Drill Program on the Lucas Gold Project

Noble Minerals Prepares for Drill Program on the Lucas Gold Project

(TheNewswire) Toronto, Ontario October 7, 2026 TheNewswire - Noble Mineral Exploration Inc. ("Noble" or the "Company") (TSX-V:NOB, FRANKFURT: NB7, OTCQB:NLPXF) is pleased to give an update on the Lucas Gold Project in the Timmins area of Ontario. The drill program is expected to be a total of... Keep Reading...
Feather Cap option exercised

Feather Cap option exercised

Corazon Mining (CZN:AU) has announced Feather Cap option exercisedDownload the PDF here. Keep Reading...
Steadright Files Q1 Interim FS and MD&A / Moroccan Site and Cancellation of Crushing & Grinding Equipment Share Purchase Agreement With Possible Renegotiation

Steadright Files Q1 Interim FS and MD&A / Moroccan Site and Cancellation of Crushing & Grinding Equipment Share Purchase Agreement With Possible Renegotiation

(TheNewswire) Muskoka, Ontario — October 6th, 2026 — TheNewswire - Steadright Critical Minerals Inc. (CSE: SCM,OTC:SCMNF) ("Steadright" or the "Company"), is pleased to announce that it has filed its Q1 Interim Financial Statements and Management's Discussion and Analysis (MD&A) for the three... Keep Reading...
Great Western Mining Corporation PLC Announces Issue of Equity and Grant of Options

Great Western Mining Corporation PLC Announces Issue of Equity and Grant of Options

DUBLIN, IE / ACCESS Newswire / October 6, 2026 / Great Western Mining Corporation PLC ("Great Western", "GWM" or the "Company") (AIM:GWMO)(ESM:8GW) announces the issue of 67,051 new ordinary shares of €0.0001 each at Stg 3.46 pence per share ("Remuneration Shares") in settlement of part of the... Keep Reading...

Interactive Chart

Latest Press Releases

Related News