Western Copper and Gold Announces Positive PEA on Casino

 
 

   $2.3 billion After-Tax NPV (8%) at Base Case metal prices  

 

  After-Tax IRR 19.5% at Base Case metal prices  

 

  Cashflow over the first four years of $965 million per year at Base Case metal prices  

 

  Base case development contemplates 25-year mine life  

 

  Extended Two-Phase development contemplates a 47-year mine life  

 

  Base Case metal prices:  Cu: US$3.35 /lb, Au: US$1,600 /oz, Ag: US$24 /oz, Mo: US$12 /lb  

 

  VANCOUVER, BC , June 22, 2021 /CNW/ - Western Copper and Gold Corporation ("Western" or the "Company") (TSX: WRN) (NYSE American: WRN) is pleased to release the results of its Preliminary Economic Assessment (the "PEA", or "Study") on its wholly-owned Casino copper-gold-molybdenum deposit in the Yukon ("Casino" or the "Project").  The Study considered the Project being constructed as an open pit mine, with a concentrator processing nominally 120,000 tonnes per day and a gold heap leach facility processing nominally 25,000 tonnes per day.

 

 

  Western Copper and Gold Corporation logo (CNW Group/Western Copper and Gold Corporation) 

 
 

The Study supersedes all previous studies and incorporates the updated mineral resource with an effective date of July 3 , 2020.  The Study also incorporates outcomes of the Best Available Tailings Technology Study (the "BATT Study") completed in 2018 with participation by First Nations, the Yukon Environmental and Socio-economic Assessment Board ("YESAB") and the Yukon Government. The design concept for the tailings management facility ("TMF") also reflects the guidance received from the Independent Engineering Review Panel.

 

The Study examines the development of the Casino Project, which comprises the processing of 1.3 billion tonnes of mineralized material for both the mill and heap leach, with deposition of mill tailings and mine waste in the TMF facility consistent with the design concepts considered during the BATT Study as a base case development.

 

"I am extremely pleased with the results from this PEA", said Paul West-Sells , President & Chief Executive Officer. "This Study reaffirms Casino as one of the very few long-life copper-gold projects with robust economics in a top mining district, the Yukon.  We look forward to continuing working with our recent strategic investor, Rio Tinto, First Nations and other stakeholders to advance this project through additional engineering to feasibility."

 

In this news release, unless otherwise indicated, all further references to "$" are to Canadian dollars and references to "US$" are to United States dollars.

 

  HIGHLIGHTS  

 
 
                                        
 
 

   Base Case*   

 
 

   Payback period, years   

 
 

  3.0  

 
 
 
 

   NPV pre-tax (8% discount)   

 
 

  $3.62 billion  

 
 

   NPV after-tax (8% discount)   

 
 

  $2.33 billion  

 
 
 
 

   LOM pre-tax free cash flow   

 
 

  $13.0 billion  

 
 

   LOM after-tax free cash flow   

 
 

  $9.1 billion  

 
 
 
 

   IRR pre-tax (100 % equity)   

 
 

  23.3%  

 
 

   IRR after-tax (100% equity)   

 
 

  19.5%  

 
 
 
 

   Initial Capital Investment   

 
 

  $3.25 billion  

 
 

   Total mineralized material mined   

 
 

  1.3 billion tonnes  

 
 

   Mill mineralized material   

 
 

  1.1 billion tonnes  

 
 

   Heap leach mineralized material   

 
 

  204 million tonnes  

 
 
 
 

   Mill operation   

 
 

  25 years  

 
 

   Heap leach operation   

 
 

  23 years  

 
 

   LOM strip ratio   

 
 

  0.38:1  

 
 
 

Base Case metal prices: Cu: US$3.35 /lb, Au: US$1,600 /oz, Ag: US$24 /oz, Mo: US$12 /lb.

 

  KEY CHANGES FROM THE PREVIOUS STUDY  

 

The engineering design basis for this PEA is similar in most respects to earlier studies but includes several significant design improvements.  The major changes include:

 

  Tailings Management Facility  

 

The TMF is sized to provide sufficient capacity to store approximately 712 Mt of tailings and 500 Mt of mining waste rock and overburden materials. The remaining 415 Mt of non-acid generating ("NAG") tailings will be used for dam construction following classification with hydrocyclones and dewatering screens. The TMF for the PEA includes design changes based on the recommendations from the BATT Study.  The key changes to the TMF design concept include:

 
  • Substantial reduction in the quantity of free-standing water impounded during operations and a corresponding reduction of risk associated with this facility.
  •  
  • Closure by saturated NAG tailings cover limiting the need for a flooded cover.
  •  
  • A tailings dewatering facility to conserve additional coarse sand material for dam construction. Surplus sand produced through cycloning and screening operations will be used to buttress the downstream slopes of the main embankment.
  •  
  • Changes to the design of the starter dam to reduce construction risk.
  •  
  • Added a HDS water treatment facility to provide mitigation for potential water surplus conditions, However, surplus water is not expected under design operating conditions.
  •  

  Updated Mineral Resource  

 

The updated mineral resource, released in July 2020 , was used as the basis of the PEA.  For the purposes of the Study, only the measured and indicated mineral resources were considered as mill or heap leach feed.  Inferred mineral resources in the pit are considered to be waste as there are limited inferred mineral resources in the designed pit.

 

Note that the Study reports on mineral resources, not mineral reserves.  Mineral resources that are not mineral reserves do not have demonstrated economic viability.

 

  Heap Leach Gold Recovery  

 

New column testing on various lithology samples representing the feed to the heap leach indicated that the gold recovery in the heap leach could be increased from 66% to 70%.

 

  Access Road  

 

Costing for the access road was adjusted to incorporate the commitment from the Yukon and Federal government to fund portions of the access road.  More detail can be found in the Western news release dated September 5, 2017 .

 

  Airstrip  

 

The proposed airstrip has been relocated along the access road to limit the potential impact on caribou habitat.

 

  FINANCIAL RESULTS  

 

The Study indicates that the potential economic returns from the Project justify its further development and securing the required permits and licenses for operation.

 

The financial results of the Study were developed under commodity prices that were based on analyst projections of long-term metal prices and CAN$:US$ exchange rate ("Base Case" prices).

 

Note that an exchange rate of CAN$:US$ of 0.80 was used for the capital cost estimation for all metal price scenarios.

 

The following table summarizes the financial results:

 
 
                                          
 
 

   Base Case   

 
 

   Copper (US$/lb)  

 
 

  3.35  

 
 

   Molybdenum (US$/lb)  

 
 

  12.00  

 
 

   Gold (US$/oz)  

 
 

  1,600  

 
 

   Silver (US$/oz)  

 
 

  24.00  

 
 

   Exchange Rate (C$:US$)  

 
 

  0.80  

 
 
 
 

   NPV pre-tax (5% discount, $millions)  

 
 

  5,790  

 
 

   NPV pre-tax (8% discount, $millions)  

 
 

  3,620  

 
 

   IRR pre-tax (100% equity)  

 
 

  23.3%  

 
 
 
 

   NPV after-tax (5% discount, $millions)  

 
 

  3,900  

 
 

   NPV after-tax (8% discount, $millions)  

 
 

  2,330  

 
 

   IRR after-tax (100% equity)  

 
 

  19.5%  

 
 
 
 

   LOM pre-tax free cash flow ($millions)  

 
 

  13,000  

 
 

   LOM after-tax free cash flow ($millions)  

 
 

  9,070  

 
 
 
 

   Payback period (years)  

 
 

  3.0  

 
 

   Net Smelter Return ($/t milled)  

 
 

  28.14  

 
 

   Copper Cash Cost* (US$/lb)  

 
 

  (1.13)  

 
 
 

*C1 cash costs, net of by-product credits.

 

The financial results of the Study are significantly influenced by copper and gold prices, as is shown in the tables below:

 
 
                                          
 

   Copper Price (US$/lb)*   

 
 

   $2.50   

 
 

   $3.00   

 
 

   $3.35   

 
 

   $4.00   

 
 

   $4.50   

 
 

   $5.00   

 
 

  NPV pre-tax (8%) ($M)  

 
 

  2,290  

 
 

  3,070  

 
 

   3,620   

 
 

  4,630  

 
 

  5,410  

 
 

  6,190  

 
 

  NPV after-tax (8%) ($M)  

 
 

  1,400  

 
 

  1,950  

 
 

   2,330   

 
 

  3,040  

 
 

  3,590  

 
 

  4,140  

 
 

  IRR pre-tax  

 
 

  18.5%  

 
 

  21.4%  

 
 

   23.3%   

 
 

  26.6%  

 
 

  29.0%  

 
 

  31.3%  

 
 

  IRR after-tax  

 
 

  15.4%  

 
 

  17.9%  

 
 

   19.5%   

 
 

  22.3%  

 
 

  24.3%  

 
 

  26.2%  

 
 

  Payback (years)  

 
 

  3.7  

 
 

  3.2  

 
 

   3.0   

 
 

  2.7  

 
 

  2.5  

 
 

  2.3  

 
 
 

 

 
 
                                          
 

   Gold Price (US$/oz)*   

 
 

   $1200   

 
 

   $1400   

 
 

   $1600   

 
 

   $1800   

 
 

   $2000   

 
 

   $2200   

 
 

  NPV pre-tax (8%) ($M)  

 
 

  2,580  

 
 

  3,100  

 
 

   3,620   

 
 

  4,130  

 
 

  4,650  

 
 

  5,170  

 
 

  NPV after-tax (8%) ($M)  

 
 

  1,600  

 
 

  1,960  

 
 

   2,330   

 
 

  2,700  

 
 

  3,060  

 
 

  3,430  

 
 

  IRR pre-tax  

 
 

  19.3%  

 
 

  21.3%  

 
 

   23.3%   

 
 

  25.2%  

 
 

  27.1%  

 
 

  29.0%  

 
 

  IRR after-tax  

 
 

  16.1%  

 
 

  17.8%  

 
 

   19.5%   

 
 

  21.1%  

 
 

  22.7%  

 
 

  24.3%  

 
 

  Payback (years)  

 
 

  3.5  

 
 

  3.2  

 
 

   3.0   

 
 

  2.8  

 
 

  2.6  

 
 

  2.5  

 
 
 

*All other metal prices except those noted are the same as the Base Case.

 

Higher grade material is fed to the concentrator during the first four years of the concentrator operation. This factor, combined with the concurrent heap leach facility operation, results in higher yearly cash flows and other metrics during this period and contributes significantly to the Project's financial performance.

 
 
                        
 
 

   Years 1-4   

 
 

   Life of Mine   

 
 

  Average Annual Pre-tax Cash Flow ($millions)  

 
 

  1,081  

 
 

  645  

 
 

  Average Annual After-tax Cash Flow ($millions)  

 
 

  965  

 
 

  528  

 
 

  Average Net Smelter Return (NSR) ($/t ore milled)  

 
 

  41.92  

 
 

  28.14  

 
 

  % of Revenue - Copper  

 
 

  50  

 
 

  47  

 
 

  % of Revenue - Gold  

 
 

  37  

 
 

  36  

 
 

  % of Revenue - Silver  

 
 

  3  

 
 

  3  

 
 

  % of Revenue - Molybdenum  

 
 

  10  

 
 

  14  

 
 
 

  CAPITAL COSTS  

 

Total initial capital investment in the Project is estimated to be $3.25 billion , which represents the total direct and indirect cost for the complete development of the Project, including associated infrastructure and power plant.  The following table shows how the initial capital is distributed between the various components.

 
 
                            
 

   Cost Item   

 
 

   Total ($M)   

 
 

   Process Plant and Infrastructure   

 
 
 

  Project Directs including freight  

 
 

  1,777  

 
 

  Project Indirects  

 
 

  390  

 
 

  Contingency  

 
 

  412  

 
 

   Subtotal   

 
 

   2,579   

 
 

   Mining   

 
 
 

  Mine Equipment  

 
 

  409  

 
 

  Mine Preproduction  

 
 

  211  

 
 

   Subtotal   

 
 

   620   

 
 

  Owner's Costs  

 
 

  52  

 
 

   Total Initial Capital Costs   

 
 

   3,251   

 
 

  Sustaining Capital  

 
 

  719  

 
 

   Total Life of Mine Capital Costs   

 
 

   3,970   

 
 
 

  OPERATING COSTS  

 

Operating costs for the milling operation were calculated per tonne of material processed through the mill over the life of mine:

 
 
          
 
 

   LOM   

 
 
 

   ($/tonne)   

 
 

  Milling  

 
 

  $5.72  

 
 

  General & Administrative  

 
 

  $0.45  

 
 

   Total   

 
 

   $6.17   

 
 
 

Heap leach operating costs were calculated per tonne of material processed through the heap leach over the life of the heap leach.

 
 
          
 
 

   LOM   

 
 
 

   ($/tonne)   

 
 

  Heap Leach Operation  

 
 

  $1.30  

 
 

  ADR/SART  

 
 

  $4.67  

 
 

   Total   

 
 

   $5.98   

 
 
 

Mining costs were calculated to average $1.93 per tonne of material moved and $3.10 per tonne of mineralized material.

 
 
        
 
 

   ($/tonne)   

 
 

  Cost per tonne material (material moved)  

 
 

  $1.93  

 
 

  Cost per tonne mill feed (mill + heap material)  

 
 

  $3.10  

 
 

  Cost per tonne mill feed  

 
 

  $3.66  

 
 
 

The combined mining and milling costs are $9.84 per tonne material milled for the life of mine, which compares favorably to the life-of-mine net smelter return of $28.14 per tonne at Base Case metal prices.

 

  DEVELOPMENT PLAN  

 

The Study evaluates the development of the Casino deposit as a conventional open pit mine, concentrator complex, and heap leach operation. The initial production will focus on the deposit's oxide cap as a heap leach operation to recover gold and silver in doré form. The main sulphide deposit will be processed using a conventional concentrator to produce copper-gold-silver and molybdenum concentrates.  Key metrics of the processing plant are shown below:

 
 
                                                                                                                  
 
 

   Years 1-4   

 
 

   Life of Mine   

 
 

   Strip ratio   

 
 

  0.28  

 
 

  0.38  

 
 

   Nominal Throughput   

 
 
 
 

  Mill (tpd)  

 
 

  120,000  

 
 

  120,000  

 
 

  Heap (tpd)  

 
 

  25,000  

 
 

  25,000  

 
 

   Average Annual Metal Production   

 
 
 
 

  Copper (Mlbs)  

 
 

  252  

 
 

  178  

 
 

  Gold (kozs)  

 
 

  339  

 
 

  231  

 
 

  Silver (kozs)  

 
 

  1,570  

 
 

  1,360  

 
 

  Molybdenum (Mlbs)  

 
 

  16.5  

 
 

  16.6  

 
 

   Average Annual Mill Feed Grade   

 
 
 
 

  Copper (%)  

 
 

  0.312  

 
 

  0.197  

 
 

  Gold (g/t)  

 
 

  0.360  

 
 

  0.226  

 
 

  Silver (g/t)  

 
 

  2.039  

 
 

  1.702  

 
 

  Molybdenum (%)  

 
 

  0.026  

 
 

  0.022  

 
 

   Average Annual Heap Leach Grade*   

 
 
 
 

  Gold (g/t)  

 
 

  0.359  

 
 

  0.259  

 
 

  Silver (g/t)  

 
 

  2.271  

 
 

  1.95  

 
 

  Copper (%t)  

 
 

  0.039  

 
 

  0.034  

 
 

   Recovery (Mill)   

 
 
 
 

  Copper (%)  

 
 

  84.5  

 
 

  86.6  

 
 

  Gold (%)  

 
 

  67.6  

 
 

  67.1  

 
 

  Silver (%)  

 
 

  55.3  

 
 

  53.1  

 
 

  Molybdenum (%)  

 
 

  65.9  

 
 

  71.3  

 
 

   Recovery (Heap)   

 
 
 
 

  Gold (%)  

 
 

  70.0  

 
 

  70.0  

 
 

  Copper (%)  

 
 

  18.0  

 
 

  18.0  

 
 

  Silver (%)  

 
 

  26.0  

 
 

  26.0  

 
 

   Annual Concentrate Production   

 
 
 
 

  Cu (dry ktonnes)  

 
 

  408  

 
 

  288  

 
 

  Mo (dry ktonnes)  

 
 

  13  

 
 

  13  

 
 

   Average Concentrate Grade   

 
 
 
 

  Copper Concentrate  

 
 
 
 

  Cu (%)  

 
 

  28.0  

 
 

  28.0  

 
 

  Au (g/t)  

 
 

  25.9  

 
 

  24.9  

 
 

  Ag (g/t)  

 
 

  119.8  

 
 

  147.1  

 
 

  Molybdenum Concentrate  

 
 
 
 

  Mo (%)  

 
 

  56.0  

 
 

  56.0  

 
 
 

*Heap leach first four years grades taken from the start of the heap leach.

 

  INFRASTRUCTURE  

 

A new 132-km all-weather access road will be developed, extending from the end of the existing Freegold Road and generally following the alignment of the existing "Casino Trail" to the mine site. The Study contemplated that concentrates will be transported, stored and loaded on ships via upgraded facilities provided by the Port of Skagway, Alaska . The Project operating cost estimate includes the anticipated concentrate handling service charges based on use of the upgraded facilities.

 

  SECOND PHASE DEVELOPMENT  

 

The Study also examined extending the operation after treating the first 1.3 billion tonnes of mineralized material (Phase I) for approximately 25 years (Phase II) for a total life-of-mine of 47 years. The extended operation is achieved using the original concentrator and associated infrastructure at the same nominal processing rate of 120,000 tonnes per day. An additional 1 billion tonnes of mineralized material would be processed by the mill during the extended operation. A secondary TMF would be constructed downstream of the original TMF to accommodate the additional tailings and waste rock associated with extended operations.

 

The indicative capital requirements and economic performance indicators for the extended operations scenario is as shown below.  As this table shows, the differences between Phase I capital costs and the combined Phase I + Phase II capital costs are the additional sustaining capital to construct the secondary TMF facility and the mine equipment required to support the Project through the additional years of mine life.

 
 
                                          
 

   Cost Item   

 
 

   Phase I
Total ($M)
 
 

 
 

   Phase I + II   

 

   Total ($M)   

 
 

   Process Plant and Infrastructure   

 
 
 
 

  Project Directs including freight  

 
 

  1,777  

 
 

  1,777  

 
 

  Project Indirects  

 
 

  390  

 
 

  390  

 
 

  Contingency  

 
 

  412  

 
 

  412  

 
 

   Subtotal   

 
 

   2,579   

 
 

   2,579   

 
 

  Mine  

 
 
 
 

  Mine Equipment  

 
 

  409  

 
 

  419  

 
 

  Mine Preproduction  

 
 

  211  

 
 

  206  

 
 

   Subtotal   

 
 

   620   

 
 

   625   

 
 

  Owner's Costs  

 
 

  52  

 
 

  52  

 
 

   Total Initial Capital Cost   

 
 

   3,251   

 
 

   3,256   

 
 

  Sustaining Capital  

 
 

  719  

 
 

  1,808  

 
 

   Total Life of Mine Capital Costs   

 
 

   3,970   

 
 

   5,064   

 
 
 

The net present value and internal rate of return for developing the two-phase project are not significantly different from those for developing the single-phase project, however, the life-of-mine and life-of-mine cash flow increase significantly.  Highlights from developing the Phase I + II development at Base Case metal prices are shown below:

 
 
                                                                              
 
 

   Phase I
Development
 
 

 
 

   Phase I + II Development   

 
 

   NPV pre-tax* (8% discount)   

 
 

  $3.62 billion  

 
 

  $3.70 billion  

 
 

   NPV after-tax* (8% discount)   

 
 

  $2.33 billion  

 
 

  $2.38 billion  

 
 
 
 
 

   LOM pre-tax free cash flow*   

 
 

  $13.0 billion  

 
 

  $17.2 billion  

 
 

   LOM after-tax free cash flow*   

 
 

  $9.1 billion  

 
 

  $12.0 billion  

 
 
 
 
 

   IRR pre-tax* (100 % equity)   

 
 

  23.3%  

 
 

  23.1%  

 
 

   IRR after-tax* (100% equity)   

 
 

  19.5%  

 
 

  19.3%  

 
 
 
 
 

   Total mineralized material mined   

 
 

  1.3 billion tonnes  

 
 

  2.4 billion tonnes  

 
 

   Mill mineralized material   

 
 

  1.1 billion tonnes  

 
 

  2.1 billion tonnes  

 
 

   Heap leach mineralized material   

 
 

  204 million tonnes  

 
 

  240 million tonnes  

 
 

   Average annual mill feed grades   

 
 
 
 

  Copper (%)  

 
 

  0.197  

 
 

  0.163  

 
 

  Gold (g/t)  

 
 

  0.226  

 
 

  0.192  

 
 

  Silver (g/t)  

 
 

  1.70  

 
 

  1.507  

 
 

  Molybdenum (%)  

 
 

  0.022  

 
 

  0.018  

 
 

   Average annual heap leach grades*   

 
 
 
 

  Gold (g/t)  

 
 

  0.259  

 
 

  0.245  

 
 

  Silver (g/t)  

 
 

  1.95  

 
 

  1.87  

 
 

  Copper (g/t)  

 
 

  0.034  

 
 

  0.034  

 
 
 
 
 

   Mill operation   

 
 

  25 years  

 
 

  47 years  

 
 

   Heap leach operation   

 
 

  23 years  

 
 

  33 years  

 
 

   LOM waste:ore ratio   

 
 

  0.38:1  

 
 

  0.47:1  

 
 
 

*Based on Base Case metal prices: Cu: US$3.35 /lb, Au: US$1,600 /oz, Ag: US$24 /oz, Mo: US$12 /lb

 

  STAKEHOLDER ENGAGEMENT  

 

The Project is located within the traditional territory of Selkirk First Nation. Aspects of the Project impact the traditional territories of the Little Salmon/Carmacks First Nation, Tr'ondëk Hwëch'in, Kluane First Nation and White River First Nation.  The nearest communities are the Village of Carmacks and Pelly Crossing , and the Project is 200 km upstream of Dawson City along the Yukon River.

 

Western is committed to developing and operating the Project in a safe, ethical and socially responsible manner. Western has been consulting extensively on the Project since 2008, and First Nations and their technical advisors have participated directly in the refinement of the tailings and mine waste strategy at the Project, as reflected in the design presented in the PEA.

 

Since 2006, Western has spent over $75 Million in Yukon advancing the Project, working with over 50 different Yukon and First Nations joint venture companies. Western is active in the local community, with longstanding support and sponsorship of over 30 local organizations and charities.

 

As the Project is further refined, Western will continue to seek feedback from and partnerships with local First Nations and communities and is committed to developing the Project with First Nations' and local community input.

 

  LOOKING FORWARD  

 

Based on the positive results of the Study, Western plans to advance the Project to establish a mineral reserve estimate for the Project with the ultimate objective of submitting an application for environmental assessment under the Yukon Environmental and Socioeconomic Assessment Act, the first step in the permitting process.

 

  CONFERENCE CALL  

 

Western will hold a conference call and webcast on   Tuesday, June 22, 2021   at   8 am Pacific Time   ( 11 am Eastern Time ) to discuss the Study.

 

Webcast access: https://services.choruscall.ca/links/westerncopperandgold20210622.html  

 

Telephone access:
Vancouver local and International     1-604-638-5340
Toll Free North America:   1-800-319-4610

 

An archived recording of the conference call will be available by dialing 1-604-638-9010 or 1-800-319-6413 within North America , passcode is 7194.  The webcast and presentation slides will be archived on the Company's website www.westerncopperandgold.com .

 

  TECHNICAL REPORT & QUALIFIED PERSONS  

 

M3 Engineering & Technology Corporation ("M3), a full-service Engineering, Procurement, Construction & Management firm, is recognized for its experience in copper processing and capabilities in the development and construction of mines and mineral processing plants.  A National Instrument 43-101 (NI 43-101) compliant technical report prepared by the following Qualified Persons will be posted on the Company's website ( www.westerncopperandgold.com ) as well as on SEDAR ( www.sedar.com ), and on EDGAR within 45 days:

 
  •   Daniel Roth , P.Eng. of M3 – Overall scientific and technical information, with a focus on project infrastructure, capital costs, and the economic analysis.
  •  
  •   Laurie Tahija , MMSA-QP, of M3 – Metallurgy, recovery methods, and process operating costs.
  •  
  •   Michael G. Hester , F Aus IMM, of Independent Mining Consultants – Resource estimation, mining methods and mining costs.
  •  
  •   Carl Schulze , P.Geo., of Aurora Geosciences – History, geology, exploration, drilling, and sampling.
  •  
  •   Caroline J. Vallat , P.Geo., of GeoSpark Consulting Inc. – Data verification.
  •  
  •   Daniel Friedman , P.Eng., of Knight Piésold Ltd. – Tailings and heap leach facilities.
  •  

The Qualified Persons have reviewed and approved the scientific, technical, and economic information contained in this news release.

 

  ABOUT Western Copper and Gold Corporation  

 

 Western Copper and Gold Corporation is developing the Casino Project, Canada's premier copper-gold mine in the Yukon Territory and one of the most economic greenfield copper-gold mining projects in the world.  For more information, visit www.westerncopperandgold.com .

 

On behalf of the board,

 

  "Paul West-Sells"
Dr. Paul West-Sells  
President and CEO
Western Copper and Gold Corporation 

 

  Cautionary Disclaimer Regarding Forward-Looking Statements and Information  

 

  Mineral resources that are not mineral reserves do not have demonstrated economic viability. Therefore, investors are cautioned not to assume that all or any part of an inferred mineral resource could ever be mined economically. It cannot be assumed that all or any part of "measured mineral resources," "indicated mineral resources," or "inferred mineral resources" will ever be upgraded to a higher category. The mineral resource estimates contained herein may be subject to legal, political, environmental or other risks that could materially affect the potential development of such mineral resources. See the technical report, once filed, for more information with respect to the key assumptions, parameters, methods and risks of determination associated with the foregoing. The PEA is preliminary in nature, includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA will be realized.  

 

  This news release contains certain forward-looking statements concerning anticipated developments in Western's operations in future periods. Statements that are not historical fact are "forward-looking statements" as that term is defined in the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" as that term is defined in National Instrument 51-102 ("NI 51-102") of the Canadian Securities Administrators (collectively, "forward-looking statements"). Certain forward-looking information should also be considered future-oriented financial information ("FOFI") as that term is defined in NI 51-102. The purpose of disclosing FOFI is to provide a general overview of management's expectations regarding the anticipated results of operations and capital expenditures and readers are cautioned that FOFI may not be appropriate for other purposes. Forward-looking statements are frequently, but not always, identified by words such as "expects", "anticipates", "believes", "intends", "estimates", "potential", "possible" and similar expressions, or statements that events, conditions or results "will", "may", "could" or "should" occur or be achieved. These forward-looking statements may include, but are not limited to, statements regarding: mineral resource estimation; mine plan and operations; internal rate of return; sensitivities; net present value; potential recoveries; design parameters; economic potential; processing mineralized material; the potential of robust economics at Casino; advancing the Project through additional engineering and towards the next step in permitting and submission of an environmental and socio-economic effects statement; key changes to the TMF design; increases to the gold recovery in the heap leach; potential economic returns from the Project; estimated initial capital investment costs; estimated operating costs; estimated mining costs; development of the airstrip and all weather access road; anticipated concentrate handling service charges; developing and operating the Project in a safe, ethical and socially-responsible manner; plans for further development and securing the required permits and licenses for further studies to consider operation; market price of precious and base metals; or other statements that are not statement of fact. The material factors or assumptions used to develop forward-looking statements include prevailing and projected market prices and foreign exchange rates, exploration estimates and results, continued availability of capital and financing, construction and operations, the Company not experiencing unforeseen delays, unexpected geological or other effects, equipment failures, permitting delays, and general economic, market or business conditions and as more specifically disclosed throughout this document, and in the AIF and Form 40-F.  

 

  Forward-looking statements are statements about the future and are inherently uncertain, and actual results, performance or achievements of Western and its subsidiaries may differ materially from any future results, performance or achievements expressed or implied by the forward-looking statements due to a variety of risks, uncertainties and other factors. Such risks and other factors include, among others, risks involved in fluctuations in gold, copper and other commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; risks related to joint venture operations; risks related to cooperation of government agencies and First Nations in the development of the property and the issuance of required permits; risks related to the need to obtain additional financing to develop the property and uncertainty as to the availability and terms of future financing; the possibility of delay in construction projects and uncertainty of meeting anticipated program milestones; uncertainty as to timely availability of permits and other governmental approvals; and other risks and uncertainties disclosed in Western's AIF and Form 40-F, and other information released by Western and filed with the applicable regulatory agencies.  

 

  Western's forward-looking statements are based on the beliefs, expectations and opinions of management on the date the statements are made, and Western does not assume, and expressly disclaims, any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as otherwise required by applicable securities legislation. For the reasons set forth above, investors should not place undue reliance on forward-looking statements.  

 
 
 

 Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/western-copper-and-gold-announces-positive-pea-on-casino-301317146.html  

 

SOURCE Western Copper and Gold Corporation 

 

 

 

 Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/June2021/22/c3807.html  

 
 

News Provided by Canada Newswire via QuoteMedia

Western Copper and Gold

Western Copper and Gold Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Western Copper and Gold Corporation (TSX:WRN, NYSE:WRN)

Western Copper and Gold

Keep reading...Show less

Developing a World-Class Copper-Gold Asset in the Yukon

Loyal Metals Limited

Loyal to Acquire the High-Grade Highway Reward Copper Gold Mine

Loyal Metals Limited (ASX:LLM) (Loyal, LLM, or the Company) is pleased to announce that it has acquired a binding option to purchase the Highway Reward Copper Gold Mine in Queensland, Australia, one of the highest-grade copper mines worldwide, with past production totalling 3.65 million tonnes at 5.7% Cu and 260,000 tonnes at 4.5 g/t Au 1-9. This acquisition is the first step in Loyal’s 2025 Strategic Plan to broaden its critical minerals portfolio into copper. No exploration has been conducted on the mining leases since mining ceased in July 2005, despite a ~680% increase in copper prices and a ~1,256% increase in gold prices since the 1997 feasibility study 3,4. With over $4.4 million in funding, Loyal is well-positioned to revisit the high-grade Highway Reward Copper Gold Mine by deploying modern exploration techniques11.

Keep reading...Show less
Textured copper ribbons weave over a black background.

​Copper​ Market Hit by Major Supply Squeeze as LME Inventories Drop

One of the sharpest copper supply crunches in recent memory is rattling global commodities markets, as inventories at the London Metal Exchange (LME) plummet and the spot price soars.

Bloomberg reported that as of Monday (June 23), copper for immediate delivery was trading at a premium of US$345 per metric ton over three month futures, the widest spread since a record squeeze in 2021.

That dramatic price divergence reflects the market’s acute concerns over access to physical copper, with readily available inventories on the LME falling by around 80 percent this year alone.

Keep reading...Show less
Many copper bobbins and warehouse copper pipes.

Top 10 Copper-producing Companies

Copper miners with productive assets have much to gain as supply and demand tighten.

In May 2024, the copper price hit a new all-time high of US$10,954 per metric ton (MT) on the London Metal Exchange and US$5.20 per pound on the COMEX on the back of increasing demand and growing supply concerns.

Copper is one of the most important resources for the energy transition. However, in recent years, demand for the red metal has outpaced mining supply. While construction and electrical grids have long been major markets for copper, today the rise in demand for electric vehicles, EV charging infrastructure and energy storage applications are emerging drivers of copper consumption.

Another trend driving future copper demand is the rapid urbanization in the Global South, as rural populations migrate to cities, putting pressure on electricity grids.

Keep reading...Show less
White Cliff Minerals

John Hancock to join White Cliff Minerals Board

Astrotricha Capital SEZC appointed Advisors

White Cliff Minerals Limited (“WCN” or the “Company”) (ASX: WCN; OTCQB: WCMLF) is pleased to announce that John Hancock will join the Board of White Cliff Minerals effective 1 August 2025.

Keep reading...Show less
Gavel on books with "5 Top Canadian Mining Stocks This Week" text overlay.

Top 5 Canadian Mining Stocks This Week: Royalties Jumps 183 Percent on Legal Win

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX, TSXV and CSE, starting with a round-up of Canadian and US news impacting the resource sector.

Friday (June 20) was the last day for the spring session of Canada’s parliament before its summer break.

On the agenda for the day was a vote on bill C-5, “The One Canadian Economy Act,” which was introduced on June 5.

Keep reading...Show less
Cyprium Metals

Nifty Copper Project Virtual Site Visit

Cyprium Metals Limited (ASX: CYM, OTC: CYPMF) (Cyprium or the Company) invites shareholders to join an investor webinar and live Q&A hosted by Executive Chairman Matt Fifield on Tuesday 24th June 2025. Investors will be guided on a virtual site visit of the Nifty Copper Complex showcasing the sulphide and heap leach resources and extensive brownfield infrastructure.

Keep reading...Show less
Western Copper and Gold

Western Copper and Gold Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×