SilverCrest Announces Completion of Construction and Start of Commissioning Activities at Las Chispas

TSX: SIL | NYSE American: SILV

SilverCrest Metals Inc. ("SilverCrest" or the "Company") is pleased to announce that Ausenco Engineering Canada Inc. ("Ausenco") has completed construction and handed over the Las Chispas processing plant to SilverCrest, ahead of the Feasibility Study* schedule. Other construction activities handled directly by SilverCrest (road, bridge, dry stack tailings facility, temporary diesel power plant and assay lab) have also been completed.

Processing plant commissioning is now underway with the plant expected to reach commercial production in Q4, 2022. Given the extensive amount of underground development completed to date, there is a significant amount of stockpiled ore on surface to allow for a more measured ramp-up of underground mining over the first few years of production and increased operational flexibility. The Feasibility Study outlined a plan in which the process plant will not be fed exclusively from underground mined material until 2025.

Operations are currently being powered by both the diesel generators and the partially completed power line, which collectively is providing all of the Las Chispas power requirements. SilverCrest anticipates fully transitioning away from the diesel generators in H2, 2022 as CFE (Comision Federal de Electricidad, Mexico's power authority) finalizes its portion of the power line.

While the final capital costs incurred remain to be settled, the capital cost of the Las Chispas Project is anticipated to be below the US$137.7 million budget estimated in the Feasibility Study.

N. Eric Fier , CEO, remarked, "We are extremely proud to achieve this key milestone, ahead of schedule and under budget. I commend all who have been involved in the project to date and thank our stakeholders, including local communities, for their continued support. Completing construction marks a significant de-risking step as we move towards becoming a high-grade precious metal producer. With our skilled and experienced team in place, we are well positioned to work through commissioning and ramp-up to achieve commercial production in Q4, 2022. While doing so, we will continue with exploration, advancing ongoing projects in the nearby communities, and looking at ways to add further value for our shareholders."

Pierre Beaudoin , COO, commented, "I would like to thank the combined team of Ausenco and SilverCrest for their continued efforts over the past 17 months. Completing construction during the COVID-19 pandemic has tested everyone's resilience and it is with great satisfaction that I congratulate them for accomplishing an incredible trio of successes: No major accidents, below budget and ahead of schedule. I am convinced that this will be amongst the highlights of their respective careers. With handover now complete, we are excited to take the project forward into production.  It is also with great pleasure to announce that we have opened a new assay lab in the nearby community of Arizpe ( Sonora, Mexico ), which has created a significant number of new local jobs that may be sustained beyond the mine life of Las Chispas."

* NI 43-101 Technical Report & Feasibility Study on the Las Chispas Project dated January 4, 2021 ("Feasibility Study").

ABOUT SILVERCREST METALS INC.
SilverCrest is a Canadian precious metals exploration and development company headquartered in Vancouver, BC , that is focused on new discoveries, value-added acquisitions and near-term production in Mexico's historic precious metal districts. The Company's top priority is on the high-grade, historic Las Chispas mining district in Sonora, Mexico , where it has completed construction of its Las Chispas Project and is proceeding with commissioning. SilverCrest is the first company to successfully drill-test the historic Las Chispas Property resulting in numerous high-grade precious metal discoveries. The Company is led by a proven management team in all aspects of the precious metal mining sector, including taking projects through discovery, finance, on time and on budget construction, and production.

FORWARD-LOOKING STATEMENTS
This news release contains "forward-looking statements" and "forward-looking information" (collectively "forward-looking statements") within the meaning of applicable Canadian and United States securities legislation. These include, without limitation, statements with respect to: the timing and expectations of the Company completing commissioning and ramp up and achieving commercial production in Q4, 2022, connection to the power grid in H2, 2022, and underground development to reach full capacity in 2025. Such forward-looking statements or information are based on a number of assumptions, which may prove to be incorrect. Assumptions have been made regarding, among other things: impact of the COVID-19 pandemic; the reliability of mineralization estimates, mining and development costs, the conditions in general economic and financial markets; availability of skilled labour; timing and amount of expenditures related to rehabilitation and drilling programs; and effects of regulation by governmental agencies. The actual results could differ materially from those anticipated in these forward-looking statements as a result of risk factors including: uncertainty as to the impact and duration of the COVID-19 pandemic; the timing and content of work programs; results of exploration activities; the interpretation of drilling results and other geological data; receipt, maintenance and security of permits and mineral property titles; environmental and other regulatory risks; project cost overruns or unanticipated costs and expenses; and general market and industry conditions. Forward-looking statements are based on the expectations and opinions of the Company's management on the date the statements are made. The assumptions used in the preparation of such statements, although considered reasonable at the time of preparation, may prove to be imprecise and, as such, readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date the statements were made. The Company undertakes no obligation to update or revise any forward-looking statements included in this news release if these beliefs, estimates and opinions or other circumstances should change, except as otherwise required by applicable law.

N. Eric Fier , CPG, P.Eng
Chief Executive Officer
SilverCrest Metals Inc.

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/silvercrest-announces-completion-of-construction-and-start-of-commissioning-activities-at-las-chispas-301555527.html

SOURCE SilverCrest Metals Inc.

Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/May2022/26/c8772.html

News Provided by Canada Newswire via QuoteMedia

SIL:CA,SILV
The Conversation (0)
Bar graph with fluctuating data over a black background.

Sunshine Silver Mining Shares Jump 11 Percent in NYSE Debut

Sunshine Silver Mining & Refining Company (NYSE:SSMR) surged 11 percent in its NYSE debut on Thursday (June 4), raising US$270 million to resurrect one of the highest-grade silver assets in the US.Trading under the ticker SSMR, the stock opened at US$15. Sunshine priced its initial public... Keep Reading...
Green pushpin placed over Mexico.

Silver Linings: The Mexican Silver Belt

The Mexican Silver Belt (La Faja de Plata) is an 800 kilometer long geographical corridor cutting across Northern and Central México. It stretches from Chihuahua and Sonora at the border with the US to the Central México state of Guanajuato, following the Sierra Madre Occidental mountain range,... Keep Reading...
Prince Reports 27.43 Metres Grading 93.7 g/t Silver, 12.0% Mn, 2.29% Pb and 2.48% Zn at Its Prince Silver Project in Nevada;

Prince Reports 27.43 Metres Grading 93.7 g/t Silver, 12.0% Mn, 2.29% Pb and 2.48% Zn at Its Prince Silver Project in Nevada;

Mobilizes Third RC Drill Rig to Accelerate Ongoing 9,000-metre Drill Program

Prince Silver Corp. (CSE: PRNC) (OTCQX: PRNCF) (FSE: T130) ("Prince Silver" or the "Company") is pleased to announce additional assay results from its ongoing 9,000-metre reverse circulation ("RC") drilling program at the Company's Prince Silver Project ("Prince" or the "Prince Project"),... Keep Reading...
Three wooden blocks with black letters "M&A" rest on a computer keyboard.

Elemental Secures Panuco Silver-Gold Royalty in US$239 Million Vizsla Deal

Elemental Royalty (TSX:ELE,NASDAQ:ELE) has inked a US$239 million deal to acquire Vizsla Royalties (TSXV:VROY,OTCQX:VROYF), securing long-life exposure to the Panuco silver-gold project. The acquisition grants Elemental an uncapped 2 to 3.5 percent net smelter return royalty on the Mexico-based... Keep Reading...
A metallic paper airplane rests on a smooth light gray surface.

Record Silver Price a Key Q1 Tailwind for Miners

Following an unprecedented first quarter that saw silver prices break into triple digits before sharply correcting, the sector’s top producers registered massive cash generation and bolstered balance sheets. Silver achieved a historic milestone early in the first quarter, surging past US$100 an... Keep Reading...

Interactive Chart

Latest Press Releases

Related News