Mt Cattlin Ore Reserve update confirms mine life extension

Mt Cattlin Ore Reserve update confirms mine life extension

Allkem Limited (ASX: AKE, " Allkem " or the " Company ") provides an Ore Reserve update for its Mt Cattlin operation in Western Australia (" WA ").

HIGHLIGHTS

  • Ore Reserve tonnage increased 34% to 7.8Mt at 1.20% Li 2 O and 130ppm Ta 2 O 5 at a cut-off grade of 0.4% Li 2 O.
  • The Ore Reserve and planned mining schedule suggests a projected Life-of-Mine for the next 4-5 years (2027-2028) via open pit mining methods. The Ore Reserve has increased with higher grade despite mining depletion to support production. The recent category upgrades in the latest Mineral Resource Estimate, and substantial increases in revenue pricing for spodumene concentrate have contributed to the increase in Ore Reserves.
  • The next mining stage (Stage 4) consists of two separate cutbacks (Stage 4-1 and 4-2) to optimise ore presentation. A mining proposal for Stage 4 has been submitted to WA regulators and is anticipated to be received by the end of CY23.
  • The Board has approved mining of the first cutback (Stage 4-1) of the open pit, which will result in continued spodumene production into 2026.
  • In the second cutback (Stage 4-2), the increasing waste/ore strip ratio at depth via open pit mining methods is being evaluated against an alternate underground mining option. The company sees significant opportunity in transitioning to an underground mine including the unlocking of greater orebody extension potential and prolonging the life of mine.
  • An underground Feasibility Study is expected to be delivered by Q1 CY24. It will enable a variety of scenarios to be modelled and will ensure an optimised future mining method is selected.

ORE RESERVE ESTIMATE

The Mt Cattlin Ore Reserve estimate is based on the Mineral Resource Estimate of 12.8Mt at 1.3% Li 2 O grade and 179ppm Ta 2 O 5 , released on 17 April 2023 . The Mineral Resource was updated after the completion of a major infill drilling program which successfully upgraded Inferred Mineral Resources with 92% of the total Mineral Resource tonnage now classified as Indicated Mineral Resources.

Allkem has reviewed and updated the Mt Cattlin Ore Reserve (Table 1 below), incorporating infill drilling results from the 2NW deposit, depleted mined material and site stockpiles at 31 March 2023 and material to be mined after this date are presented in accordance with JORC (2012) Ore Reserve Reporting.

Table 1: Mt Cattlin Ore Reserve Update as at 31 March 2023

Classification Location Ore Tonnes
(Mt)
Grade Li 2 O
(%)
Grade Ta 2 O 5
(ppm)
Contained
Metal (‘000) t
Li
2 O)
Contained
Metal (‘000) lbs
Ta
2 O 5
Proved In-situ - - - - -
Probable In-situ 6.1 1.3 130 80 1,800
Stockpiles 1.8 0.8 99 14 380
Total Ore Reserve 7.8 1.2 130 93 2,200

Notes: Ore Reserves are reported above a cut-off grade of 0.4 % Li 2 O. The reported Ore Reserve incorporates regularisation of the Mineral Resource to a Selective Mining Unit of dimension 5.0 m x 5.0 m x 2.5 m (East, North, Elevation), with no additional mining dilution or mining recovery factors applied. Estimates have been rounded to a maximum of two significant figures, thus sum of columns may not equal.

Reserve Methodology

Pit optimisations have been carried out using a fixed spodumene concentrate sale price of US$1,500/t and an exchange rate of 0.7 USD:AUD. Whittle pit optimisation software has been used to identify the preferred pit shell on which the pit design was based.

The target design shells were selected to provide a logically phased mine life that maintains future optionality to further evaluate the trade-off between the larger second phase cutback compared to, or in conjunction with, underground mining.

The current mine sequence is based on:

  • Continued mining of the current stage (Stage 3) of the 2NW pit to completion,
  • Phasing of the next stage (Stage 4) into two separate cutbacks to manage the strip ratio and provide smoother ore supply to the processing plant; and
  • The timing of a Mining Proposal that has been lodged in May with WA regulators to extend the current pit and allow for both cutbacks. The associated documentation, including updated Mine Closure Plan, will be reviewed in due course and is anticipated to be approved by the end of CY23.

The mine plan is shown to be technically and financially feasible with an overall life of mine (LOM) ore: waste strip ratio of 19.8:1. A suitable cashflow positive buffer exists below the assumed product prices to provide confidence that the Ore Reserve estimate will be financially viable within a reasonably expected range of possible product prices.

Figure 1: Mt Cattlin Cross section Looking East

Mt Cattlin Cross section Looking East


Figure 2: Mt Cattlin Stage 4 Open Pit Plan

Mt Cattlin Stage 4 Open Pit Plan


Figure 3: Mt Cattlin Stage 4 Open Pit Plan

Mt Cattlin Stage 4 Open Pit Plan

Prior to the current 2023 Ore Reserve estimate, the most recent estimate (Table 2) was a depletion by Allkem as of 30 June 2022. The 2023 Ore Reserve estimate shows the total reserves have increased despite the mining depletion that has occurred since the previous reserve statement. Mineral Resource conversion from Inferred to Indicated and the economic environment around Lithium have contributed to the increase in Ore Reserves.

Table 2: Mt Cattlin Ore Reserve at 30 June 2022

Category
Tonnage
Mt
Grade
% Li2O
Grade
ppm Ta2O5
Contained metal
(‘000) t Li2O
Contained metal
lbs Ta2O5
Proven - - - - - %
Probable 2NW only 3.3 1.12 105 37.0 764,000
Stockpiles 2.4 0.80 122 19.0 646,000
Total 5.8 0.98 113 56.0 1,410,000

Notes: Reported at cut-off grade of 0.4 % Li 2 O within current mine design. The preceding statements of Ore Reserves conforms to the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code) 2012 edition. All tonnages reported are dry metric tonnes. Reported with 17% dilution and 93% mining recovery. Revenue factor US$650/tonne applied. Minor discrepancies may occur due to rounding to appropriate significant figures.

A description of the major factors that resulted in changes from the 2023 Ore Reserve to the 2022 Ore Reserve is as follows:

  • An updated 2022 Mineral Resource Estimate with higher grade and increased tonnages in the Indicated category;
  • Increased pit shell from US$650/tonne to US$1,500/tonne; and
  • Decrease in Ore Reserves due to ongoing open pit mining and stockpile processing.

NEXT STEPS

Underground Feasibility Study

The Underground Feasibility Study is underway and will trade off optimised mining methodologies to improve the most beneficial/more economic outcomes. The study is expected to be completed by early CY24. The approval to proceed as an underground mine will be compared with the existing Open Pit Feasibility Study and also consider the potential for future upside (i.e. orebody continuation at depth).

Step out drilling

It was observed that both the USD 1,100 and 1,500 RPEEE Mineral Resource iterations remain limited by a lack of drilling data which will be resolved by further step out drilling planned for later in CY23.

RESOURCE AND RESERVE CONTROLS & GOVERNANCE

Allkem ensures that quoted Mineral Resource and Ore Reserve estimates are subject to internal controls and external review at both project and corporate levels. Mineral Resource and Ore Reserves are estimated and reported in accordance with the 2012 edition of the JORC Code. Further information is available in the appendices and JORC Table 1.

Allkem stores and collects exploration data using industry standard software that contains internal validation checks. Exploration samples from drilling have certified reference material standards introduced to the sample stream at set ratios, typically 1 per 25 samples. These are reported as necessary to the relevant Competent Persons to assess both accuracy and precision of the assay data applied to resource estimates. In resource modelling, block models are validated by checking the input drill hole composites against the block model grades by domain.

Allkem engages independent, qualified experts on a commercial fee for service basis, to undertake Mineral Resource and Ore Reserve audits. Allkem internally reconciles the resource outcomes to validate both the process and the outcome.

The Company has developed its internal systems and controls to maintain JORC compliance in all external reporting, including the preparation of all reported data by Competent Persons who are members of the Australasian Institute of Mining and Metallurgy or a ‘Recognised Professional Organisation'. As set out above, the Mineral Resource and Ore Reserve statements included in this announcement were reviewed by suitably qualified Competent Persons (below) prior to their inclusion, in the form and context announced.

PROJECT ECONOMICS

Project economics for the full stage 4 expansion are set out below and will be updated following approval to proceed with stage 4-2 and/or an underground option.

Operating costs

Operating cash costs for the LOM are estimated at US$935/dmt produced. It incorporates the remainder of the current Stage 3 open pit, Stage 4 open pits, and processing of end-of-life stockpiles from 1 April 2023 to end of mine life.

The table below proves a summary of the estimated LOM annual unitary cost by category.

Table 3: Estimated LOM operating cost by category

LOM Operating Cash Cost US$/dmt produced
Costs
Mining 445
Processing 268
General & Administration 68
Site Operating Costs 780
Transport & Logistics 40
Cash & Operating Costs 821
Royalties 126
By-Product credits -12
FOB Cash Cost 935


Commodity prices

Forecast pricing for benchmark 6.0% Li 2 O spodumene concentrate has been sourced from independent market analyst group Wood Mackenzie 1 and discounted for costs and penalties to give a Realised Price. The final pricing used is effectively net A$ FOB.

Tantalite (Ta 2 O 5 ) concentrate is a by-product that contributes meaningful, but not material, revenue to the project. A flat sale price based on existing contracts has been applied to expected production.

A forward USD: AUD exchange rate forecast provided by Allkem has been used for this study, as shown in Table 4.

Table 4: Forward Estimates for Concentrate Price and Foreign Exchange

Period

Realised Li 2 O Exchange rate Realised Li 2 O Realised Ta 2 O 5
US$/dmt AUD:USD A$/dmt A$/dry lb
H2 CY23 4,048 0.70 5,783 34.72
CY24 2,074 0.70 2,963 34.72
CY25 1,425 0.70 2,036 34.72
CY26 2,375 0.70 3,393 34.72
CY27 2,103 0.70 3,004 34.72
CY28 1,762 0.70 2,517 34.72
H1 CY29 1,486 0.70 2,123 34.72


The cashflow model was also tested at a conservative realised price of US$1,500/dmt Li 2 O in the optimisation, and cashflows remained positive for the overall Ore Reserve, and on each stage.

____________________________________
1 The data and information provided by Wood Mackenzie should not be interpreted as advice and you should not rely on it for any purpose. You may not copy or use this data and information except as expressly permitted by Wood Mackenzie in writing. To the fullest extent permitted by law, Wood Mackenzie accepts no responsibility for your use of this data and information except as specified in a written agreement you have entered into with Wood Mackenzie for the provision of such of such data and information.


Economic evaluation

An economic evaluation was conducted by consultants Entech Mining using financial data sourced from Allkem, independent market analysis, and competitive tender.

Project economics for all of Stage 4 is forecast to generate a NPV of US$1.2B (A$1.7B) when evaluated with the prices in Table 4. Economics will be updated following approval to proceed with stage 4-2 or as an underground option

As an existing operation, Mt Cattlin requires only minor initial capital expenditure to support the Stage 4 expansion, and low total project capital requirements of approximately US$80m (A$115m). This will be funded from operating cashflow.

The economic model calculates Net Present Value (NPV) at a discount rate of 10% over the LOM from 31 March 2023. The NPV is based on financial model period cashflows, without allowance for taxation, depreciation, or financing provisions. The summary of this is shown in Table 5.

Table 5: Summary of Mt Cattlin Project Economics

Parameter Unit Stage 3 Stage 4-1 Stage 4-2 Closure
Stockpiles
Total
Product Produced Mt 0.4 0.2 0.3 0.1 1.0
Life-Of-Mine Revenue A$B 1.8 0.5 1.0 0.3 3.5
Life-Of-Mine Total Expenditure A$B 0.4 0.4 0.6 0.2 1.5
Life-Of-Mine Free Cashflow A$B 1.4 0.1 0.4 0.1 2.0
Free Cashflow Margin % 80% 22% 37% 36% 57 %
Life-Of-Mine NPV A$B 1.4 0.1 0.2 0.1 1.7


Sensitivity analysis

Sensitivity analysis was conducted on the following variables (+/-20%) and quantified with the NPV outputs:

  • Revenue factors: spodumene concentrate price, currency exchange rate and plant recovery
  • Cost factors: mining operating costs and processing operating costs

The results are graphically summarised in Figure 4. The outputs show the expected heightened sensitivity from revenue factors compared to cost factors. The plant recovery and revenue trends mimic each other, and currency exchange rate (FX) is the inverse. The cost sensitivity trends of the mining and processing operating costs mimic each other with mining being somewhat influential on cashflow and NPV due to being a larger overall cost.

Figure 4: NPV Sensitivity to Key Revenue and Cost Factor Variables

NPV Sensitivity to Key Revenue and Cost Factor Variables

ENDS

This release was authorised by Mr Martin Perez de Solay, CEO and Managing Director of Allkem Limited.

Allkem Limited

ABN 31 112 589 910

Level 35, 71 Eagle St
Brisbane, QLD 4000
Investor Relations & Media Enquiries

Andrew Barber
M: + 61 418 783 701 E: Andrew.Barber@allkem.co

Phoebe Lee
P: +61 7 3064 3600 E : Phoebe.Lee@allkem.co
Connect

info@allkem.co
+61 7 3064 3600
www.allkem.co

IMPORTANT NOTICES

This investor ASX/TSX release ( Release ) has been prepared by Allkem Limited (ACN 112 589 910) (the Company or Allkem ). It contains general information about the Company as at the date of this Release. The information in this Release should not be considered to be comprehensive or to comprise all of the material which a shareholder or potential investor in the Company may require in order to determine whether to deal in Shares of Allkem. The information in this Release is of a general nature only and does not purport to be complete. It should be read in conjunction with the Company's periodic and continuous disclosure announcements which are available at allkem.co and with the Australian Securities Exchange ( ASX ) announcements, which are available at www.asx.com.au .

This Release does not take into account the financial situation, investment objectives, tax situation or particular needs of any person and nothing contained in this Release constitutes investment, legal, tax, accounting or other advice, nor does it contain all the information which would be required in a disclosure document or prospectus prepared in accordance with the requirements of the Corporations Act 2001 (Cth) ( Corporations Act ). Readers or recipients of this Release should, before making any decisions in relation to their investment or potential investment in the Company, consider the appropriateness of the information having regard to their own individual investment objectives and financial situation and seek their own professional investment, legal, taxation and accounting advice appropriate to their particular circumstances.

This Release does not constitute or form part of any offer, invitation, solicitation or recommendation to acquire, purchase, subscribe for, sell or otherwise dispose of, or issue, any Shares or any other financial product. Further, this Release does not constitute financial product, investment advice (nor tax, accounting or legal advice) or recommendation, nor shall it or any part of it or the fact of its distribution form the basis of, or be relied on in connection with, any contract or investment decision.

The distribution of this Release in other jurisdictions outside Australia may also be restricted by law and any restrictions should be observed. Any failure to comply with such restrictions may constitute a violation of applicable securities laws.

Past performance information given in this Release is given for illustrative purposes only and should not be relied upon as (and is not) an indication of future performance.

Forward Looking Statements

Forward-looking statements are based on current expectations and beliefs and, by their nature, are subject to a number of known and unknown risks and uncertainties that could cause the actual results, performances and achievements to differ materially from any expected future results, performances or achievements expressed or implied by such forward-looking statements, including but not limited to, the risk of further changes in government regulations, policies or legislation; the risks associated with the continued implementation of the merger between the Company and Galaxy Resources Ltd, risks that further funding may be required, but unavailable, for the ongoing development of the Company's projects; fluctuations or decreases in commodity prices; uncertainty in the estimation, economic viability, recoverability and processing of mineral resources; risks associated with development of the Company Projects; unexpected capital or operating cost increases; uncertainty of meeting anticipated program milestones at the Company's Projects; risks associated with investment in publicly listed companies, such as the Company; and risks associated with general economic conditions.

Subject to any continuing obligation under applicable law or relevant listing rules of the ASX, the Company disclaims any obligation or undertaking to disseminate any updates or revisions to any forward-looking statements in this Release to reflect any change in expectations in relation to any forward-looking statements or any change in events, conditions or circumstances on which any such statements are based. Nothing in this Release shall under any circumstances (including by reason of this Release remaining available and not being superseded or replaced by any other Release or publication with respect to the subject matter of this Release), create an implication that there has been no change in the affairs of the Company since the date of this Release.

Competent Person Statement

The information in this announcement that relates to Exploration Results and Mineral Resources is based on information compiled by Albert Thamm, B.Sc. (Hons)., M.Sc. F.Aus.IMM (203217), a Competent Person who is a Fellow of The Australasian Institute of Mining and Metallurgy. Albert Thamm is a full-time employee of Galaxy Resources Pty. Limited. Albert Thamm has sufficient experience that is relevant to the style of mineralization and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Albert Thamm consents to the inclusion in this announcement of the matters based on his information in the form and context in which it appears.

The information in this announcement that relates to the 31 March 2023 Mt Cattlin Ore Reserve is based on information compiled by Daniel Donald, B. Eng. (Mining), F.Aus.IMM (210032), a Competent Person who is a Member of the Australasian Institute of Mining and Metallurgy. Daniel Donald is an employee working for Entech Mining Pty Ltd and has been engaged by Allkem Limited to prepare the documentation for the Mt Cattlin operation on which the Ore Reserve Report is based, for the period ended 31 March 2023, and has sufficient experience that is relevant to the style of mineralization and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Daniel Donald consents to the inclusion in this announcement of the matters based on his information in the form and context in which it appears.

Technical information relating to the Company's Mt Cattlin project contained in this release is derived from, and in some instances is an extract from, the technical report entitled "Mt Cattlin Ore Reserve Estimate, March 31, 2023" (Technical Report) which has been reviewed and approved by Albert Thamm, F.Aus.IMM (who is an employee of Galaxy Resources Pty. Ltd) as it relates to geology, drilling, sampling, exploration, QA/QC and mineral resources and Daniel Donald F.Aus.IMM (an employee of Entech Pty Ltd) as it relates to mining methods, Ore Reserves, site infrastructure, capital cost, operating cost estimates, , mining cost, financial modelling and economic analysis in accordance with National Instrument 43-101 – Standards for Disclosure for Mineral Projects. The Technical Report will be filed within 45 days of this release and will be available for review under the Company's profile on SEDAR at www.sedar.com.

Not for release or distribution in the United States

This announcement has been prepared for publication in Australia and may not be released to U.S. wire services or distributed in the United States. This announcement does not constitute an offer to sell, or a solicitation of an offer to buy, securities in the United States or any other jurisdiction, and neither this announcement or anything attached to this announcement shall form the basis of any contract or commitment. Any securities described in this announcement have not been, and will not be, registered under the U.S. Securities Act of 1933 and may not be offered or sold in the United States except in transactions registered under the U.S. Securities Act of 1933 or exempt from, or not subject to, the registration of the U.S. Securities Act of 1933 and applicable U.S. state securities laws.


APPENDIX 1 – JORC 2012 TABLE 1 DISCLOSURE

Section 1: Sampling Techniques and Data

MT CATTLIN LITHIUM PROJECT SAMPLING AND DATA
Sampling techniques Nature and quality of sampling (e.g. cut channels, random chips, or specific specialized industry standard measurement tools appropriate to the minerals under investigation, such as down hole gamma sondes, or handheld XRF instruments, etc.). These examples should not be taken as limiting the broad meaning of sampling.
Include reference to measures taken to ensure sample representivity and the appropriate calibration of any measurement tools or systems used.
Aspects of the determination of mineralization that are Material to the Public Report.
In cases where ‘industry standard' work has been done this would be relatively simple (e.g. ‘reverse circulation drilling was used to obtain 1 m samples from which 3 kg was pulverized to produce a 30 g charge for fire assay'). In other cases more explanation may be required, such as where there is coarse gold that has inherent sampling problems. Unusual commodities or mineralization types (e.g. submarine nodules) may warrant disclosure of detailed information.
Pre-2017
Mt Catlin mineralization was sampled using a mixture of Diamond (DD) Reverse Circulation drill holes (RC), rotary Air Blast (RAB) and Open Hole (OH). In the north zone drilling is a 40mE x 40mN spacing and infilled to 20mE to 25mE x 20mN to 20mN in the central zone. In the south the drilling is on a 40mE x 80mN pattern. Drill holes were drilled vertical to intersect true thickness of the spodumene mineralization.

A total of 39 DD holes for 1,528.56m, 986 RC holes for 48,763m,59 OH holes for 1,999m and 23 RAB for 402m had been completed before 2017.

The drill-hole collars were surveyed by professional survey contractors. A total of 71 drill holes were surveyed by Surtron Technologies Australia of Welshpool in 2010. Sampling was carried out under Galaxy Resources QAQC protocols and as per industry best practice.

RC sample returns were closely monitored, managed and recorded. Drill samples were logged for lithology and SG measurements. Diamond HQ and PQ core was quarter-cored to sample lengths relating to the geological boundaries, but not exceeding 1m on average. RC samples were composited from 1m drill samples split using a two-stage riffle splitter 25/75 to obtain 2kg to 4kg of sample for sample preparation. All samples were dried, crushed, pulverized and split to produce a 3.5kg and then 200g sub-sample for analysis For Li (method AAS40Q), for Ta, Nb and Sn (method XRF78O) and in some cases for SiO2, Al2O3, CaO, Cr2O3, Fe2O3, K2O3, MgO, MnO, P2O5, SO3, TiO2 and V2O5 were analysed by XRF78O. Entire drill-hole lengths were submitted for assay.

Drilling 2017-8
From 1m of drilling and sampling, two 12.5% splits are taken by a static cone splitter in calico drawstring bags. This obtains two 2kg to 4kg samples with one being retained as an archive sample and the other submitted for assay, where required an archive bag is used as the duplicate sample.

A 4.5-inch diameter rod string is used and the cyclone is cleaned at the end of every 6m rod as caking occurs from the mandatory use of dust suppression equipment.

Drilling November 2018 – 2021
Subsequent to 2018 update, 5,912m (41 holes) of new reverse circulation (RC) and 273.65m of diamond tails (2 holes)  has been completed (excluding metallurgical and geotechnical) has taken place.

From 1m of drilling and sampling, two 12.5% splits are taken by a static cone splitter in calico drawstring bags. This obtains two 2kg to 4kg samples with one being retained as an archive sample and the other submitted for assay, where required an archive bag is used as the duplicate sample.

A 4.5-inch diameter rod string is used and the cyclone is cleaned at the end of every 6m rod as caking occurs from the mandatory use of dust suppression equipment.

2022 Drilling
The current drillhole dataset for the project contains 3,232 drillholes, for 175,950 metres, comprised of a combination of reverse circulation (RC), diamond drilling (DD), and RC with a diamond tail (RC_DDT) drillholes.

The dominant drillhole type is RC, with over 95% of the metres being from RC drillholes.

Hole_Type Count Metres % Drillholes % Metres
DDH 45 5,437.8 1.4% 3.1%
RC 3,173 169,037.8 98.2% 96.1%
RC_DDT 14 1,474.4 0.4% 0.8%
TOTAL 3,232 175,950 100% 100%
Drilling techniques Drill type (e.g. core, reverse circulation, open-hole hammer, rotary air blast, auger, Bangka, sonic, etc.) and details (e.g. core diameter, triple or standard tube, depth of diamond tails, face-sampling bit or other type, whether core is oriented and if so, by what method, etc.). RC drilling hammer diameter was generally 4 & 5/8 inches in early exploration, from 2009 and 2010 the bit diameter was 5 ¼ inches.

RC 2017 -2020
5.25-inch face sampling hammer, reverse circulation, truck mounted or tracked drilling rigs, Three Rivers Drilling, Castle Drilling.

Diamond core is generally RC from surface, and either PQ size tails in weathered rock and narrowed to HQ in fresh rock (standard tubing). Core was not oriented as the disseminated and weathered nature of the mineralization does not warrant or allow it. Diamond core is typically for metallurgical test-work.  Pre-collars drilled short of mineralisation.

RC 2021 A 5.25-inch face sampling hammer, used in reverse circulation. ASX (Australian Surface Exploration) drillers used for RC (including pre-collars).

Diamond 2021 :
Wizard Drilling utilised for diamond drilling from surface. HQ size Metallurgical and geotechnical diamond drilling (standard tubing). Two Metallurgical holes were diamond tails from approximately 70m to 80m. Four Geotechnical holes were diamond from surface and two tails from 50-60m depth.

RC 2022
PXD drilling was utilised for RC drilling from surface.  HQ size Metallurgical and geotechnical diamond drilling (standard tubing) by Orlando Drilling. Four Metallurgical holes were and three Geotechnical holes were diamond drilled from surface and two diamond tails from 150-160m depth.

Logging Whether core and chip samples have been geologically and geotechnically logged to a level of detail to support appropriate Mineral Resource estimation, mining studies and metallurgical studies.
Whether logging is qualitative or quantitative in nature. Core (or costean, channel, etc.) photography.
The total length and percentage of the relevant intersections logged.
All DD, RC and OH (PC) and RAB intervals were geologically logged (where applicable); RQD (DD only), interval weights, recovery, lithology, mineralogy and weathering were recorded in the database.

The DD core was oriented using the Ezy-Mark tool and after 2019 using the Reflex ACT electronic orientation tool.
Geological logging was qualitative.

Recording of interval weights, recovery and RQD was quantitative.
All DD core was photographed and representative 1m samples of RC and OH (PC) chips were collected in chip trays for future reference and photographed. All drill holes were logged in full.

2017-2023 logging
All drill holes are logged and validated via LogChief/ Maxwells Geosciences/DataShed systems.
Assays, standards and control limits are monitored after loading of each batch and reports supplied on demand.  All drill holes are logged in full.  Different Lithium bearing mineral species are logged in detail.

Sub- sampling techniques and sample preparation If core, whether cut or sawn and whether quarter, half or all core taken.
If non-core, whether riffled, tube sampled, rotary split, etc. and whether sampled wet or dry.
For all sample types, the nature, quality and appropriateness of the sample preparation technique.
Quality control procedures adopted for all sub-sampling stages to maximise representivity of samples.
Measures taken to ensure that the sampling is representative of the in situ material collected, including for instance results for field duplicate/second-half sampling.
Whether sample sizes are appropriate to the grain size of the material being sampled.
Pre-2016 sampling
All fresh rock DD core was quarter-cored using a stand mounted brick saw. Soft, weathered DD core was also sampled quarter-core, using a knife and scoop where applicable and practical.
RC samples were collected using a two stage riffle splitter. All samples were dry or dried prior to riffle-splitting.

All 2kg 1m drill samples were sent to SGS, dried, crushed, pulverized and split to approximately -75µ to produce a sample less than 3.5kg sub-sample for analysis.

Sampling was carried out under Galaxy Resources QAQC protocols and as per industry best practice.

Duplicate, blank and standard reference samples were inserted into the sample stream at random, but averaging no less than 1 blank and standard in every 25 samples.

Samples were selected periodically and screened to ensure pulps are pulverized to the required specifications.

Duplicate quarter-core samples were taken from DD core at random for testing averaging one in every 25 samples.

Duplicate riffle-split RC samples were taken at random, but averaging one every approximately 25 samples.

The sample sizes are appropriate to the style, thickness and consistency of the mineralization at Mt Catlin.

Drilling 2016 (SGS)
Core was halved by saw and sample lengths typically 0.5m in length. Sample preparation involved crushing followed by splitting of sample if sample greater than 3 kg using a riffle splitter (SPL26), Dry sample, crush to 6mm, pulverise to 75µm (PRP88) in a LM5 Mill.

Drilling 2017-2021
Diamond drilling was typically sawn half core with whole core used for metallurgical test work.

Intertek (2017-8)
Samples are sorted and weighed. Samples >3kg are riffle split and milled in LM5 to obtain 85% passing 75 Microns. A 400g pulp is taken and a nominal 0.25g sub-sample is fused with sodium peroxide.

Nagrom:  2018-2021
RC chips are dried to 105C°, crushed to nominal top-size of 2 mm in a Terminator Jaw crusher using method CRU01. Pulverised up to 3 kg in a LM5 pulveriser mill at 80% or better passing 75µm, using method PUL01.  If the sample is greater than 3 kg, the sample is dried, and split with rotary splitter before analysis, Diamond core is dried, crushed in a Terminator Jaw crusher to top size 6.3 mm, and pulverised in a LM5 mill up to 2.5 kg using method CRU01.  If the sample is greater than 2.5 kg, the sample is riffle split after drying to reduce the sample size.

Intertek 2022-3
Samples are sorted and weighed. Samples >3kg are riffle split and milled in LM5 to obtain 85% passing 75 Microns. A 400g pulp is taken and a nominal 0.25g sub-sample is assayed by Sodium peroxide fusion in a Ni crucible / MS, OES method FP6-Li/OM19.

Quality of assay data and laboratory tests The nature, quality and appropriateness of the assaying and laboratory procedures used and whether the technique is considered partial or total.

For geophysical tools, spectrometers, handheld XRF instruments, etc., the parameters used in determining the analysis including instrument make and model, reading times, calibrations factors applied and their derivation, etc.
Nature of quality control procedures adopted (e.g. standards, blanks, duplicates, external laboratory checks) and whether acceptable levels of accuracy (i.e. lack of bias) and precision have been established.
Pre-2016 QAQC
All samples were dried, crushed, pulverized and split to produce a 3.5kg and then 200g sub-sample for analysis For Li (method AS40Q), for Ta, Nb and Sn (method XRF78O) and in some cases for SiO2, Al2O3, CaO, Cr2O3, Fe2O3, K2O3, MgO, MnO, P2O5, SO3, TiO2 and V2O5 were analysed by XRF78O. This process involves fusing the sample in a platinum crucible using lithium metaborate/tetraborate flux. For Cs, Rb, Ga, Be and Nb from time to time analysis was by IMS40Q – DIG40Q to ICPMS end.

Duplicate, blank and certified reference samples were inserted into the sample stream at random, but averaging one every ~25 samples. Galaxy Resources utilized certified Lithium standards produced in China and one from SGS in Australia, STD-TAN1.

Inter-laboratory checking of analytical outcomes was routinely undertaken to ensure continued accuracy and precision by the preferred laboratory.
Samples were selected periodically and screened by the laboratory to ensure pulps are pulverized to the required specifications. All QAQC data is stored in the Mt Catlin database and regular studies were undertaken to ensure sample analysis was kept within acceptable levels of accuracy; the studies confirmed that accuracy and precision are within industry standard accepted limits.

Umpire analysis performed on pulps at Genalysis and Ultratrace Perth

2016-QAQC
In 2016 Perth SGS were used for a small 6 hole diamond program by General Mining. Samples were digested using a sodium peroxide fusion digest, method DIG90Q and the resultant solution from the digest was then presented to an ICP-MS for the quantification of Li2O, using method IMS40Q. The majority of standards submitted performed within expected ranges with a positive bias observed for two standards.

2017 - 2021  QAQC
Samples (including QA/QC samples) were processed by Intertek PLC, Perth laboratory in 2017 and 2018, by utilised method FP1 digest (Peroxide Fusion – complete), MS analytical finish, 22 elements, Li2O detection limit 0.03% Ta2O5 detection limit, 0.2 ppm. Monthly review of QA/QC, which includes blanks, field duplicates, high grade standards and CRM (certified reference materials) and SRM (standard reference materials). FS_ICPMS is a Laboratory Method FP1/MS (mass spectrometry) used to analyse for Cs, Nb, Rb, Ta,Th, and U . FS/ICPES (inductively coupled plasma emission spectroscopy) is Laboratory method FP1/OE used to analyse Al, Fe, K, Li, and Si. Reports include calculated values of oxides for all elements.

RC samples and diamond (including QA/QC samples) have been processed by Nagrom Perth, Perth Western Australia. Methods utilised from Lithium and Tantalum are ICP004 and ICP005 (Peroxide Fusion – complete). ICP005 utilises tungsten carbide bowl to reduce iron contamination at exploration and resource development stages (detection limit of 10ppm and 1ppm for Li2O and Ta respectively) Monthly review of QA/QC, which includes blanks, field duplicates, high grade standards and CRM (certified reference materials) and SRM (standard reference materials). All sampling has rigorous QAQC in terms of reference sampling as well as blank and standards introduced into the sample steam.
Duplicate field samples show some evidence of high nugget effect. Typically, duplicate pairs plot within acceptable limits. Field duplicates have been submitted at a rate of 1 per 20.5 samples.

Standards used are ASM0343, ASM0340 AMIS0339, OREAS147, OREAS148 and OREAS149.

Standards reported only one result outside three standard deviations from 533 assays for Lithium. The majority of Tantalum standards reported within three standard deviations.

Coarse blanks have shown no evidence of systematic contamination from 2016-2021 with results consistently low.

QAQC in 2022-3 is broadly in line with the processes above, assays are by Intertek, Perth and Kalgoorlie.

Standards used are OREAS 147, AMIS0341, OREAS 751, OREAS 753, OREAS 148, AMIS0341, AMIS0341, and OREAS 147 to support Sodium peroxide fusion in Ni crucible assay method MS, OES FP6-Li/OM19. This method provides near complete recovery for most samples.

Ore grade standards e.g. Oreas 751 reported only four results outside 2 standard deviations from assays for Lithia. The majority of Tantalum standards reported within 2 standard deviations.

A figure accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/a0a96d56-0609-4c98-a4b7-54a5abe86952

The data is moderately precise.

Verification of sampling and assaying The verification of significant intersections by either independent or alternative company personnel.

The use of twinned holes.

Documentation of primary data, data entry procedures, data verification, data storage (physical and electronic) protocols.

Discuss any adjustment to assay data.
Pre-2018 Verification
An external geological consultant and staff have visually assessed and verified significant intersections of core and RC and PC chips.
Several core holes were compared to neighbouring RC and PC drill holes.

The geological logging of the DD holes supports the interpreted geological and mineralization domains.

Studies on assays results from twinned holes showed a close correlation of geology and assays.

Primary data is recorded by hand in the field and entered Excel spread sheets with in-built validation settings and look-up codes.
Scans of field data sheets and digital data entry spread sheets are handled on site at Mt Cattlin.
Data collection and entry procedures are documented, and training given to all staff.

QAQC checks of assays had identified several standards out of control, these were subsequently reviewed and results rectified.

No clear and consistent biases were defined by Galaxy during the further investigations into QAQC performances although deviations were noted by Galaxy.

2017-8 Verification
CP independently verified drilling, sampling, assay and results from validated, externally maintained and stored database.
No adjustments to assay data other than conversion from Li to Li20 and Ta to Ta2O5.

2018 - 2022 Verification
The CP independently verified drilling, sampling, assay and results from validated, externally maintained and stored database.
No adjustments to assay data other than conversion from Li to Li20 and Ta to Ta2O5.

Primary data capture by Maxwell LogChief and management by Maxwell DataShed.  Assay data loaded directly from Laboratory supplied .csv files as are downhole and collar surveys.

An independent data verification was completed as part of a 2021 Ni-43-101 filing by then competent person.

Data exported from SQL database and verified by the CP.

No adjustments are made to assay data.


Section 2: Reporting of Exploration Results

Criteria JORC Code explanation Commentary
Mineral tenement and land tenure statu s
  • Type, reference name/number, location and ownership including agreements or material issues with third parties such as joint ventures, partnerships, overriding royalties, native title interests, historical sites, wilderness or national park and environmental settings.
  • The security of the tenure held at the time of reporting along with any known impediments to obtaining a license to operate in the area.
Mining Lease M74/244 was amalgamated and awarded on 04/08/2009 and is valid until 23/12/2030 and covers 1830 Ha.

The project is subject to normal projects approvals processes as regulated by the WA Department of Mines, Industry and Regulation.

The tenement is subject to the Standard Noongar Heritage agreement as executed 7 February 2018.

The underlying land is a mixture of freehold property and vacant Crown land. The property Freehold title is held by Galaxy Resources or its child subsidiaries.
Exploration done by other parties
  • Acknowledgment and appraisal of exploration by other parties.
During the 1960's WMC carried out an extensive drilling program to define the extent of local spodumene bearing pegmatite. The WMC work led onto a further investigation into project feasibility.

In 1989 Pancontinental Mining, Limited drilled 101 RC drill holes. In 1990 Pancontinental drilled a further 21 RC drill holes.

In 1997 Greenstone Resources drilled 3 diamond holes and 38 RC holes, undertook soil sampling and metallurgical test work on bulk samples from the mine area.

Haddington Resources Ltd in 2001 drilled 9 diamond holes for metallurgical test work and undertook further sterilization drilling.

Galaxy acquired the M72/12 mining tenement from the Sons of Gwalia administrators in 2006.

Geology
  • Deposit type, geological setting and style of mineralization.
The Mount Catlin Project lies within the Ravensthorpe Suite, with host rocks comprising both the Annabelle Volcanics to the west, and the Manyutup Tonalite to the east. The contact between these rock types extends through the Project area.

The Annabelle Volcanics at Mt Cattlin consist of intermediate to mafic volcanic rocks, comprising both pyroclastic material and lavas.

The pegmatites which comprise the orebodies occurs as a series of sub- horizontal sills, hosted by both volcanic and intrusive rocks, interpreted as a series of westward verging thrusts. Typical coarse grained spodumene (grey green colour) from the NW pegmatite shown below.

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/f75c30db-a3c7-4a94-b77e-7e2fe8863892  

Drill hole Information
  • A summary of all information material to the understanding of the exploration results including a tabulation of the following information for all Material drill holes:
    • easting and northing of the drill hole collar
    • elevation or RL (Reduced Level – elevation above sea level in meters) of the drill hole collar
    • dip and azimuth of the hole
    • down hole length and interception depth
    • hole length.
Pre-2017 drilling reported 4 August 2015 by subsidiary GMM (ASX:GMM). Last prior resource and update was 28 November 2018

2019-2022 drill collars
New resource development collar information is presented in Appendices below.

Holes generally inclined between -75 to -80 degrees to determine true width or due to local infrastructure.
Data aggregation methods
  • In reporting Exploration Results, weighting averaging techniques, maximum and/or minimum grade truncations (e.g. cutting of high grades) and cut-off grades are usually Material and should be stated.
  • Where aggregate intercepts incorporate short lengths of high grade results and longer lengths of low grade results, the procedure used for such aggregation should be stated and some typical examples of such aggregations should be shown in detail.
  • The assumptions used for any reporting of metal equivalent values should be clearly stated.
Pre-2017 Data
Where higher grade zones internal to broader intervals of lower grade mineralization were reported, these were noted as included intervals and italicized.

2019-2022 Drilling
New results are reported to a 0.3% cut-of grade (below), minimum 4m width, maximum 1m internal dilution.  Only drillholes incorporated into the resource model are reported.

No metal equivalent values are used.

Relationship between mineralization widths and intercept lengths
  • These relationships are particularly important in the reporting of Exploration Results.
  • If the geometry of the mineralization with respect to the drill hole angle is known, its nature should be reported.
  • If it is not known and only the down hole lengths are reported, there should be a clear statement to this effect (eg ‘down hole length, true width not known').
All intersection grades have been reported previously as length weighted average grades using a 0.3% Li2O lower grade cut-off except where stated.

Intersections were calculated allowing a maximum of 2m of internal dilution with no top-cut applied. Cutting of high grades is not required due to nature of the mineralization and grade distribution/estimation.

The Mt Cattlin lithium and tantalum mineralization occurs as a thick horizontal to gently dipping pegmatite and generally lies 30 to 280m below the current topographic surface resulting in drill intercepts nearing true widths.

All reported intersections in 2023 are approximate true widths.
Diagrams
  • Appropriate maps and sections (with scales) and tabulations of intercepts should be included for any significant discovery being reported These should include, but not be limited to a plan view of drill hole collar locations and appropriate sectional views.
Diagrams are included in the text above.

Balanced reporting
  • Where comprehensive reporting of all Exploration Results is not practicable, representative reporting of both low and high grades and/or widths should be practiced to avoid misleading reporting of Exploration Results.
All significant intersections above 0.3% Li2O have been fully reported in previous releases.

2019-2022 Drilling
Drill hole collars and relevant assay details are appended below.

Other substantive exploration data
  • Other exploration data, if meaningful and material, should be reported including (but not limited to): geological observations; geophysical survey results; geochemical survey results; bulk sample– size and method of treatment; metallurgical test results; bulk density, groundwater, geotechnical and rock characteristics; potential deleterious or contaminating substances.
Fe2O3 is modelled with Li and Ta to determine the effect of deleterious chemistry and mineralogy at or near pegmatite contacts and rafts of surrounding country rock with pegmatite.
Further work
  • The nature and scale of planned further work (eg tests for lateral extensions or depth extensions or large-scale step-out drilling).
  • Diagrams clearly highlighting the areas of possible extensions, including the main geological interpretations and future drilling areas, provided this information is not commercially sensitive.
Development and extraction of the NW Pit Mineral Resource and Reserve.

Diagrams are illustrated in the text above.

Feasibility study work to trade off open pit vs underground options has commenced.


Section 3: Estimation and Reporting of Mineral Resources – Mt Cattlin

Criteria JORC Code explanation Commentary
Database integrity
  • Measures taken to ensure that data has not been corrupted by, for example, transcription or keying errors, between its initial collection and its use for Mineral Resource estimation purposes.
  • Data validation procedures used.
Pre-2017
At the time of the 2012 Mineral Resource estimates, Allkem had appointed a data administrator to manage and host the Mt Catlin database in a GBIS SQL database.

Field data was entered into project-specific password-protected spread sheets with in-built auto-validation settings. The spread sheets were emailed to head office on a weekly basis and then passed on to the data administrator, where all data was subject to validation procedures and checks before being imported into the central database. Invalid data was not imported into the central database but was quarantined until corrected. Data exports were routinely sent from head office to site for visual validation using ArcGIS and Micromine.

2017 to Jan 2019
Database and data QAQC processes was re-established after review in 2016. The Datashed database was managed/maintained by Maxwell Geoservices and was validated externally to GXY and aggregated meta-data from site and the sample laboratory. The assay laboratory reported sample validation and checks on arrival. Database managers' reported both QAQC and validation checks monthly and upon request.

Jan 2019 to Current
Allkem have employed a Database Administrator who loads all data, manages the database and performs routine validations on all loaded data.

All logging is undertaken on a Toughbook using the dedicated LogChief logging system matched to the Datashed database.

Visual validation of drilling data versus the wireframes in Surpac software is undertaken routinely by Mine Geology and Exploration personnel.

Site visits
  • Comment on any site visits undertaken by the Competent Person and the outcome of those visits.
  • If no site visits have been undertaken indicate why this is the case.
The reporting CP has completed several site visits since 2016.

Geological interpretation
  • Confidence in (or conversely, the uncertainty of) the geological interpretation of the mineral deposit.
  • Nature of the data used and of any assumptions made.
  • The effect, if any, of alternative interpretations on Mineral Resource estimation.
  • The use of geology in guiding and controlling Mineral Resource estimation.
  • The factors affecting continuity both of grade and geology.
The geological interpretation is considered robust due to the nature of the geology and mineralisation.

Surface diamond and reverse circulation (RC) drillholes have been logged for lithology, structure, and alteration and mineralisation data.

The lithological logging of pegmatite in combination with the Li 2 O, Fe 2 O 3 and MgO assays, including grain size and mineralogical differentiation, have been used to guide the sectional interpretation of the pegmatites in Leapfrog Geo modelling software.

The geological wireframes have then been used as a boundary within which internal, mineralisation wireframes have been generated in Leapfrog software using geology logging and assay data. The primary assumption is that the mineralisation is hosted within the fine-grained material within the pegmatite sills, which is considered robust.

Weathering surfaces have been updated by Allkem Resources in Leapfrog Geo software for recently completed drillholes.

Due to the consistent nature of the pegmatite identified in the area, no alternative interpretations have been considered. The pegmatites are found to be continuous over the area of the deposit.

The Li 2 O% mineralisation interpretations are contained wholly within the pegmatite geological units. Evidence of late-stage faulting is present and has, where appropriate, been incorporated into the geological model.

Dimensions
  • The extent and variability of the Mineral Resource expressed as length (along strike or otherwise), plan width, and depth below surface to the upper and lower limits of the Mineral Resource
The Mt Cattlin pegmatites strike north-south and are typically between 10 m and 30 m wide and are typically flat-lying or with a subtle dip east of around 5 to 10 degrees. Several different pegmatites have been identified, either as separate intrusions or due to fault offsets, over a strike length of 1,300 m, an across strike extent of 1,700 m and down to a depth of greater than 300 m below surface.

Thirteen pegmatites have been identified to date in the NW and SW area. They range in extent from 50 m along strike and 50 m down-dip to 650 m along-strike and 500 m down-dip. The pegmatites range in thickness from a few metres to 20 m.

Estimation and modelling techniques
  • The nature and appropriateness of the estimation technique(s) applied and key assumptions, including treatment of extreme grade values, domaining, interpolation parameters and maximum distance of extrapolation from data points. If a computer assisted estimation method was chosen include a description of computer software and parameters used.
  • The availability of check estimates, previous estimates and/or mine production records and whether the Mineral Resource estimate takes appropriate account of such data.
  • The assumptions made regarding recovery of by-products.
  • Estimation of deleterious elements or other non-grade variables of economic significance (e.g. sulphur for acid mine drainage characterisation).
  • In the case of block model interpolation, the block size in relation to the average sample spacing and the search employed.
  • Any assumptions behind modelling of selective mining units.
  • Any assumptions about correlation between variables
  • Description of how the geological interpretation was used to control the resource estimates.
  • Discussion of basis for using or not using grade cutting or capping.
  • The process of validation, the checking process used, the comparison of model data to drillhole data, and use of reconciliation data if available.
Grade estimation for Li 2 O%, Fe 2 O 3 % and Ta 2 O 5 ppm has been completed using Ordinary Kriging (OK) into pegmatite domains using Datamine, Studio RM software. Grade estimation of Fe 2 O 3 % has been completed using OK into the encapsulating mafic waste and late-stage mafic dyke, which intersects the pegmatites.

The geological, mineralisation and weathering wireframes generated have been used to define the domain codes by concatenating the three codes into one. The drillholes have been flagged with the domain code and composited using the domain code to segregate the data. Hard boundaries have been used at all domain boundaries for the grade estimation Pegmatite waste wireframing using
Compositing has been undertaken within domain boundaries at 1m with a merge tolerance of 0.1 m.

Top cuts for all elements have been assessed for all mineralised and un-mineralised pegmatite domains, as well as for the external waste and mafic dyke domains, with only those domains with extreme values having been top cut. The top cut levels have been determined using a combination of histograms, log probability and mean-variance plots. Two domains have been top cut for Li 2 O. Three domains have been top-cut for or Ta 2 O 5 ppm and no top-cutting completed in Fe 2 O 3 %.

Variography has been completed in Supervisor 8.14 software on an individual domain basis. Domains with too few samples have borrowed variography.

No assumptions have been made regarding the recovery of any by-products.

The drillhole data spacing ranges from 40 m by 40 m resource definition drillhole spacing out to an 80 m by 80 m exploration spacing.

The block model parent block size is 20 m (X) by 20 m (Y) by 5 m (Z), which is considered appropriate for the dominant drillhole spacing used to define the deposit. A sub-block size of 2.5 m (X) by 2.5 m (Y) by 0.625 m (Z) has been used to define the mineralisation edges, with the estimation undertaken at the parent block scale .
  • Pass 1 estimations have been undertaken using a minimum of 7 and a maximum of 27 samples into a search ellipse set at approximately half of the variogram range. A 4 sample per drillhole limit has been applied in all pegmatite domains.
  • Pass 2 estimations have been undertaken using a minimum of 7 and a maximum of 27 samples into a search ellipse set at approximately the variogram range. A 4 sample per drillhole limit has been applied in all pegmatite domains.
  • Pass 3 estimations have been undertaken using a minimum of 2 and a maximum of 24 samples into a search ellipse set at four times the Search 2 range.
The Mineral Resource estimate has been validated using visual validation tools combined with volume comparisons with the input wireframes, mean grade comparisons between the block model and composite grade means and swath plots comparing the composite grades and block model grades by Northing, Easting and RL.

Mining reconciliation data for the NW and SW regions is available.

No selective mining units are assumed in this estimate.

No correlation between variables has been assumed.

Moisture
  • Whether the tonnages are estimated on a dry basis or with natural moisture, and the method of determination of the moisture content.
Tonnes have been estimated on a dry basis.

Cut-off parameters
  • The basis of the adopted cut-off grade(s) or quality parameters applied
For the reporting of the Mineral Resource Estimate, a 0.4 Li2O% cut-off within a USD 1,100 Whittle pit shell has been used.

Mining factors or assumptions
  • Assumptions made regarding possible mining methods, minimum mining dimensions and internal (or, if applicable, external) mining dilution. It is always necessary as part of the process of determining reasonable prospects for eventual economic extraction to consider potential mining methods, but the assumptions made regarding mining methods and parameters when estimating Mineral Resources may not always be rigorous. Where this is the case, this should be reported with an explanation of the basis of the mining assumptions made.
A Whittle pit optimisation has been run at 1,100 USD in order to generate a pit shell wireframe for Mineral Resource reporting purposes and to meet the RPEEE reporting requirement.

The mining assumptions/parameters applied to the optimisation are:
  • Mining Recovery – 93%
  • Mining Dilution – 17%
  • Li2O% Price/tonne 6% concentrate – USD$1,100
  • Li2O% recovery – 75%
  • Ta2O5ppm Price/pound concentrate – USD$40
  • Ta2O5ppm recovery – 25%
  • Transport and port Cost/tonne – AUD$49.68
  • State Royalty – 5%
  • Processing Cost/tonne – AUD$33.16
  • Mining Cost/tonne – AUD$4.29
USD exchange rate of 0.70 Li 2 O cut-off of 0.4% has been applied in the Whittle optimisation.

Both Inferred and Indicated Mineral Resource classifications have been utilised in the RPEEE optimisation.

Metallurgical factors or assumptions
  • The basis for assumptions or predictions regarding metallurgical amenability. It is always necessary as part of the process of determining reasonable prospects for eventual economic extraction to consider potential metallurgical methods, but the assumptions regarding metallurgical treatment processes and parameters made when reporting Mineral Resources may not always be rigorous. Where this is the case, this should be reported with an explanation of the basis of the metallurgical assumptions made.
A Li2O% metallurgical recovery of 75% and Ta2O5 ppm recovery of 25% has been applied during the pit optimisation and generation of the RPEEE pit shell.

Environmental factors or assumptions
  • Assumptions made regarding possible waste and process residue disposal options. It is always necessary as part of the process of determining reasonable prospects for eventual economic extraction to consider the potential environmental impacts of the mining and processing operation. While at this stage the determination of potential environmental impacts, particularly for a greenfields project, may not always be well advanced, the status of early consideration of these potential environmental impacts should be reported. Where these aspects have not been considered this should be reported with an explanation of the environmental assumptions made
No environmental factors or assumptions have been incorporated into this Mineral Resource Estimate since Mt Cattlin is a producing operation with Environmental approvals and an Environmental Management Plan in place.

Bulk density
  • Whether assumed or determined. If assumed, the basis for the assumptions. If determined, the method used, whether wet or dry, the frequency of the measurements, the nature, size and representativeness of the samples.
  • The bulk density for bulk material must have been measured by methods that adequately account for void spaces (vugs, porosity, etc), moisture and differences between rock and alteration zones within the deposit,
  • Discuss assumptions for bulk density estimates used in the evaluation process of the different materials.

No additional bulk density data has been collected in the NW Area. As a consequence, the bulk density values determined in the previous MRE (Nov 2018) have been assigned to the block model.

The bulk densities which have been assigned to the Mineral Resource block model by lithology and weathering state are:

Waste Lithologies Oxide 2.50
Transitional 2.70
Fresh 2.86
Unmineralized Oxide 2.42
Pegmatite Transitional 2.62
Fresh 2.78
Mineralised Pegmatite Oxide 2.47
Transitional 2.71
Fresh 2.72
Classification
  • The basis for the classification of the Mineral Resources into varying confidence categories
  • Whether appropriate account has been taken of all relevant factors (i.e. relative confidence in tonnage/grade estimations, reliability of input data, confidence in continuity of geology and metal values, quality, quantity and distribution of the data).
  • Whether the result appropriately reflects the Competent Person's view of the deposit.
The resource classification has been applied to the MRE based on the drilling data spacing, grade and geological continuity, quality of the estimation and data integrity.

The classification takes into account the relative contributions of geological and data quality and confidence, as well as grade confidence and continuity.

Portions of the deposit which have been estimated in the first two estimation passes and which have been estimated with a high degree of confidence, with defined grade continuity, have been classified as Indicated Mineral Resources.

Portions of the deposit that have been estimated and have a suitable level of drilling to assume geological continuity of the pegmatite have been classified as Inferred Mineral Resources.

The classification reflects the view of the Competent Person.

Audits or reviews
  • The results of any audits or reviews of Mineral Resource estimates.
This 2023 Mineral Resource estimate for Mt Cattlin has been peer reviewed and validated. Original outputs in Datamine/Studio have been translated into Dassault/Surpac for further development into regularised models for the development of diluted models.

Discussion of relative accuracy/

confidence
  • Where appropriate a statement of the relative accuracy and confidence level in the Mineral Resource estimate using an approach or procedure deemed appropriate by the Competent Person. For example, the application of statistical or geostatistical procedures to quantify the relative accuracy of the resource within stated confidence limits, or, if such an approach is not deemed appropriate, a qualitative discussion of the factors that could affect the relative accuracy and confidence of the estimate
  • The statement should specify whether it relates to global or local estimates, and, if local, state the relevant tonnages, which should be relevant to technical and economic evaluation. Documentation should include assumptions made and the procedures used
  • These statements of relative accuracy and confidence of the estimate should be compared with production data, where available
The relative accuracy of the Mineral Resource estimate is reflected in the reporting of the Mineral Resource as per the guidelines of the 2012 JORC Code.

The remaining Measured, Indicated, and Inferred material from the NW and SW region have been considered in the mineral resource.

The estimate is domained by identified pegmatite number and zoned by mineralised and un-mineralised subtypes using 0.3% lithia and Na2O
Estimates are thus local by domain.

The same geological model and wireframes are used for grade control and mine planning in Dassault/Surpac Software.

Regularized translations of the original Datamine Studio model are used in Dassault/Surpac re-blocked to 5 x 5 x 6.25m for short term mine planning and monthly reconciliations.

Reconciliation is within tolerance for an "Indicated" resource.


Section 4: Ore Reserves

Criteria JORC Code explanation Commentary
Mineral Resource estimate for conversion to Ore Reserves

Description of the Mineral Resource estimate used as a basis for the conversion to an Ore Reserve. The Mineral Resource estimate (MRE) used was prepared by Mining Plus Pty Ltd under the direction of Allkem and classified in accordance with the JORC 2012 guidelines. The MRE was natively prepared in Datamine software with a record date of 31 December 2022, and a summary was released to the ASX on 17 April 2023.
The MRE was transformed into a diluted, regularised, mining model inclusive of mining recovery, by Orelogy Mine Consulting.
Reconciliation between the two models was considered acceptable, and the inbuilt dilution and mining recovery reflect the historical values of 17% dilution and 94% mining recovery which were derived from site model to process plant reconciliations.

Clear statement as to whether the Mineral Resources are reported additional to, or inclusive of, the Ore Reserves.

The Mineral Resources are reported inclusive of the Ore Reserves.

Site visits Comment on any site visits undertaken by the Competent Person and the outcome of those visits.
If no site visits have been undertaken indicate why this is the case.

The Competent Person has undertaken a site visit within the current reporting period.

Study status The type and level of study undertaken to enable Mineral Resources to be converted to Ore Reserves.
The Code requires that a study to at least Pre-Feasibility Study level has been undertaken to convert Mineral Resources to Ore Reserves. Such studies will have been carried out and will have determined a mine plan that is technically achievable and economically viable, and that material Modifying Factors have been considered.

Mt Cattlin is a mature operating mine and a Feasibility Study (FS) investigating the continuation of current operations is the basis of the conversion of the MRE to an ORE.
The FS has addressed all material Modifying Factors required for the conversion of Mineral Resources to Ore Reserves and has shown that the mine plan is technically achievable and economically viable. Where possible and appropriate, the FS has used parameters in line with the current operations.

Cut-off parameters The basis of the cut-off grade(s) or quality parameters applied. A cut-off grade of 0.4% Li2O has been used for reporting the ORE (as was used in the underlying MRE).
The economic cut-off grade calculation is approximately 0.2% Li2O, but the more conservative cut-off grade was adopted based on historical operating experience as an approximation of the practical process plant recovery constraint.

Mining factors or assumptions















The method and assumptions used as reported in the Pre-Feasibility or Feasibility Study to convert the Mineral Resource to an Ore Reserve (i.e., either by application of appropriate factors by optimisation or by preliminary or detailed design). An optimisation of the MRE was undertaken with General Mine Planning (GMP) software, both Geovia and Datamine products. Comparisons between the outputs showed them to be materially equivalent.
The addition to the specific modifying factors described in the sub-sections below, the optimisation data inventory and input parameters included:
  • Regularised mining model created from the MRE that included dilution and mining recovery
  • Surveyed surface topography provided from Mt Cattlin as at 31/03/23
  • Contract mining costs from a competitive tender process
  • Closure costs from the site Mine Closure Plan cost estimate
  • Spodumene concentrate (SC5.2) revenue price of US$1,500/t inclusive of shipping and marketing costs
  • Tantalite concentrate revenue from current sales contract
  • State Government and third-party royalties
  • Processing, General & Administration, concentrate surface haulage, and port costs from current site budgets and forecasts (based on actual data)
  • Net Present Value (NPV) discounting rate of 10%
Where supplied by Allkem, these input parameters were reviewed by Entech and considered appropriate for the current spodumene concentrate market.
The staged pit design and schedule is considered suitable for Ore Reserve estimation.

The choice, nature and appropriateness of the selected mining method(s) and other mining parameters including associated design issues such as pre-strip, access, etc. The ORE includes the Stage 4 North-West (NW) pit which is a down dip extension of the current Stage 3 NW pit i.e., deepening of current floor, and cutting back of the current pit rim.
The mining methodology is a continuation of the conventional hard rock open cut practices of the current operations with continuous drill, blast and excavate cycles (with ore grade control as required).
The existing operations provide access to the operations of the ORE.

The assumptions made regarding geotechnical parameters (e.g., pit slopes, stope sizes, etc), grade control and pre-production drilling. A comprehensive geotechnical study appropriate for an FS level was undertaken by Entech to determine the pit design parameters used in the ORE. Three dedicated geotechnical diamond drill holes, totalling 651 m, located in the vicinity of the final pit walls were drilled, logged, sampled and laboratory tested to collect detailed geotechnical data. In addition, photogrammetric modelling of the current pit walls, structure digitisation, in-pit mapping and data from previous studies was utilised to characterise the rock mass and provide input data for stability analysis that were used to derive the recommended design parameters.
97% of the rock within the pit containing the ORE is competent fresh (unweathered) material, and key design parameters derived for fresh rock were:
  • 20 m bench height
  • 70 o bench face angle
  • 8.5 m wide spill berm
  • 52 o inter-ramp angle
  • 12 m wide geotechnical berm every approx. 100 m of high wall face
Pit designs were reviewed by Entech's Principal Geotechnical Engineer to ensure compliance with geotechnical intent.
In conjunction with the Mineral Resource and grade control predictive computerised block models, established site grade control procedure utilises visual inspection of blast hole cuttings and pit-floor visual geological control when mining ore ("ore spotting"). The combination of techniques enables identification and segregation of barren pegmatite or pegmatite containing fine grained spodumene, from pegmatite containing coarse grained spodumene (ore). Specific grade control drilling campaigns (RC technique) are used in areas of higher structural or mineralogical uncertainty.
Mt Cattlin is an operating mine with current production and excavation knowledge. The resource drilling that defines the Stage 4 expansion is +95% Reverse Circulation (RC), and predominantly spaced at 40 m x 40 m.

The major assumptions made, and Mineral Resource model used for pit and stope optimisation (if appropriate). The underlying Mineral Resource model was jointly developed by independent consultant Mining Plus Pty Ltd and Allkem Ltd (see ASX release 17 April 2023).  A dilution study was then carried out by consultant Orelogy Mine Consulting (Orelogy) to determine the appropriate methodology to create a diluted, regularised Mining Model that could be readily used in GMP software. The key steps and outcomes from the dilution study and modifications to create the Mining Model were:
  • Regularising the block size into Selective Mining Unit (SMU) dimensions of 5.0 m x 5.0 m x 2.5 m (East, North, Elevation).
  • The SMU size was selected based on the size of the equipment, the parent and sub cell block sizes in the resource model and matched the existing mining bench height to the vertical dimensions of the block.
  • The ore blocks were flagged as either "Clean" (uncontaminated with mining dilution) or "Contaminated" (contaminated with basalt country rock and requiring beneficiation by optical sorting prior to being processed) ore types depending upon the proportion of clean ore within the SMU block.
  • The overall model reports 82% of the ore to the Clean category and 18% to the Contaminated category.
The mining dilution factors used. No external dilution factors have been applied. The Mining Model described above compared to the source undiluted model has a back-calculated dilution of 16%.

The mining recovery factors used. No external mining recovery factors have been applied. The Mining Model described above compared to the source undiluted model has a back-calculated ore loss of 5.7%.

Any minimum mining widths used. A minimum mining width of 40 m has been applied in the pit designs.

The manner in which Inferred Mineral Resources are utilised in mining studies and the sensitivity of the outcome to their inclusion. Inferred Mineral Resources comprise 12% of the MRE and were used to inform the optimisation.
The designed pit inventory has 0.5% of Inferred Mineral Resource which has been treated as waste for the economic assessment. The design of the pit is not sensitive to the inclusion, or not, of Inferred Mineral Resource.

The infrastructure requirements of the selected mining methods. The ORE as an extension of current operations, and the current site infrastructure is suitable for proposed mining methods.

Metallurgical factors or assumptions









The metallurgical process proposed and the appropriateness of that process to the style of mineralisation. Ore is processed through the existing crushing, screening, ore sorting, and heavy media separation (HMS) plant with a nominal and permitted capacity of 1.8 million tonnes (Mt) per annum. The Mt Cattlin plant has been in operation for over a decade and is suitable for this style of mineralisation.

Whether the metallurgical process is well-tested technology or novel in nature. The Mt Cattlin plant is comprised of well tested technology and suited to the production of saleable spodumene concentrate.
Several ancillary circuits have been added over the life of the plant including optical ore sorters and fines recovery to incrementally enhance project economics. All the processing technology has been in use in this or other configurations for numerous to many years and are not regarded as novel.

The nature, amount and representativeness of metallurgical test work undertaken, the nature of the metallurgical domaining applied and the corresponding metallurgical recovery factors applied. As an operating processing facility, the Mt Cattlin plant has amassed significant knowledge and expertise in the treatment of the Mt Cattlin ores.
Fine grained spodumene recovers poorly in the Mt Cattlin processing plant. The underlying MRE model has explicitly domained the fine-grained material and excluded it from the new in-situ MRE inventory.
Confirmatory metallurgical test work on ore in the Stage 4 extension is in progress.
A regression formula developed from historical operating performance that uses head grade to predict plant recovery, for a given grade of concentrate, is in daily use at Mt Cattlin. The Feasibility Study has used this algorithm to calculate metallurgical recovery in the economic analysis.

Any assumptions or allowances made for deleterious elements. Allowances have been made for iron oxide (Fe2O) content of the spodumene concentrate. The (potential) penalty element is estimated in the MRE, reported in the ORE, monitored during processing, and quantified in the final spodumene concentrate product. Revenue pricing used in the cashflow model incorporates likely penalty charges.

The existence of any bulk sample or pilot scale test work and the degree to which such samples are considered representative of the orebody as a whole. The ORE is a continuation of the ore zones that have been successfully mined and processed at Mt Cattlin. Bulk samples and/or pilot scale testing is not required due to the demonstrated process flowsheet performance.

For minerals that are defined by a specification, has the ore reserve estimation been based on the appropriate mineralogy to meet the specifications? The Ore Reserves have been based on lithia (Li2O), Tantalite (Ta2O5), and iron oxide (Fe2O) grade ranges that are acceptable to existing sales contracts and readily saleable into the international market.

Environmental The status of studies of potential environmental impacts of the mining and processing operation. Details of waste rock characterisation and the consideration of potential sites, status of design options considered and, where applicable, the status of approvals for process residue storage and waste dumps should be reported. The Mt Cattlin mine site is an operating and mature operation with well-understood impacts and established environmental management systems and capability. The site operating procedures are consistent with the principles of ISO 14001:2015 Environmental Management Systems.
Key potential risk areas include noise, vibration and air emissions/quality are regulated, and have specific management plans to ensure compliance.
Waste rock and processing tails stored on site are classified as Non-Acid Forming (NAF) and chemically benign. The waste rock is predominantly unweathered (fresh), competent, basalt and andesites which form stable and erosion resistant landforms. Mt Cattlin pegmatite tailings are a coarse, sandy, material that drains readily and exhibits excellent stability on placement. The Heavy Media Separation process used to produce spodumene concentrate does not introduce chemicals into the tailings stream.
A 2023 Mining Proposal for pit and waste dump expansion required for part of this ORE has been submitted to the WA regulator, with approval expected in the third quarter of 2023. Further approvals will be required during the life of this ORE, potentially including pit and waste dumping area increases and a new In-Pit Tailings Storage Facility.
There is no reason to expect that all required approvals cannot be gained in sufficient time to allow the exploitation of this ORE as planned.

Infrastructure The existence of appropriate infrastructure: availability of land for plant development, power, water, transportation (particularly for bulk commodities), labour, accommodation; or the ease with which the infrastructure can be provided, or accessed. The Mt Cattlin mine site is a mature operating mine. All mining, processing, power and water supplies, road and port infrastructure are in place and operational.
Accommodation is based near site for a mixed commute and residential workforce. The operation has access to a nearby regional bituminised airstrip capable of landing 100-seat jets. Sealed roads link the site to Perth, and major regional towns.

Costs











The derivation of, or assumptions made, regarding projected capital costs in the study. The FS has assessed and included appropriate capital costs. As an existing operation the capital required for the operating life of the ORE is not significant.

The methodology used to estimate operating costs. The operating costs have been derived two sources:
  • contract mining costs - competitive market tender
  • all other operating costs - from analysis of the site FY24 forecast (which is derived from actual historical costs and existing contracts)
Allowances made for the content of deleterious elements. The revenue prices used in the economic analysis have incorporated all applicable penalty charges as modelled, including deductions for product grade less than the benchmark 6.0% spodumene grade (SC6), and for any iron oxide content above limits.
The charges are not material in the overall pricing.

The source of exchange rates used in the study. The exchange rate of consequence is Australian to United States of America (USD:AUD) currency exchange rate as spodumene product is sold in US dollars (USD). As an existing Western Australian based operation, most costs are in denominated in AUD.
A flat 0.70 USD:AUD exchange rate was used in the cashflow modelling that was provided by Allkem.

Derivation of transportation charges. Product transportation and handling charges (road haulage from Mt Cattlin to Esperance port, and Esperance port costs) were provided by Allkem and were derived from existing contracts.
The product revenue price used was discounted to be net of sea freight.

The basis for forecasting or source of treatment and refining charges, penalties for failure to meet specification, etc. The headline external pricing forecasts for spodumene concentrate grading 6.0 % Li 2 O were discounted for expected product grades of between 5.2% Li 2 O and 5.5% Li 2 O. The discounts were derived from existing contract penalty charges. Penalties were also applied to Fe2O3 exceedances if they occurred.

The allowances made for royalties payable, both Government and private. Selling costs have allowed for a 5.0% ad-valorum Western Australian state royalty and $1.50/t of ore processed third party royalty.

Revenue factors

The derivation of, or assumptions made regarding revenue factors including head grade, metal or commodity price(s) exchange rates, transportation and treatment charges, penalties, net smelter returns, etc. The ORE head grade is reported by the GMP software interrogating the diluted mining model within the designed pit. Normal good practice checks have been made in this process, as well as reporting through alternative GMP software, and comparing to similar internal work by Allkem.
The spodumene concentrate commodity price used in the cashflow model is based on pricing by an external independent market forecaster , with appropriate modifications for Mt Cattlin product specification. Allowances have been made for surface and sea freight charges based on current site budgets and forecasts. The realised price (i.e., FOB; net of charges) forecast over the likely period the product from this ORE will be sold into market has an average of A$2,978/dmt and a median of A$2,963/dmt.
Minor revenue is derived from the sale of a by-product Tantalite concentrate and the sale price used is based on current contracts which average approximately A$35/ dry lb.

Transport charges are derived from existing contracts, and likewise penalty charges are taken from existing sales contracts.

The derivation of assumptions made of metal or commodity price(s), for the principal metals, minerals and co-products. As described above, the commodity price assumptions have been taken from independent market analysts and existing contracts and are deemed appropriate.

Market assessment





The demand, supply and stock situation for the particular commodity, consumption trends and factors likely to affect supply and demand into the future. An Independent market researcher (commercial in confidence) forecasts for demand, supply, and stock levels during the likely market window of the product of this ORE have been used to characterise the international market for spodumene concentrate.
The demand for spodumene concentrate is primarily driven by automotive batteries, and the underlying strong global growth in electric vehicles. From extreme deficit in supply over the past two years that has seen steep price growth and incentive for new supply, it is forecast that the overall market is moving into surplus, with intermediate fluctuations, until the end of the decade, from where it will again retreat into deficit.
The accuracy of these forecasts will be dominated by the accuracy of the assumptions quantifying the rate of growth in mine supply, and the rate of growth of EV sales.

A customer and competitor analysis along with the identification of likely market windows for the product. The Mt Cattlin spodumene concentrate is currently sold through offtake agreements mainly to mainland Chinese convertors. Offtake agreements have pricing conditions reflecting spodumene market prices.
During the market window applicable to this ORE, the Mt Cattlin product moves from being fully contracted, to a mix of contract and spot market exposure, to fully available for spot pricing. This mix of contract vs. spot markets exposure is subject to continuous review and adjustment.
Significant global supply chain diversification is underway which is seeing new lithium processing plants being developed in countries other than China, adding diversification to the potential customer base.

Price and volume forecasts and the basis for these forecasts. Overall market supply and demand, along with customer and competitor factors have been considered in the compiling of the pricing forecast applicable to this ORE.
The optimisation price selected of US$1,500/t of spodumene concentrate was conservatively lower than the average pricing forecast of the likely market window. The cashflow model pricing used was based on the current forecasts for the likely market window, modified for the specification of the Mt Cattlin product, as discussed above in the Revenue Factors section. It is assumed that all product produced is sold into existing contracts and spot markets.

For industrial minerals the customer specification, testing and acceptance requirements prior to a supply contract. Mt Cattlin concentrates are sold into typical international specifications, the more relevant specifications being Li 2 O grade, Ta 2 O 5 grade (both revenue factors), and Fe 2 O 3 grade (a potential penalty factor). Mt Cattlin product does not typically attract Fe penalties, and the lithia grade is forecast to range between 5.5% Li 2 O and 5.2% Li 2 O depending on market assessment.
Customer specification and acceptance of the product rely on a typical process of samples taken by an independent agency and conformance of the assays obtained by both the seller and buyer to an allowable range of variance.

Economic

The inputs to the economic analysis to produce the net present value (NPV) in the study, the source and confidence of these economic inputs including estimated inflation, discount rate, etc. The cashflow model is uninflated and applies a 10% discount rate to calculate the project NPV, which was robustly positive.
Mining costs were derived by a competitive market tender process based on a designed and scheduled pit, and existing site infrastructure. Processing, General & Administration, product haulage, port, and shipping costs reflect corporate forecasts based on historical site actual data modified for Allkem's view on FY24 market conditions.
As an ongoing operation, capital costs were relatively minor but included an allowance for developing a new In-Pit Tailings Storage Facility (IPTSF) during the life of mine, buffering land purchases, as well as ongoing sustaining capital. An end of mine allowance of $17.5 M has been incorporated into the economic analysis.
The overall cost base assumptions and analysis methodology are considered appropriate, robust and at FS level of accuracy.

NPV ranges and sensitivity to variations in the significant assumptions and inputs. The cashflow model has been tested for sensitivity to key economic assumptions. As is typically found, the revenue assumptions (e.g., sale price, USD:AUD exchange rate, head grade, plant recovery) have a much greater influence than cost assumptions (e.g., operating costs, capital costs). At 20% individual variances to any of these variables the project remains robustly economic over life of mine and generates positive cashflows.
Stripping Ratio is generally a proxy for risk, and the individual stages of the overall project (as currently evaluated) have quite different stripping ratios than the overall project average. The NPV sensitivity to key variables is therefore significantly different if analysed by stage. If the most sensitive stage (Stage 4-1) is assessed by the most influential variable (Revenue) at the most negative value (-20%), the cashflow is weakly positive whilst the NPV falls to zero. The following stage (Stage 4-2) and the sum of the two stages (Stage 4-1 + Stage 4-2) remain with strongly positive cashflows and NPV's when Revenue is tested at -20%.

Social The status of agreements with key stakeholders and matters leading to social licence to operate. As an operating site Mt Cattlin has a well-established and implemented Environmental Management Plan and suite of operating procedures consistent with the principles of ISO 14001:2015 Environmental Management Systems and includes, but is not limited to:
  • Environmental Policy
  • Requirements of approvals, permits and licences
  • Environmental responsibilities of site personnel
  • Site induction programmes
  • Environmental monitoring and reporting requirements
  • Inspection and audit process
  • Non-conformance, corrective action, and risk management of incidents
  • Preparation of procedures and work instructions addressing identified elements such as dewatering, saline spillage, waste management and bioremediation
  • Stakeholder consultation, including:
  • Regular update meetings with Shire of Ravensthorpe and Ravensthorpe Business Association
  • Ongoing consultation with local neighbours
  • Ongoing consultation with Traditional Owner groups and presentations at the Southwest Aboriginal Land and Sea Council working party meetings
  • Appointment of an Environmental and Community Liaison Officer
  • Biannual presentations to the Ravensthorpe community
  • Establishment of the Mt Cattlin Community Consultation Group in 2018 with members consisting of respected leaders of the community and Mt Cattlin senior management. Minutes of meetings and presentations are made publicly available via https://www.mtcattlin.com.au/ccg/
Allkem have advised the Competent Person that there are no current issues that would be expected to endanger the ‘social licence to operate'.

Other





To the extent relevant, the impact of the following on the project and/or on the estimation and classification of the Ore Reserves: Commentary below.

Any identified material naturally occurring risks. The FS has investigated the potential for flooding via a hydrology study which informed the design of the abandonment bund and the Cattlin Creek diversion channel and associated bunding. No residual issues were apparent.
The TSF design has included analysis of performance under seismic conditions, which was found to be acceptable.
The life of the ORE at less than five years is considered too short to be meaningful affected by longer term climate change. Short term variability in the form of floods or droughts is unlikely to materially affect the operation.
The site continued operating through the recent global pandemic.

The status of material legal agreements and marketing arrangements. All material legal and marketing agreements are in place and accounted for.

The status of governmental agreements and approvals critical to the viability of the project, such as mineral tenement status, and government and statutory approvals. There must be reasonable grounds to expect that all necessary Government approvals will be received within the timeframes anticipated in the Pre-Feasibility or Feasibility study. Highlight and discuss the materiality of any unresolved matter that is dependent on a third party on which extraction of the reserve is contingent. The ORE stated are located on active mining leases, in good standing.
All required permits for the current Stage 3 works, which represents approximately 40% of this ORE, are approved and are in place.
A Mining Proposal that describes the first phase of the Stage 4 expansion has been submitted to the WA Regulator for approval, which is expected in August 2023. In addition to the usual technical and regulatory compliance assessment that defines Mining Proposal assessment, a tenement status conversion from an Exploration Licence (E) to a General Purpose Licence (G) is required to enable waste dumping as a permitted activity, and the Mining Proposal to be subsequently approved. The E is held by Allkem and is in good standing, and the conversion to a G is expected to happen in May 2023 as per standard procedure in the timeframe estimated for overall Mining Proposal approval.
Post receipt of the Mining Proposal approval described above, subsequent permitting applications will then be made for the second phase of the Stage 4 expansion, including the next In-Pit Tailings Storage Facility (IPTSF). The second phase approvals are expected to be gained by the end of the first quarter of 2024, allowing sufficient time, including contingency, before the planned works are required to commence.

Classification



The basis for the classification of the Ore Reserves into varying confidence categories. The Mineral Resources above an in-situ economic cut-off grade within the designed open pit and below the surveyed topography surfaces (as of 31 March 2023) have been modified by the application of suitable modifying factors and has been classified Probable, based on the Measured or Indicated classification of the Mineral Resource estimate.
The surface stockpiles are classified as Probable Ore Reserves to simplify reporting. Some stocks such as ROM ore would normally qualify as Proved, but the downgrading is not material to the ORE.
The level of work undertaken through the FS is considered sufficient for the classification of Proved and Probable Ore Reserves.

Whether the result appropriately reflects the Competent Person's view of the deposit. Mr. Daniel Donald, the Competent Person for this Ore Reserve estimation, has reviewed the work undertaken to date and considers that it is sufficiently detailed and relevant to allow declaration of these Ore Reserves.

The proportion of Probable Ore Reserves that have been derived from Measured Mineral Resources (if any). As described above, all surface stocks have been classified as Probable when it may have been possible to classify some as Proved. Any potential upgrading would have no material effect on the ORE.

Audits or reviews The results of any audits or reviews of Ore Reserve estimates. The Ore Reserve has been estimated by independent consultants Entech Pty Ltd with assistance from Allkem and Strategic Metallurgy with the MRE, mining model, and processing areas respectively.
Entech have undertaken internal peer review during the process.

Discussion of relative accuracy/ confidence





Where appropriate a statement of the relative accuracy and confidence level in the Ore Reserve estimate using an approach or procedure deemed appropriate by the Competent Person. For example, the application of statistical or geostatistical procedures to quantify the relative accuracy of the reserve within stated confidence limits, or, if such an approach is not deemed appropriate, a qualitative discussion of the factors which could affect the relative accuracy and confidence of the estimate. The Competent Person deems that the methodology applied to arrive at the Ore Reserve estimate for Mt Cattlin is appropriate and defendable.
The overall accuracy of the cost estimate used in the ORE is considered to be ±15%. The cost estimates have been derived from competitive market tender for mining costs, and actual site operating data for processing and General and Administration (G&A) costs, so the global accuracy is considered robust.
The current South-East In-Pit Tailings Storage Facility (SE IPTSF) capacity will be reached by the second-half 2024, and deposition will switch to the nearby NE IPTSF, which will have capacity for the remainder of the life of mine. The detailed design, costing and permitting of the NE IPTSF has not yet been finalised. Whilst the NE IPTSF capital expenditure (capex) is immaterial in the overall project cashflow, the estimation has been conservatively calculated and is at a PFS, rather than FS-level of accuracy. There is no reason to expect that permitting approvals will not be gained for the proposed NE IPTSF when applied for.
The Probable ore stockpiles include 900 kt @ 0.8% Li 2 O of tailings from early project life that are planned to retreated at mine closure. The economic analysis test has used conservative metal recovery (30%) and product grade specifications (4.5% Li 2 O) indicated from metallurgical test work to date. Test work is continuing and flowsheet development is also underway but currently the level of accuracy is PFS rather than FS. The contribution of the tailings retreatment at mine closure is not considered material to the overall project.

The statement should specify whether it relates to global or local estimates, and, if local, state the relevant tonnages, which should be relevant to technical and economic evaluation. Documentation should include assumptions made and the procedures used. The statement relates to global estimates of a mine scale.

Accuracy and confidence discussions should extend to specific discussions of any applied Modifying Factors that may have a material impact on Ore Reserve viability, or for which there are remaining areas of uncertainty at the current study stage. Confidence in the application of the modifying factors is appropriate for the estimate.

Historically disproportionate amounts of fine-grained ore in the ROM feed negatively affected plant recovery in the second half of 2022. This has since been identified in the Mineral Resource and domained out of the new MRE which underpins this ORE.

It is recognised that this may not be possible or appropriate in all circumstances. These statements of relative accuracy and confidence of the estimate should be compared with production data, where available. The contract mining cost data which was derived from competitive market tender has also been compared to actual site production data. All other operating cost data is directly derived from actual production data. In summary, the cost data used compares very well with production data and incorporates the inflationary/pandemic effects seen over the previous several years.
Processing plant throughput and recovery data has been derived directly from production data, and therefore compare very well.
The mining model used to evaluate the ORE incorporates regularised blocks at SMU size, and mining dilution and mining recovery derived from actual production data and plant reconciliations. This new mining model has only been used in three month-end reconciliation at this point in time. The new model is expected to continue to reconcile well due to the technical improvements described above.


Figures accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/8a13271b-078c-478d-a772-11aa73e327c7

https://www.globenewswire.com/NewsRoom/AttachmentNg/4939260a-4a8b-4b61-a7dd-ab4cca831445

https://www.globenewswire.com/NewsRoom/AttachmentNg/838ee883-3b4e-4731-a9bd-ef07a92c11be

https://www.globenewswire.com/NewsRoom/AttachmentNg/3470423d-1891-4cec-84d0-e6c9508b8154


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

AKE:CA
The Conversation (0)
First Production Achieved at Olaroz Stage 2

First Production Achieved at Olaroz Stage 2

Allkem Limited (ASX|TSX: AKE, " Allkem " or the " Company ") is pleased to advise that Stage 2 of the Olaroz Lithium Facility has successfully achieved first production, with wet lithium carbonate cake produced at the filter presses.

The Olaroz Stage 2 development has a nameplate capacity of 25,000 tonnes per year (" tpa ") of technical grade lithium carbonate. Olaroz is managed through Sales de Jujuy SA, a joint venture company owned with Toyota Tsusho Corporation (" TTC ") and JEMSE (a Jujuy State company).

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
James Bay Drilling Update - New High Grade Zone Identified in NW

James Bay Drilling Update - New High Grade Zone Identified in NW

Allkem Limited (ASX|TSX: AKE the Company ) is pleased to provide an update on the exploration and resource definition drilling program at its James Bay Project in Québec, Canada.

HIGHLIGHTS

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
March 2023 Quarterly Activities Report

March 2023 Quarterly Activities Report

Allkem Limited (ASX|TSX: " AKE" the " Company" ) provides an update on its global lithium portfolio, business activities and financial position 1 as at 31 March 2023.

HIGHLIGHTS
OPERATIONS

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Mt Cattlin Resource Update with Higher Grade

Mt Cattlin Resource Update with Higher Grade

Allkem Limited (ASX|TSX: AKE, " Allkem " or the " Company ") provides an updated Mineral Resource Estimate (" MRE ") and development drilling update at 31 December 2022 for its Mt Cattlin operation in Western Australia.

HIGHLIGHTS

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
March Quarter Results Briefing

March Quarter Results Briefing

Allkem Limited (ASX|TSX: AKE) ("Allkem" or "the Company") will release its March Quarter Activities Report on Thursday, 20 April 2023.

Managing Director and CEO, Mr. Martín Pérez de Solay and Chief Sales and Marketing Officer, Christian Barbier will conduct a live webcast briefing at 10:00 am AEST (Sydney, Melbourne) on the same day.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Albemarle Reports First Quarter 2024 Results

Albemarle Corporation (NYSE: ALB), a global leader in providing essential elements for mobility, energy, connectivity and health, today announced its results for the first quarter ended March 31, 2024 .

Albemarle Corp. Logo. (PRNewsFoto/Albemarle Corporation)

First-Quarter 2024 and Recent Highlights
(Unless otherwise stated, all percentage changes represent year-over-year comparisons)

  • Net sales of $1.4 billion , driven by Energy Storage volume growth as projects ramp
  • Net income of $2 million , or ($0.08) (a) per diluted share attributable to common shareholders
  • Adjusted diluted EPS attributable to common shareholders of $0.26
  • Adjusted EBITDA (b) of $291 million
  • On track to deliver more than $280 million target in productivity benefits in 2024; in Q1, delivered over $90 million in productivity and restructuring cost savings
  • Conducted successful bidding events for spodumene concentrate and lithium carbonate, designed to promote price transparency and discovery
  • Achieved 50% operating rate milestone at Kemerton I; commissioning at Meishan and ramp of the Salar Yield Improvement Project continue to progress well
  • Reaffirmed FY 2024 corporate outlook considerations, including ranges based on lithium market price scenarios

(a)

After mandatory convertible preferred stock dividends

(b)

Beginning in 2024, Adjusted EBITDA definition includes Albemarle's share of the pre-tax earnings of the Talison joint venture

"In the first quarter, our team demonstrated agility in dynamic market conditions by continuing to deliver solid volumetric growth, ramping new conversion facilities, and executing cost reduction and productivity improvements," said Kent Masters, Albemarle's chairman and CEO. "We have strengthened our competitive position, enhanced our financial flexibility, and started to increase lithium market price transparency. Our actions best position us to serve our core end-markets today and for the future." Masters added, "We remain focused on disciplined capital allocation to deliver profitable organic growth and value for all stakeholders."

2024 Total Corporate Outlook Considerations
The company maintains its prior full-year outlook, which is based on three lithium market price scenarios.


Total Corporate FY 2024E

Including Energy Storage Scenarios

Observed market price case (a)

YE 2023

Q4 2023 average

H2 2023 average

Average lithium market price ($/kg LCE) (a)

~$15

~$20

~$25

Net sales

$5.5 - $6.2 billion

$6.1 - $6.8 billion

$6.9 - $7.6 billion

Adjusted EBITDA (b)(c)

$0.9 - $1.2 billion

$1.6 - $1.8 billion

$2.3 - $2.6 billion



(a)

Price represents blend of relevant Asia and China market indices for the periods referenced.

(b)

The company does not provide a reconciliation of forward-looking non-GAAP financial measures to the most directly comparable financial measures calculated and reported in accordance with GAAP, as the company is unable to estimate significant non-recurring or unusual items without unreasonable effort. See "Additional Information regarding Non-GAAP Measures" for more information.

(c)

Presented under updated adjusted EBITDA definition as of 2024. FY23 adjusted EBITDA under updated definition would be $3.5B. See Non-GAAP Reconciliations for further details.

2024 Other Corporate Outlook Considerations
Following the company's public offering of depository shares representing an interest in its mandatory convertible preferred stock, interest and financing expenses are expected to be at the low end of the previous range of $180 to $220 million . The change in weighted-average common shares outstanding (diluted) reflects the recently issued shares of mandatory convertible preferred stock on an as-converted basis. The change to the adjusted effective tax rate range is related to geographic income mix and is dependent on the assumption of lithium market price. All other corporate outlook considerations are unchanged.


Other Corporate FY 2024E

Capital expenditures

$1.6 - $1.8 billion

Depreciation and amortization

$580 - $660 million

Adjusted effective tax rate

(5%) - 27%

Corporate costs

$120 - $150 million

Interest and financing expenses

$180 - $210 million

Weighted-average common shares outstanding (diluted) (d)

135 - 139 million



(d)

Each quarter, Albemarle will report the more dilutive of either: 1) adding the underlying shares in the mandatory to the share count or 2) reducing Albemarle's net income to common shareholders by the mandatory dividend. The 20-day volume-weighted average common share price will be used in determining the underlying shares to be added to the share count.

First Quarter 2024 Results

In millions, except per share amounts

Q1 2024


Q1 2023


$ Change


% Change

Net sales

$    1,360.7


$    2,580.3


$   (1,219.5)


(47.3) %

Net income attributable to Albemarle Corporation

$           2.4


$    1,238.6


$   (1,236.1)


(99.8) %

Adjusted EBITDA (a)(b)

$       291.2


$    1,761.7


$   (1,470.5)


(83.5) %

Diluted (loss) earnings per share attributable to
common shareholders

$        (0.08)


$       10.51


$      (10.59)


(100.8) %

Non-recurring and other unusual items (a)

0.34


(0.19)





Adjusted diluted earnings per share attributable to
common shareholders
(a)(c)

$         0.26


$       10.32


$      (10.06)


(97.5) %



(a)

See Non-GAAP Reconciliations for further details.

(b)

For comparability, 2023 figures presented under adjusted EBITDA definition that the company adopted beginning in 2024.

(c)

Totals may not add due to rounding.

Net sales for the first quarter of 2024 were $1.4 billion compared to $2.6 billion for the prior-year quarter, a year-over-year decline of 47% that was driven primarily by lower pricing in Energy Storage. Net income attributable to Albemarle of $2 million decreased by $1.2 billion and adjusted EBITDA of $291 million declined by $1.5 billion from the prior-year quarter. The decline in earnings was primarily due to lower lithium market pricing, as well as additional margin compression due to inventory timing and reduced equity earnings at the Talison joint venture, which more than offset favorable volumes.

The effective income tax rate for the first quarter of 2024 was 2.2% compared to 23.9% in the same period of 2023. On an adjusted basis, the effective income tax rates were (12.4)% and 23.6% for the first quarter of 2024 and 2023, respectively, with the decrease primarily due to changes in the geographic income mix.

Energy Storage Results

In millions

Q1 2024


Q1 2023


$ Change


% Change

Net Sales

$           800.9


$        1,943.7


$       (1,142.8)


(58.8) %

Adjusted EBITDA

$           198.0


$        1,567.7


$       (1,369.7)


(87.4) %

Energy Storage net sales for the first quarter of 2024 were $801 million , a decrease of $1.1 billion , or 59%, due to lower pricing (-89%), which more than offset higher volumes (+31%) related to the ramp of lithium projects, including the La Negra III/IV expansion in Chile and the processing plant in Qinzhou, China , and sales of chemical-grade spodumene. Adjusted EBITDA of $198 million decreased $1.4 billion , driven by lower lithium market pricing, as well as margin compression due to inventory timing and reduced equity earnings at the Talison joint venture, which more than offset favorable volumes.

Specialties Results

In millions

Q1 2024


Q1 2023


$ Change


% Change

Net Sales

$           316.1


$           418.8


$          (102.7)


(24.5) %

Adjusted EBITDA

$             45.2


$           162.2


$          (117.0)


(72.1) %

Specialties net sales for the first quarter of 2024 were $316 million , a decrease of $103 million , or 25%, primarily due to lower prices (-19%) and lower volumes (-6%). Adjusted EBITDA of $45 million decreased $117 million . Both volumes and prices were impacted by weaker demand, particularly for consumer electronics.

Ketjen Results

In millions

Q1 2024


Q1 2023


$ Change


% Change

Net Sales

$           243.8


$           217.8


$             26.0


11.9 %

Adjusted EBITDA

$             22.0


$             14.5


$               7.4


51.1 %

Ketjen net sales of $244 million for the first quarter of 2024 were up 12% compared to the previous year due to higher volumes (+10%) and higher prices (+2%), primarily from clean fuel technologies. Adjusted EBITDA of $22 million increased $7 million largely due to higher sales and lower input costs.

Cash Flow and Capital Deployment
Cash from operations of $98 million for the first quarter of 2024 decreased $623 million versus the prior year period. The year-over-year decrease was driven by lower adjusted EBITDA and reduced dividends received from equity investments, partially offset by lower investment in working capital. Capital expenditures of $579 million increased by $164 million versus the prior-year period due to the timing of project spend.

On March 8, 2024 , Albemarle completed a $2.3 billion public mandatory convertible preferred stock offering to fortify the balance sheet, enhance financial flexibility, and fund in-flight growth investments. Albemarle's capital allocation priorities continue to focus on investing in its organic opportunities to drive profitable growth, maintaining its investment grade credit rating, and funding its dividends.

Balance Sheet and Liquidity
As of March 31, 2024 , Albemarle had estimated liquidity of approximately $3.7 billion , including $2.1 billion of cash and equivalents, $1.5 billion available under its revolver and $124 million available under other credit lines. Total debt was $3.5 billion , representing a debt covenant net debt to adjusted EBITDA of approximately 0.9 times.

Earnings Call

Date:

Thursday, May 2, 2024

Time:

9:00 AM Eastern time

Dial-in (U.S.):

1-800-590-8290

Dial-in (International):

1-240-690-8800

Conference ID:

ALBQ1

The company's earnings presentation and supporting material are available on Albemarle's website at https://investors.albemarle.com .

About Albemarle
Albemarle Corporation (NYSE: ALB) leads the world in transforming essential resources into critical ingredients for mobility, energy, connectivity, and health. We partner to pioneer new ways to move, power, connect and protect with people and planet in mind. A reliable and high-quality global supply of lithium and bromine allow us to deliver advanced solutions for our customers. Learn more about how the people of Albemarle are enabling a more resilient world at albemarle.com and on X (formerly Twitter) @AlbemarleCorp.

Albemarle regularly posts information to www.albemarle.com , including notification of events, news, financial performance, investor presentations and webcasts, non-GAAP reconciliations, Securities and Exchange Commission ("SEC") filings and other information regarding the company, its businesses and the markets it serves.

Forward-Looking Statements
This press release contains statements concerning our expectations, anticipations and beliefs regarding the future, which constitute "forward-looking statements" within the meaning of the Private Securities Litigation Reform Act of 1995. These forward-looking statements, which are based on assumptions that we have made as of the date hereof and are subject to known and unknown risks and uncertainties, often contain words such as "anticipate," "believe," "estimate," "expect," "guidance," "intend," "may," "outlook," "scenario," "should," "would," and "will". Forward-looking statements may include statements regarding: our 2024 company and segment outlooks, including expected market pricing of lithium and spodumene and other underlying assumptions and outlook considerations; expected capital expenditure amounts and the corresponding impact on cash flow; market pricing of lithium carbonate equivalent and spodumene; anticipated timing of the commissioning of the Meishan China lithium conversion facility; plans and expectations regarding other projects and activities, cost reductions and accounting charges, and all other information relating to matters that are not historical facts. Factors that could cause Albemarle's actual results to differ materially from the outlook expressed or implied in any forward-looking statement include: changes in economic and business conditions; financial and operating performance of customers; timing and magnitude of customer orders; fluctuations in lithium market prices; production volume shortfalls; increased competition; changes in product demand; availability and cost of raw materials and energy; technological change and development; fluctuations in foreign currencies; changes in laws and government regulation; regulatory actions, proceedings, claims or litigation; cyber-security breaches, terrorist attacks, industrial accidents or natural disasters; political unrest; changes in inflation or interest rates; volatility in the debt and equity markets; acquisition and divestiture transactions; timing and success of projects; performance of Albemarle's partners in joint ventures and other projects; changes in credit ratings; and the other factors detailed from time to time in the reports Albemarle files with the SEC, including those described under "Risk Factors" in Albemarle's most recent Annual Report on Form 10-K and any subsequently filed Quarterly Reports on Form 10-Q, which are filed with the SEC and available on the investor section of Albemarle's website (investors.albemarle.com) and on the SEC's website at www.sec.gov . These forward-looking statements speak only as of the date of this press release. Albemarle assumes no obligation to provide any revisions to any forward-looking statements should circumstances change, except as otherwise required by securities and other applicable laws.

Albemarle Corporation and Subsidiaries

Consolidated Statements of Income

(In Thousands Except Per Share Amounts) (Unaudited)



Three Months Ended


March 31,


2024


2023

Net sales

$ 1,360,736


$ 2,580,252

Cost of goods sold

1,321,798


1,303,712

Gross profit

38,938


1,276,540

Selling, general and administrative expenses

194,912


154,306

Research and development expenses

23,532


20,471

Operating (loss) profit

(179,506)


1,101,763

Interest and financing expenses

(37,969)


(26,777)

Other income, net

49,901


82,492

(Loss) income before income taxes and equity in net income of unconsolidated
investments

(167,574)


1,157,478

Income tax (benefit) expense

(3,721)


276,963

(Loss) income before equity in net income of unconsolidated investments

(163,853)


880,515

Equity in net income of unconsolidated investments (net of tax)

180,500


396,188

Net income

16,647


1,276,703

Net income attributable to noncontrolling interests

(14,199)


(38,123)

Net income attributable to Albemarle Corporation

2,448


1,238,580

Mandatory convertible preferred stock dividends

(11,584)


Net (loss) income attributable to Albemarle Corporation common shareholders

$      (9,136)


$ 1,238,580

Basic (loss) earnings per share attributable to common shareholders

$        (0.08)


$        10.57

Diluted (loss) earnings per share attributable to common shareholders

$        (0.08)


$        10.51





Weighted-average common shares outstanding – basic

117,451


117,232

Weighted-average common shares outstanding – diluted

117,451


117,841

Albemarle Corporation and Subsidiaries

Condensed Consolidated Balance Sheets

(In Thousands) (Unaudited)



March 31,


December 31,


2024


2023

ASSETS




Current assets:




Cash and cash equivalents

$        2,055,813


$           889,900

Trade accounts receivable

874,038


1,213,160

Other accounts receivable

438,507


509,097

Inventories

1,904,827


2,161,287

Other current assets

549,540


443,475

Total current assets

5,822,725


5,216,919

Property, plant and equipment

12,587,763


12,233,757

Less accumulated depreciation and amortization

2,831,728


2,738,553

Net property, plant and equipment

9,756,035


9,495,204

Investments

1,259,001


1,369,855

Other assets

329,283


297,087

Goodwill

1,613,534


1,629,729

Other intangibles, net of amortization

251,755


261,858

Total assets

$      19,032,333


$      18,270,652

LIABILITIES AND EQUITY




Current liabilities:




Accounts payable to third parties

$        1,165,955


$        1,537,859

Accounts payable to related parties

129,613


550,186

Accrued expenses

454,600


544,835

Current portion of long-term debt

5,076


625,761

Dividends payable

58,354


46,666

Income taxes payable

237,098


255,155

Total current liabilities

2,050,696


3,560,462

Long-term debt

3,519,453


3,541,002

Postretirement benefits

26,382


26,247

Pension benefits

145,067


150,312

Other noncurrent liabilities

833,548


769,100

Deferred income taxes

657,468


558,430

Commitments and contingencies




Equity:




Albemarle Corporation shareholders' equity:




Common stock

1,175


1,174

Mandatory convertible preferred stock

2,235,379


Additional paid-in capital

2,962,585


2,952,517

Accumulated other comprehensive loss

(597,205)


(528,526)

Retained earnings

6,930,868


6,987,015

Total Albemarle Corporation shareholders' equity

11,532,802


9,412,180

Noncontrolling interests

266,917


252,919

Total equity

11,799,719


9,665,099

Total liabilities and equity

$      19,032,333


$      18,270,652

Albemarle Corporation and Subsidiaries

Selected Consolidated Cash Flow Data

(In Thousands) (Unaudited)



Three Months Ended

March 31,


2024


2023

Cash and cash equivalents at beginning of year

$     889,900


$   1,499,142

Cash flows from operating activities:




Net income

16,647


1,276,703

Adjustments to reconcile net income to cash flows from operating activities:




Depreciation and amortization

123,751


87,271

Stock-based compensation and other

9,317


10,540

Equity in net income of unconsolidated investments (net of tax)

(180,500)


(396,188)

Dividends received from unconsolidated investments and nonmarketable
securities

50,756


547,552

Pension and postretirement expense

1,273


1,954

Pension and postretirement contributions

(4,824)


(2,825)

Realized loss on investments in marketable securities

33,746


Unrealized loss (gain) on investments in marketable securities

6,737


(45,732)

Deferred income taxes

116,447


14,098

Working capital changes

(52,320)


(764,071)

Other, net

(23,076)


(8,322)

Net cash provided by operating activities

97,954


720,980

Cash flows from investing activities:




Capital expenditures

(579,322)


(415,608)

Sales (purchases) of marketable securities, net

84,893


(122,267)

Investments in equity investments and nonmarketable securities

(74)


(1,133)

Net cash used in investing activities

(494,503)


(539,008)

Cash flows from financing activities:




Proceeds from issuance of mandatory convertible preferred stock

2,236,750


Repayments of long-term debt and credit agreements

(29,019)


Proceeds from borrowings of long-term debt and credit agreements

29,019


Other debt repayments, net

(620,753)


(713)

Dividends paid to shareholders

(46,908)


(46,282)

Dividends paid to noncontrolling interests


(53,145)

Proceeds from exercise of stock options

86


81

Withholding taxes paid on stock-based compensation award distributions

(10,619)


(18,617)

Other

(1,256)


Net cash provided by (used in) financing activities

1,557,300


(118,676)

Net effect of foreign exchange on cash and cash equivalents

5,162


24,296

Increase in cash and cash equivalents

1,165,913


87,592

Cash and cash equivalents at end of period

$   2,055,813


$   1,586,734

Albemarle Corporation and Subsidiaries

Consolidated Summary of Segment Results

(In Thousands) (Unaudited)



Three Months Ended


March 31,


2024


2023

Net sales:




Energy Storage

$   800,898


$ 1,943,682

Specialties

316,065


418,778

Ketjen

243,773


217,792

Total net sales

$ 1,360,736


$ 2,580,252





Adjusted EBITDA:




Energy Storage

$    197,996


$ 1,567,692

Specialties

45,181


162,158

Ketjen

21,979


14,543

Total segment adjusted EBITDA

265,156


1,744,393

Corporate

26,080


17,311

Total adjusted EBITDA

$    291,236


$ 1,761,704

See accompanying non-GAAP reconciliations below.

Additional Information regarding Non-GAAP Measures

It should be noted that adjusted net income attributable to Albemarle Corporation, adjusted net income attributable to Albemarle Corporation common shareholders, adjusted diluted earnings per share attributable to common shareholders, non-operating pension and other post-employment benefit ("OPEB") items per diluted share, non-recurring and other unusual items per diluted share, adjusted effective income tax rates, EBITDA, adjusted EBITDA (on a consolidated basis), EBITDA margin and adjusted EBITDA margin are financial measures that are not required by, or presented in accordance with, accounting principles generally accepted in the United States , or GAAP. These non-GAAP measures should not be considered as alternatives to Net income attributable to Albemarle Corporation ("earnings") or other comparable measures calculated and reported in accordance with GAAP. These measures are presented here to provide additional useful measurements to review the company's operations, provide transparency to investors and enable period-to-period comparability of financial performance. The company's chief operating decision maker uses these measures to assess the ongoing performance of the company and its segments, as well as for business and enterprise planning purposes.

A description of other non-GAAP financial measures that Albemarle uses to evaluate its operations and financial performance, and reconciliation of these non-GAAP financial measures to the most directly comparable financial measures calculated and reported in accordance with GAAP can be found on the following pages of this press release, which is also is available on Albemarle's website at https://investors.albemarle.com . The company does not provide a reconciliation of forward-looking non-GAAP financial measures to the most directly comparable financial measures calculated and reported in accordance with GAAP, as the company is unable to estimate significant non-recurring or unusual items without unreasonable effort. The amounts and timing of these items are uncertain and could be material to the company's results calculated in accordance with GAAP.

ALBEMARLE CORPORATION AND SUBSIDIARIES

Non-GAAP Reconciliations

(Unaudited)

See below for a reconciliation of adjusted net income attributable to Albemarle Corporation, adjusted net income attributable to Albemarle Corporation common shareholders, EBITDA and adjusted EBITDA (on a consolidated basis), which are non-GAAP financial measures, to Net income attributable to Albemarle Corporation ("earnings"), the most directly comparable financial measure calculated and reported in accordance with GAAP. Adjusted net income attributable to Albemarle Corporation common shareholders is defined as net income after mandatory convertible preferred stock dividends, but before the non-recurring, other unusual and non-operating pension and other post-employment benefit (OPEB) items as listed below. The non-recurring and unusual items may include acquisition and integration related costs, gains or losses on sales of businesses, restructuring charges, facility divestiture charges, certain litigation and arbitration costs and charges, and other significant non-recurring items. EBITDA is defined as net income attributable to Albemarle Corporation before interest and financing expenses, income tax expense, and depreciation and amortization. Adjusted EBITDA is defined as EBITDA plus or minus the proportionate share of Windfield Holdings income tax expense, non-recurring, other unusual and non-operating pension and OPEB items as listed below.


Three Months Ended


March 31,


2024


2023

In thousands, except percentages and per share amounts

$


% of
net
sales


$


% of
net
sales

Net income attributable to Albemarle Corporation

$         2,448




$  1,238,580



Add back:








Non-operating pension and OPEB items (net of tax)

(351)




374



Non-recurring and other unusual items (net of tax)

40,044




(22,774)



Adjusted net income attributable to Albemarle Corporation

42,141




1,216,180



Mandatory convertible preferred stock dividends

(11,584)






Adjusted net income attributable to Albemarle Corporation common shareholders

$       30,557




$  1,216,180











Adjusted diluted earnings per share attributable to common shareholders

$           0.26




$         10.32











Adjusted weighted-average common shares outstanding – diluted

117,668




117,841











Net income attributable to Albemarle Corporation

$         2,448


0.2 %


$  1,238,580


48.0 %

Add back:








Interest and financing expenses

37,969


2.8 %


26,777


1.0 %

Income tax (benefit) expense

(3,721)


(0.3) %


276,963


10.7 %

Depreciation and amortization

123,751


9.1 %


87,271


3.4 %

EBITDA

160,447


11.8 %


1,629,591


63.2 %

Proportionate share of Windfield income tax expense

73,689


5.4 %


165,985


6.4 %

Non-operating pension and OPEB items

(325)


— %


601


— %

Non-recurring and other unusual items

57,425


4.2 %


(34,473)


(1.3) %

Adjusted EBITDA

$     291,236


21.4 %


$  1,761,704


68.3 %









Net sales

$  1,360,736




$  2,580,252



Non-operating pension and OPEB items, consisting of mark-to-market actuarial gains/losses, settlements/curtailments, interest cost and expected return on assets, are not allocated to Albemarle's operating segments and are included in the Corporate category. In addition, the company believes that these components of pension cost are mainly driven by market performance, and the company manages these separately from the operational performance of the company's businesses. In accordance with GAAP, these non-operating pension and OPEB items are included in Other income, net. Non-operating pension and OPEB items were as follows (in thousands):


Three Months Ended


March 31,


2024


2023

Interest cost

$       8,505


$       9,010

Expected return on assets

(8,830)


(8,409)

Total

$        (325)


$          601

In addition to the non-operating pension and OPEB items disclosed above, the company has identified certain other items and excluded them from Albemarle's adjusted net income calculation for the periods presented. A listing of these items, as well as a detailed description of each follows below (per diluted share):


Three Months Ended


March 31,


2024


2023

Restructuring and other charges (1)

$         0.23


$            —

Acquisition and integration related costs (2)

0.01


0.03

Loss (gain) in fair value of public equity securities (3)

0.35


(0.29)

Other (4)

(0.15)


0.04

Tax related items (5)

(0.10)


0.03

Total non-recurring and other unusual items

$         0.34


$       (0.19)



(1)

In January 2024, the Company announced it was taking measures to unlock near term cash flow and generate long-term financial flexibility by re-phasing organic growth investments and optimizing its cost structure. As a result, the Company recorded severance costs for employees in Corporate and each of the businesses, and losses related to the cancellation of certain capital expenditure projects. During the three months ended March 31, 2024, $33.5 million of these expenses were recorded in Selling, general and administrative expenses and $2.8 million were recorded in Other income, net ($27.0 million after income taxes, or $0.23 per share). The severance has primarily been paid, with the remainder to be paid in 2024.



(2)

Costs related to the acquisition, integration and divestitures for various significant projects, recorded in Selling, general and administrative expenses for the three months ended March 31, 2024 and 2023 were $1.9 million and $5.1 million ($1.5 million and $4.0 million after income taxes, or $0.01 and $0.03 per share), respectively.



(3)

Loss of $33.7 million and $9.4 million recorded in Other income, net resulting from the sale of investments in public equity securities and the change in fair value of investments in public equity securities, respectively, for the three months ended March 31, 2024 ($41.1 million after income taxes, or $0.35 per share). Gain of $45.8 million ($34.4 million after income taxes, or $0.29 per share) recorded in Other income, net for the three months ended March 31, 2023, resulting from the increase in fair value of investments in public equity securities.



(4)

Other adjustments for the three months ended March 31, 2024 included amounts recorded in:

  • Cost of goods sold - $1.4 million of expenses related to non-routine labor and compensation related costs that are outside normal compensation arrangements.
  • Selling, general and administrative expenses - $0.1 million of expenses related to certain legal costs.
  • Other income, net - $17.3 million gain primarily from the sale of assets at a site not part of our operations, an $8.7 million gain from PIK dividends of preferred equity in a Grace subsidiary and a $2.4 million gain primarily resulting from the adjustment of indemnification related to a previously disposed business, partially offset by $2.9 million of charges for asset retirement obligations at a site not part of our operations.

After income taxes, these net gains totaled $17.3 million, or $0.15 per share.




Other adjustments for the three months ended March 31, 2023 included amounts recorded in:

  • Selling, general and administrative expenses - $1.9 million of charges primarily for environmental reserves at sites not part of our operations and $0.7 million of facility closure expenses related to offices in Germany.
  • Other income, net - $3.6 million of asset retirement obligation charges primarily for a site not part of our operations.

After income taxes, these net charges totaled $4.8 million, or $0.04 per share.



(5)

Included in Income tax benefit for the three months ended March 31, 2024 are discrete net tax benefits of $12.3 million, or $0.10 per share primarily related to the reduction in a foreign tax reserve and excess tax benefits realized from stock-based compensation arrangements.




Included in Income tax expense for the three months ended March 31, 2023 are discrete net tax expenses of $2.9 million, or $0.03 per share primarily related to foreign return to provisions offset by excess tax benefits realized from stock-based compensation arrangements.

See below for a reconciliation of the adjusted effective income tax rate, the non-GAAP financial measure, to the effective income tax rate, the most directly comparable financial measure calculated and reported in accordance with GAAP (in thousands, except percentages).


Income before
income taxes and
equity in net income
of unconsolidated
investments


Income tax expense


Effective income tax
rate

Three months ended March 31, 2024






As reported

$                   (167,574)


$                       (3,721)


2.2 %

Non-recurring, other unusual and non-operating pension and OPEB
items

57,100


17,407



As adjusted

$                   (110,474)


$                      13,686


(12.4) %







Three months ended March 31, 2023






As reported

$                 1,157,478


$                    276,963


23.9 %

Non-recurring, other unusual and non-operating pension and OPEB
items

(33,872)


(11,472)



As adjusted

$                 1,123,606


$                    265,491


23.6 %

As noted above, beginning in 2024, the company changed its definition of adjusted EBITDA for financial accounting purposes. The updated definition includes Albemarle's share of the pre-tax earnings of the Talison joint venture, whereas the prior definition included Albemarle's share of Talison earnings net of tax. See below for a reconciliation of adjusted EBITDA (on a consolidated basis), the non-GAAP financial measure, to Net income attributable to Albemarle Corporation ("earnings"), the most directly comparable financial measure calculated and reported in accordance with GAAP, as if it were presented under the new definition for the year ended December 31, 2023 .

Net income attributable to Albemarle Corporation

$               1,573,476

Depreciation and amortization

429,944

Interest and financing expenses

116,072

Income tax expense

430,277

Proportionate share of Windfield income tax expense

779,703

Gain on sale of business/interest in properties, net

(71,190)

Acquisition and integration related costs

26,767

Goodwill impairment

6,765

Non-operating pension and OPEB items

(7,971)

Mark-to-market gain on public equity securities

44,732

Legal accrual

218,510

Other

(1,097)

Total adjusted EBITDA

$               3,545,988

Contact:
Meredith Bandy 1.980.999.5168

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/albemarle-reports-first-quarter-2024-results-302133681.html

SOURCE Albemarle Corporation

News Provided by PR Newswire via QuoteMedia

Keep reading...Show less
Lithium Universe

Lithium Universe Limited (ASX: LU7) – Reinstatement to Official Quotation

Description

The suspension of trading in the securities of Lithium Universe Limited (‘LU7’) will be lifted immediately, following the release by LU7 of an announcement regarding the finalisation of a capital raising.

Keep reading...Show less
Lithium Universe

LU7 Raises $3.64 Million to Advance Closing the Lithium Conversion Gap Strategy

Lithium Universe Limited (referred to as "Lithium Universe" or the "Company," ASX: "LU7") is pleased to advise that it has completed a $3,644,333.34 million capital raising to sophisticated investors, at a price of $0.02 for each one fully paid ordinary share (FPS) subscribed.

Keep reading...Show less
Balkan Mining and Minerals

March 2024 Quarterly Activities Report

Balkan Mining and Minerals Ltd (ASX: BMM; "BMM" or "the Company") provides the Company’s quarterly activities report for the nine months ended 31 March 2024 (“Quarter”).

Keep reading...Show less
Galan Lithium

Quarterly Activities and Cash Flow Report

The Board of Galan Lithium Limited (Galan or the Company) is pleased to provide this Quarterly Activities Report for the quarter ended 31 March 2024 and to the date of this report. The main focus for the quarter was the ongoing construction works/activities at the Company’s 100% owned, high- grade/low-impurity Hombre Muerto West (HMW) Project in the Catamarca Province, Argentina. Galan continues its steady progress in advancing its low cost, high grade HMW project to production in a timely manner.

Keep reading...Show less
Portofino Grants Stock Options

Portofino Grants Stock Options

Portofino Resources INC. (TSXV: POR) (OTCQB: PFFOF) (FSE: POTA) ("Portofino" or the "Company") announces that, in accordance with the Company's Share Option Plan it has granted options to purchase an aggregate of 360,000 common shares of the Company to certain consultants of the Company. Each Option is exercisable into one Common Share at an exercise price of $0.05. The Options are subject to certain vesting conditions and expire five years from the grant date.

About Portofino Resources Inc.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×