GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 52% complete on 28 February 2022.
Construction milestones achieved during the month include the raise drilling of the first 4.5-meter diameter primary ventilation shaft (80m) and the commencement of the civil works associated with the LNG/Solar power station.
Managing Director, Tony James commented, “It’s a great milestone to go past the 50% mark for the overall construction progress at Abra. Steady progress has been made in the processing plant construction with a total of 766m3 of concrete poured project to date.
Underground development has reached 880m since commencement against a plan of 815m. By the end of February, the decline has reached 1,422mRL which is 128m below the surface and 109m above the orebody. The successful drilling of the first 4.5m primary ventilation shaft also represents a critical reduction in mining risk as the mine will be able to establish the first leg of the ventilation following installation of the primary ventilation fan that was acquired in 2019.”
Click here for the full ASX release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
03 February
Silver Supply Tight, Demand Rising — What's Next? First Majestic's Mani Alkhafaji
Mani Alkhafaji, president of First Majestic Silver (TSX:AG,NYSE:AG), discusses silver supply, demand and price dynamics, as well as how the company is positioning for 2026.He also shares his thoughts on when silver stocks may catch up to the silver price: "You've got to give it a couple of... Keep Reading...
03 February
Rio Silver’s Path to Near-Term Cashflow
Rio Silver (TSXV:RYO,OTCPL:RYOOF) President and CEO Chris Verrico outlines the company’s transition into a pure-play silver developer. With the silver price reaching historic highs, Rio Silver is capitalizing on its strategic position in Peru — the world’s second largest silver producer — to... Keep Reading...
02 February
When Will Silver Stocks Catch Up to the Silver Price?
The silver price remains historically high despite a recent pullback, and many silver stocks haven't kept pace. Silver's strong performance over the past year is the result of a perfect storm of factors, including an entrenched supply deficit, growing industrial demand, a weakening US dollar and... Keep Reading...
02 February
BP Silver Initial Drilling Intersects Significant Mineralization Within Cosuño Lithocap
Hole CO-0001 Returns 29 Meters at 56 g/t Silver & 0.28 g/t Gold (80 g/t AgEq)
BP Silver Corp. (TSXV: BPAG) ("BP Silver" or the "Company") announces assay results ("Assays") from the first two drill holes of its eleven-hole Phase I drill program (the "Program") at the Cosuño Silver Project ("Cosuño") in Bolivia. The Company expects to release assays from the remaining nine... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00