Denison Reports Financial and Operational Results for Q1 2022, including $47.8 million gain on Physical Uranium Holdings

Denison Mines Logo (CNW Group/Denison Mines Corp.)

Denison Mines Corp. ('Denison' or the 'Company') (TSX: DML) (NYSE: DNN) today filed its Condensed Consolidated Financial Statements and Management's Discussion & Analysis ('MD&A') for the quarter ended March 31, 2022 . Both documents will be available on the Company's website at www.denisonmines.com or on SEDAR (at www.sedar.com ) and EDGAR (at www.sec.govedgar.shtml ). The highlights provided below are derived from these documents and should be read in conjunction with them. The Company's results reflect earnings attributable to Denison shareholders of $0.05 per share for the quarter ended March 31, 2022 including mark-to-market gains of $47.8 million on the Company's investment in 2.5 million pounds U 3 O 8 of physical uranium holdings.  All amounts in this release are in Canadian dollars unless otherwise stated. View PDF

David Cates , President and CEO of Denison commented, "Our results from the first quarter of 2022 reflect further improvements in the uranium market, as well as an active start to the year for the Company's Wheeler River and McClean Lake projects.

The spot price of U 3 O 8 increased by nearly 40% during the first quarter, reflecting the relative scarcity of discretionary uranium holdings available to the spot market amidst an environment of significant geopolitical uncertainty, which drove a substantial increase in the value of Denison's physical uranium holdings and the Company's earnings per share of $0.05 . Denison remains committed to holding its physical uranium position for the long-term as both a means to enhance our shareholders' exposure to the uranium market and a tool for the future financing of the development of the Wheeler River project.  At the end of the first quarter, Denison's physical uranium holdings had a market value of approximately $181 million , representing ~60% of Denison's share of the initial capital costs estimated for the Wheeler River project in the Pre-Feasibility Study.

At Wheeler River, we have commenced and made significant progress towards the execution of the first of two planned evaluation field programs in 2022.  Our first field program for the year, involves additional ISR testing and includes the installation of multiple small diameter three-spot test patterns designed to facilitate the collection of information from additional areas of the Phoenix deposit and support the finalization of our plans for the second field program planned for the year – the Feasibility Field Test ('FFT'). The FFT is scheduled for completion by the end of the fourth quarter of 2022 and is intended to support the Feasibility Study for the project by providing further verification of the permeability, leachability and containment parameters needed for the successful application of the ISR mining method at Phoenix .

At our 22.5% owned McClean Lake project, which is a joint venture with French nuclear giant Orano, we achieved a significant milestone with receipt of regulatory approval for the expansion of the McClean Lake Tailings Management Facility ('TMF').  With the TMF expansion approved, the McClean Lake mill is well positioned to remain a strategically significant asset in the Athabasca Basin for many years to come.

Overall, it has been a busy quarter for the Denison team, as we advance several key projects related to Wheeler River and our portfolio of development and exploration projects, during a very dynamic time for the uranium industry.  This work is part of an ambitious plan for 2022, which is expected to involve several potential catalysts and the completion of various key milestones through the end of 2022 and into 2023."

Highlights
  • Commenced the 2022 In Situ Recovery ('ISR') field program at the Phoenix uranium deposit (' Phoenix ')

The Company's ambitious 2022 evaluation plan for the Wheeler River Project ('Wheeler River' or the 'Project') is designed to further de-risk the technical elements of the Phoenix ISR project ahead of the completion of the Feasibility Study ('FS') initiated for the project in late 2021. Key to the 2022 plan is the completion of additional field programs ('2022 Field Program'), including the installation of additional PQ test wells in multiple three-spot test patterns to be used to assess the ISR mining conditions in additional areas of the Phoenix deposit, as well as the completion of a FFT. Efforts in support of the 2022 Field Program commenced in the first quarter, including initial mobilization of necessary equipment to the Wheeler River site, the collaring of the PQ wells, and the drilling of six of the nine planned PQ wells.

  • Obtained regulatory approval for the expansion of the McClean Lake Tailings Management Facility

In January 2022 , the Canadian Nuclear Safety Commission ('CNSC') approved an amendment to the operating license for the McClean Lake Joint Venture ('MLJV') and Midwest Joint Venture ('MWJV') operations, which allows for the expansion of the McClean Lake TMF, along with the associated revised Preliminary Decommissioning Plan ('PDP') and cost estimate. The McClean Lake mill is a strategically significant asset in the Athabasca Basin region and the approval of the TMF expansion ensures the facility will be well positioned to serve as a regional milling centre for current and future uranium mining projects in the eastern portion of the Athabasca Basin for many years to come.

As a result of the updated PDP, the Company's pro rata share of the financial assurances required to be provided to the Province of Saskatchewan has decreased from $24,135,000 to $22,972,000 . Accordingly, subsequent to quarter end, the pledged amount of cash required under the 2022 Facility has been decreased to $7,972,000 , and the Company's additional cash collateral of $135,000 has been released – resulting in the return of $1,163,000 in previously restricted cash to the Company. Additionally, the Company's reclamation obligation has been updated to reflect the PDP, as well as other relevant estimates, resulting in a decrease in the obligation of $3,303,000 .

  • Discovered high-grade uranium mineralization at 24.68% owned Waterfound River Joint Venture ('Waterfound')

In March 2022 , multiple new high-grade intercepts of unconformity-hosted uranium mineralization were discovered in the final three drill holes completed during the winter 2022 exploration program at Waterfound. The results were highlighted by drill hole WF-68, which returned a broad zone of uranium mineralization, including a peak interval of 5.91% eU 3 O 8 over 3.9 metres (0.05% eU 3 O 8 cut-off) with a sub-interval grading 25.30% eU 3 O 8 over 0.7 m , located approximately 800 metres west, along the La Rocque Conductive Corridor, of the previously discovered high-grade mineralization (including 4.49% U 3 O 8 over 10.53 metres) at the Alligator Zone. The newly identified mineralization remains open along strike in both directions and additional drilling to test the extent of mineralization is expected to be completed during the planned summer exploration drilling program.

  • Received US$2.1 million from Uranium Industry a.s ("UI") pursuant to new Repayment Agreement

During the first quarter of 2022, the Company received US$2.1 million from UI pursuant to the terms of a Repayment Agreement that was executed in January 2022.  Under the Repayment Agreement, UI has agreed to make scheduled payments on account of an arbitration award in favour of Denison (with respect to the arbitration proceedings between the Company and UI related to the 2015 sale by Denison to UI of its mining assets and operations located in Mongolia ), plus additional interest and fees.  The total amount due to Denison under the Repayment Agreement, including amounts already received in 2022, is approximately US$16 million , which is payable over a series of quarterly installments and annual milestone payments ending on December 31, 2025 .

  • Welcomed new additions to the Board of Directors and the Management Team

In January 2022 , Ms. Laurie Sterritt was appointed to Denison's Board of Directors and Mr. Kevin Himbeault was appointed to the position of Vice President of Plant Operations & Regulatory Affairs. Ms. Sterritt has over 25 years of experience in the fields of Indigenous, government, and community relations, is a member of the Kispiox Band of the Gitxsan Nation, and is a Partner at Leaders International, an executive search firm in Canada.  Mr. Himbeault has over 25 years of diverse involvement in the mining industry, including an 18-year career with Cameco Corporation ('Cameco') where he most recently held the position of Operations Manager for the Key Lake mill.  Mr. Himbeault will be tasked with oversight of all matters related to process plant operations and regulatory affairs for Denison.

Additionally, in February 2022 , Mr. Yun Chang Jeong joined the Board of Directors as a nominee of Korea Hydro Nuclear Power ('KHNP') pursuant to the KHNP Strategic Relationship Agreement ('KHNP SRA').  Mr. Jeong currently serves as the General Manager of the Nuclear Fuel Supply Section of KHNP and fills the vacancy on Denison's Board created by the resignation of KHNP's previous nominee, Mr. Jun Gon Kim .

About Denison

Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada . The Company has an effective 95% interest in its flagship Wheeler River Uranium Project, which is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region of northern Saskatchewan . Denison's interests in Saskatchewan also include a 22.5% ownership interest in the McClean Lake Joint Venture, which includes several uranium deposits and the McClean Lake uranium mill that is contracted to process the ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest Main and Midwest A deposits and a 66.90% interest in the Tthe Heldeth Túé ('THT,' formerly J Zone) and Huskie deposits on the Waterbury Lake property. Each of Midwest Main, Midwest A, THT and Huskie are located within 20 kilometres of the McClean Lake mill.

Through its 50% ownership of JCU ( Canada ) Exploration Company, Limited ('JCU'), Denison holds additional interests in various uranium project joint ventures in Canada , including the Millennium project (JCU, 30.099%), the Kiggavik project (JCU, 33.8123%) and Christie Lake (JCU, 34.4508%).

Denison's exploration portfolio includes further interests in properties covering approximately 297,000 hectares in the Athabasca Basin region.

Denison is also engaged in post-closure mine care and maintenance services through its Closed Mines group, which manages Denison's Elliot Lake reclamation mine sites in the Elliot Lake region and provides related services to certain third-party projects.

Technical Disclosure and Qualified Person

The technical information contained in this press release has been reviewed and approved by David Bronkhorst , P.Eng, Denison's Vice President, Operations and/or Andrew Yackulic , P. Geo, Denison's Director, Exploration, each of whom is a Qualified Person in accordance with the requirements of NI 43-101.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING STATEMENTS

Certain information contained in this press release constitutes 'forward-looking information', within the meaning of the applicable United States and Canadian legislation concerning the business, operations and financial performance and condition of Denison.

Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as 'plans', 'expects', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates', or 'believes', or the negatives and/or variations of such words and phrases, or state that certain actions, events or results 'may', 'could', 'would', 'might' or 'will be taken', 'occur', 'be achieved' or 'has the potential to'.

In particular, this press release contains forward-looking information pertaining to the following: projections with respect to exploration, development and expansion plans and objectives, including the plans and objectives for Wheeler River and the related evaluation field program; the interpretation of the results of its exploration drilling programs; plans and objectives for the feasibility study; its investments in uranium; the estimates of Denison's mineral reserves and mineral resources; expectations regarding Denison's joint venture ownership interests; expectations regarding the continuity of its agreements with third parties; and its interpretations of, and expectations for, nuclear energy and uranium demand. Statements relating to 'mineral reserves' or 'mineral resources' are deemed to be forward-looking information, as they involve the implied assessment, based on certain estimates and assumptions that the mineral reserves and mineral resources described can be profitably produced in the future.

Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Denison to be materially different from those expressed or implied by such forward-looking statements. For example, the results and underlying assumptions and interpretations of the PFS as well as de-risking efforts such as the ISR field programs discussed herein may not be maintained after further testing or be representative of actual conditions within the applicable deposits.  In addition, Denison may decide or otherwise be required to extend its evaluation activities and/or the FS and/or otherwise discontinue testing, evaluation and development work if it is unable to maintain or otherwise secure the necessary approvals or resources (such as testing facilities, capital funding, etc.).  Denison believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be accurate and results may differ materially from those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-looking events, please refer to the factors discussed in Denison's Annual Information Form dated March 25, 2022 under the heading 'Risk Factors'. These factors are not, and should not be, construed as being exhaustive.

Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking information contained in this press release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with respect thereto speaks only as of the date of this press release. Denison does not undertake any obligation to publicly update or revise any forward-looking information after the date of this press release to conform such information to actual results or to changes in Denison's expectations except as otherwise required by applicable legislation.

Denison Reports Financial and Operational Results for Q1 2022, including $47.8 million gain on Physical Uranium Holdings (CNW Group/Denison Mines Corp.)

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/denison-reports-financial-and-operational-results-for-q1-2022--including-47-8-million-gain-on-physical-uranium-holdings-301540165.html

SOURCE Denison Mines Corp.

Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/May2022/04/c1896.html

News Provided by Canada Newswire via QuoteMedia

DML:CA,DNN
The Conversation (0)
Denison Announces Completion of Conceptual Mining Study Evaluating ISR for Midwest and Plans to Advance Efforts in 2023

Denison Announces Completion of Conceptual Mining Study Evaluating ISR for Midwest and Plans to Advance Efforts in 2023

Denison Mines logo (CNW Group/Denison Mines Corp.)

Denison Mines Corp. ("Denison" or the "Company") (TSX: DML) (NYSE American: DNN) is pleased to announce the successful completion of an internal conceptual mining study (the "Concept Study") examining the potential application of the In-Situ Recovery ("ISR") mining method at the Company's 25.17% owned Midwest project ("Midwest"). The Concept Study was prepared by Denison during 2022 and was formally issued to the Midwest Joint Venture ("MWJV") in early 2023. Based on the positive results of the Concept Study, the MWJV has now provided Denison with approval to complete additional ISR-related evaluation work for Midwest in 2023. View PDF version .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Denison Reports Financial and Operational Results for 2022, Including Significant De-Risking and Regulatory Milestones

Denison Reports Financial and Operational Results for 2022, Including Significant De-Risking and Regulatory Milestones

Denison Mines logo (CNW Group/Denison Mines Corp.)

Denison Mines Corp. ('Denison' or the 'Company') (TSX: DML) (NYSE American: DNN) today filed its Condensed Consolidated Financial Statements and Management's Discussion & Analysis ('MD&A') for the year ended December 31, 2022 . Both documents will be available on the Company's website at www.denisonmines.com , SEDAR (at www.sedar.com ) and EDGAR (at www.sec.govedgar.shtml ). The highlights provided below are derived from these documents and should be read in conjunction with them. All amounts in this release are in Canadian dollars unless otherwise stated. View PDF version .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
  Boss Energy

2024 Infill Drilling on Satellite Uranium Growth Deposits Complete

Resource update underway in preparation for bringing significant satellite deposits into the mine plan

Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce the conclusion of a successful infill drilling program at the Gould's Dam and Jason's satellite deposits within its Honeymoon Uranium project in South Australia.

Keep reading...Show less

NexGen Achieves Major Permitting Milestone

  • The Canadian Nuclear Safety Commission ("CNSC") has notified NexGen of successful completion of final Federal technical review.
  • This is the key requirement to scheduling a Federal Commission Hearing date and subsequent Federal Project approval decision.
  • The Federal Environmental Assessment ("EA") and License represent the final major approval steps after having received Provincial EA approval in November 2023 .
  • In production, the Rook I Project is poised to make NexGen one of the world's largest and most environmentally conscious mining companies.

NexGen Energy Ltd. ("NexGen" or the "Company") (TSX: NXE) (NYSE: NXE) (ASX: NXG) is excited and proud to announce a major milestone in the Federal EA process for its 100%owned Rook I Project ("the Project"). The CNSC has provided NexGen formal confirmation that the Company has successfully addressed all information requests received as part of the Federal technical review. With completion of the CNSC technical review, the next and final steps in the Federal approval process include scheduling a Commission Hearing Date for the Project, subject to which the CNSC will render an approval decision on the Project.

NexGen Energy Ltd. Logo (CNW Group/NexGen Energy Ltd.)

This historic milestone marks a crucial step forward for the Project that has been undergoing Canada's robust and rigorous regulatory process since 2019. Completion of the Federal EA technical review stage follows the CNSC having deemed NexGen's Federal licence application sufficient in September 2023 , and receipt of Provincial EA approval in November 2023 . This development reinforces Canada's path to re-establish itself as the leader in global uranium supply and partner of choice.

Leigh Curyer, Chief Executive Officer, commented: "This exciting outcome is a testament to the exceptional efforts of our entire NexGen team, the collaborative support of our valued Indigenous Nation partners, and our transparent approach with the CNSC to ensure a robust and thorough review that meets the highest standards of environmental protection for the sustainable development of the Rook I Project. Since inception, our honest and innovative holistic approach to the successful development of this generational project has set new industry standards as to what is possible, whilst positively impacting all our valued stakeholders.

Together with the Clearwater River Dene Nation, Métis Nation – Saskatchewan Northern Region 2 and Métis Nation – Saskatchewan , Buffalo River Dene Nation, and Birch Narrows Dene Nation, we are construction ready to deliver transformative and unprecedented social, economic and environmental benefits to local communities, the Province of Saskatchewan, Canada , and the world.

We're not just developing a mine - we're building strong communities while shaping a sustainable and secure global energy future. With over $800 million in cash and liquid assets, we are ready pending a positive Commission decision with all activities required to immediately commence major site works in place."

NexGen is poised to propel Canada back to the forefront of global clean energy fuel production. The Rook I Project embodies NexGen's commitment to elite environmental performance, unprecedented community inclusion, and responsible alignment with global net-zero goals.

About NexGen

NexGen Energy is a Canadian company focused on delivering clean energy fuel for the future. The Company's flagship Rook I Project is being optimally developed into the largest, low-cost producing uranium mine globally, incorporating the most elite standards in environmental and social governance. The Rook I Project is supported by a NI 43-101 compliant Feasibility Study which outlines the elite environmental performance and industry leading economics. NexGen is led by a team of experienced uranium and mining industry professionals with expertise across the entire mining life cycle, including exploration, financing, project engineering and construction, operations, and closure. NexGen is leveraging its proven experience to deliver a Project that leads the entire mining industry socially, technically, and environmentally. The Project and prospective portfolio in northern Saskatchewan will provide generational long-term economic, environmental, and social benefits for Saskatchewan, Canada , and the world.

NexGen is listed on the Toronto Stock Exchange and the New York Stock Exchange under the ticker symbol "NXE," and on the Australian Securities Exchange under the ticker symbol "NXG," providing access to global investors to participate in NexGen's mission of solving three major global challenges in decarbonization, energy security, and access to power. The Company is headquartered in Vancouver, British Columbia , with its primary operations office in Saskatoon , Saskatchewan.

Cautionary Note to U.S. Investors

This news release includes Mineral Reserves and Mineral Resources classification terms that comply with reporting standards in Canada and the Mineral Reserves and the Mineral Resources estimates are made in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. These standards differ from the requirements of the Securities and Exchange Commission ("SEC") set by the SEC's rules that are applicable to domestic United States reporting companies. Consequently, Mineral Reserves and Mineral Resources information included in this news release is not comparable to similar information that would generally be disclosed by domestic U.S. reporting companies subject to the reporting and disclosure requirements of the SEC Accordingly, information concerning mineral deposits set forth herein may not be comparable with information made public by companies that report in accordance with U.S. standards.

Forward-Looking Information

The information contained herein contains "forward-looking statements" within the meaning of applicable United States securities laws and regulations and "forward-looking information" within the meaning of applicable Canadian securities legislation. "Forward-looking information" includes, but is not limited to, statements with respect to estimates for CapEx, OpEx and a payback period of 12 months, the appointment of a lead lender group, the availability of financing for the Project, the advancement of detailed engineering and contract negotiations, bolstering the globe's uranium supply chains to meet the rising demand for nuclear energy, the timing and cost of reclamation, including as part of the UGTMF and after-tax free cash flow remaining materially consistent with the FS, Free Cash Flow, Payback Period and IRR relative to various uranium prices, the delivery of clean energy fuel for the future, the development of the largest low cost producing uranium mine globally and incorporating elite standards in environmental and social governance, delivering a project that leads the entire mining industry socially, technically and environmentally, providing generational long-term economic, environmental and social benefits for Saskatchewan, Canada and the world, planned exploration and development activities and budgets, the interpretation of drill results and other geological information, mineral reserve and resource estimates (to the extent they involve estimates of the mineralization that will be encountered if a project is developed), requirements for additional capital, capital costs, operating costs, cash flow estimates, production estimates, the future price of uranium and similar statements relating to the economics of a project, including the Rook I Project. Generally, forward-looking information and statements can be identified by the use of forward-looking terminology such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "believes" or the negative connotation thereof or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" or the negative connotation thereof.

Forward-looking information and statements are based on NexGen's current expectations, beliefs, assumptions, estimates and forecasts about its business and the industry and markets in which it operates. Forward-looking information and statements are made based upon numerous assumptions, including, among others, that financing for the Project will be available in a timely manner and on terms acceptable to the Company, the results of planned exploration and development activities will be as anticipated and on time; the price of uranium; the cost of planned exploration and development activities; that, as plans continue to be refined for the development of the Rook I Project, there will be no changes in costs, engineering details or specifications that would materially adversely affect its viability; that financing will be available if and when needed and on reasonable terms; that third-party contractors, equipment, supplies and governmental and other approvals required to conduct NexGen's planned exploration and development activities will be available on reasonable terms and in a timely manner; that there will be no revocation of government approvals; that general business, economic, competitive, social and political conditions will not change in a material adverse manner; the assumptions underlying the Company's mineral reserve and resource estimates and updated/revised CapEx, OpEx, SusEx, and pay back period; assumptions made in the interpretation of drill results and other geological information; the ability to achieve production on the Rook I Project; and other estimates, assumptions and forecasts disclosed in the Feasibility Study for the Rook I Project. Although the assumptions made by the Company in providing forward-looking information or making forward-looking statements were considered reasonable by management at the time they were made, there can be no assurance that such assumptions will prove to be accurate.

Forward-looking information and statements also involve known and unknown risks and uncertainties and other factors, which may cause actual results, performances and achievements of NexGen to differ materially from any projections of results, performances and achievements of NexGen expressed or implied by such forward-looking information or statements, including, among others, negative operating cash flow and dependence on third-party financing, uncertainty of additional financing, the risk that pending assay results will not confirm previously announced preliminary results, the imprecision of mineral reserve and resource estimates, the price and appeal of alternate sources of energy, sustained low uranium prices, aboriginal title and consultation issues, development risks, climate change, uninsurable risks, reliance upon key management and other personnel, risks related to title to its properties, information security and cyber threats, failure to manage conflicts of interest, failure to obtain or maintain required permits and licences, changes in laws, regulations and policy, competition for resources, political and regulatory risks, general inflationary pressures, industry and economic factors that may affect the business, and other factors discussed or referred to in the Company's most recent Annual Information Form under "Risk Factors" and management's discussion and analysis under "Other Risks Factors" filed on SEDAR+ at www.sedarplus.ca and 40-F filed on Edgar at www.sec.gov   .

Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in the forward-looking information or statements or implied by forward-looking information or statements, there may be other factors that cause results not to be as anticipated, estimated or intended.

There can be no assurance that forward-looking information and statements will prove to be accurate, as actual results and future events could differ materially from those anticipated, estimated or intended. Accordingly, readers are cautioned not to place undue reliance on forward-looking information or statements due to the inherent uncertainty thereof. The Company undertakes no obligation to update or reissue forward-looking information as a result of new information or events except as required by applicable securities laws.

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/nexgen-achieves-major-permitting-milestone-302309673.html

SOURCE NexGen Energy Ltd.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/November2024/19/c8458.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
The word "uranium" beside green up arrow.

Russia Restricts US Uranium Exports, Retaliating to American Ban

The Russian government has imposed temporary restrictions on enriched uranium exports to the US.

Announced on November 15, the move follows the US' decision toban imports of Russian uranium.

While the US legislation went into effect in August, it allows for waivers to address potential supply disruptions through 2027. The new Russian policy introduces uncertainty during this time period.

Keep reading...Show less

Foremost Clean Energy Announces Strategic Engagement with Red Cloud Financial Services

Foremost Clean Energy Ltd. ( NASDAQ: FMST ) ( CSE: FAT ) (" Foremost " or the " Company "), an emerging North American uranium and lithium exploration company, is pleased to announce today that it has entered into a strategic agreement (the " Agreement ") with Red Cloud Financial Services Inc. (" RCFS" or " Red Cloud "), an arms-length independent contractor, to provide promotional services, including advice on marketing, communications and social media activities. Under the engagement, Red Cloud will be paid a fee of $10,000 per month effective October 14, 2024, for a twelve-month term which automatically renews month-to-month thereafter unless either party provides written notice of termination to the other party thirty (30) days prior to the date of termination.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Nuclear reactors and a stock chart.

US Plans to Triple Nuclear Power Capacity by 2050

The Biden administration has announced a strategic roadmap to significantly expand the United States' nuclear energy capacity, setting a target to triple capacity by 2050.

In a new nine pillar framework, the Biden-Harris administration has laid out its plans to add 200 gigawatts (GW) of new nuclear energy through new reactor builds, reactivations and upgrades to existing facilities.

The initiative seeks to meet a growing demand for reliable, carbon-free power as the nation transitions away from fossil fuels and toward cleaner energy sources.

Keep reading...Show less
Red graph and arrow pointing down.

Paladin Cuts Uranium Production Forecast, Share Price Declines

Shares of Paladin Energy (ASX:PDN,OTCQX:PALAF) declined this week after the company shared an update on its Langer Heinrich mine and revised its 2025 fiscal year production guidance.

The company now expects the mine to produce 3 million to 3.6 million pounds of U3O8, lower than its earlier prediction of 4 million to 4.5 million pounds. According to Paladin, the drop is the result of lower-than-expected output in October, which was caused by water supply disruptions, as well as continued variability in stockpiled ore.

Production from Langer Heinrich amounted to 186,667 pounds during the month.

Keep reading...Show less

Latest Press Releases