Vertex Minerals Limited  Reward Gold Mine and Company Update

Vertex Minerals Limited Reward Gold Mine and Company Update

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX) (OTCMKTS:VTXXF) is pleased to announce a further update on the Reward Gold mine start up.

HIGHLIGHTS

- All major components are now installed and fitted at the Reward Gold Mine Gravity Plant.

- Electrical fit out is well underway.

- Piping and water reticulation is ongoing.

- Tails lines are being laid to the dry sand stack location.

- Plant power up is planned for mid-December.

- General Manager and other key personnel have commenced employment.

- Ore Sorter structure is under construction and will be installed in January

- The plant will be commissioned on stockpiles located at the plant prior to the Ore Sorter installation.

- Road infrastructure upgraded.

- Portal entry and ore handling area refurbished and expanded.

- Vertex on track for January commissioning of the plant.

Mobilisation of the Gravity Plant from Ballart to site commenced earlier this month (as announced 13 November 2024), with all major components now onsite, installed and fitted at the Gravity Plant. Fitout of ancillary services (including electrical and water) is well underway, with completion and initial powering-up scheduled for mid-December 2024.

All Civil Works for this stage, including the upgrading and refurbishment of Road Infrastructure, portal entry and the ore handling area are also complete.

Ore Sorter and Forward Plan

Compelling results from Ore Sorting testwork (including a 337% increase in grade and 79% mass reduction) as announced on 25th July 2024, resulted in a decision to incorporate pre-concentration into the flow sheet and design for the Hill End project (as announced 11 September 2024). Construction of the Ore Sorter structure has commenced, with installation expected in January 2025. Installation of the Ore Sorter is not expected to delay plant commissioning, with initial processing of existing stockpiles located at the plant location to commence prior to installation and commissioning of the Ore Sorter.

Corporate and Financial

On 7 November 2024, Shareholders voted to approve the second tranche of the Company's 2-tranche share placement announced in mid-August 2024. All funds for the second tranche have been received and allotment is expected shortly.

The Company's Annual General Meeting (AGM) is scheduled for 29 November 2024 and resolutions include approval for the conversion of loan funds received under the capital-raising announced in October 2024. Various option issue approvals were granted in the 7 November Meeting and are being sought at the AGM and a prospectus for the issue of those options is being prepared.

On 27 May 2024 the Company announced that it had signed a terms sheet with Ocean Partners for a US$10M Prepayment Facility, subject to conditions precedent. Following on from the revised mine design and Gravity plant flow sheet, because of the decision to utilise an ore sorter, the capital expenditure required to develop the mine was significantly lowered. A facility of this size is no longer expected to be required by the Company and the parties have agreed that the proposed arrangement will not be completed, with no penalty to the Company. The Company is in negotiations with several parties in relation to a significantly smaller debt or prepayment facility.

Commenting on the progress, Vertex Executive Chairman Roger Jackson said: "We are very excited by the progress that has been made with the Gravity Gold plant installation at our mine ready Gold project.

The installation is well ahead of the time we had scheduled, which has helped recover the time lost due to weather with the civil construction. We are hopeful we can now power the plant up for testing in just a few weeks. We then can commission the plant with the gold ore stockpiles we have sitting at the plant.

I would commend Gekko and our Hill End team for their efforts with this installation."

*To view photgraphs, please visit:
https://abnnewswire.net/lnk/BSH85XZW



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited



Contact:
Roger Jackson
Executive Chairman
roger@vertexminerals.com.au

Tully Richards
Technical Director
tully@vertexminerals.com.au

News Provided by ABN Newswire via QuoteMedia

VTX:AU
Vertex Minerals

Vertex Minerals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Vertex Minerals

Vertex Minerals


Keep reading...Show less

Australia’s next high-grade, green gold producer

Vertex Minerals Limited  Underground Production Commences at the Reward Gold Mine Project

Vertex Minerals Limited Underground Production Commences at the Reward Gold Mine Project

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) (OTCMKTS:VTXXF) commences underground production at the Reward Gold Mine, moving to high grade gold production.

Operational Milestones

- First blasting of gold producing ore on the Lady Belmore Reef was undertaken over the weekend.

- The material will start complementing the low-grade gold stockpile feed to the Gravity Processing Plant, until all mining fronts are enabled.

- In forthcoming weeks, VTX remains firmly on track to commence processing of high-grade stope ore from the underground mine.

- The Reward Underground 11kva to 1000v Transformer Substation is installed and powered up. Cabling to the Primary Fan is completed.

- Access Drives to the two Starter Stopes are being cleaned, ready for the Production Rig to commence drilling the High-Grade Stopes.

- Decline 3 developed on the Mica Vein is fully dewatered, ready to be flatback mined for providing further gold feed to the Gravity Plant.

- Vertex aims to have developed at least 4 mining fronts and maintain continuous feed to the plant, which will involve various mining methods.

- Mining the Reward Gold Mine - Resource 225kozs at 16.7g/t

As previously announced, the startup mine schedule includes mining 2,075 tonnes at 17.8 g/t Au from a developed airleg stope block. The planned stope width is the same as the interpretation of the mineralisation. Refer to VTX ASX announcement 4th June 2025

Given the stope will take some time to extract, additionally, the Vertex Geology and Mining Team have brought forward a very high-grade long hole stope to commence mining in August 2025. The high-grade long hole stope isto be mined with a long hole stope method, using the Epiroc Production Rig.

*To view photographs, please visit:
https://abnnewswire.net/lnk/2U10401V



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Underground Production Commences Reward Gold Mine Project

Underground Production Commences Reward Gold Mine Project

Vertex Minerals (VTX:AU) has announced Underground Production Commences Reward Gold Mine Project

Download the PDF here.

Vertex Minerals Limited  Quarterly Activities Report

Vertex Minerals Limited Quarterly Activities Report

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) (OTCMKTS:VTXXF), is pleased to provide a summary of its activities for the quarter ended 30 June 2025.

HIGHLIGHTS FOR QUARTER

- Commencement of operations at the Reward Gold Mine Gravity plant, with processing of low-grade stockpiled gold ore through the gravity gold plant undertaken throughout the quarter, producing saleable gold.

- During the quarter, Vertex remained focused on moving the business to be operationally ready for underground mining at the Reward gold mine.

- VTX remainsfirmly on track to deliver first underground high grade gold ore to the Gravity Gold plant in Q3 2025, with commissioning and underground mine readiness ramp-up activities progressing as planned.

- VTX's Technical Services team has identified a fully developed stope block to include in the mine production start-up.

o Stopes are suitable for airleg mining which will augment jumbo production.

o Stope blocks contain an Inferred Resource of 2,075 tonnes at 17.8 g/t Au and forms part of the 2023 Mineral Resource Estimate. With the lower block having over 700 tonnes at 42.5 g/t. The planned stope width is the same as the interpretation of the mineralisation

- Key management hires, with staff procurement complete for on-site field team:

o Appointment of Mr Vince Fayad and Mr Kurt Laney as Joint CFOs

o Appointment of Mr Ian Morgan as Company Secretary

o Specialist on-site technical services team now fully onboarded

- Firm commitments received to raise approximately A$11 million via a combination of share placement and convertible note issuance to institutional and sophisticated investors.

- Vertex registered office and principal place of business changed to the following address: 6 Bowen St, Hill End, NSW, 2850.

- Vertex will run the mine, drill equipment and the processing plant as an owner operator. Gold Underground Mining Readiness

- First phase of underground specialist miners onboarded under owner operator model

o TD1 Jumbo Drill fully operational and operating underground

o Primary ventilation installed

o First stope development dewatering completed

o Explosive Magazine constructed

o Water feed installed

o Air lines installed and operational -

o 11kva power installation underway

o Jumbo boxes on site

- Revised mine plan and schedule completed and ready to implement.

- Pulse Mining System installed and implemented.

- Underground Ore trialled through gravity plant

o The underground miners have trialled a batch of 90 ton of development material with some reef quartz through the gravity plant with throughput exceeding expectation and beyond the nameplate plant flow sheet value.

- INX Software Installed and Implemented

o INX Software and site access kiosks to go live at mine site in August.

o INX will improve safety framework with real time incident and injury reporting system.

o Strengthens site access controls for employees, contractors and visitors to site.

- Sand Stack facility fully operational

o Facility fully functioning with return water pump station installed and operational (water recycling)

o 57 Megalitre Turon River water licence purchased for back up water supply

- Environmental & Compliance Implementation

o Multiple real-time monitoring systems installed (dust, noise, vibration)

- Underground Drilling site being established

o Drill Cuddy (room for drill rig) drilled and fired for Vertex Diamond Rig readiness

Improvements to plant

- DSM screen installed

- Gemini table improvements with new top and gearbox

- Process water pump upgrade

- Treating of underground rock has shown higher plant throughput

Vertex Minerals Executive Chairman, Roger Jackson, commented:

"We are pleased to present our Activities Report for the June quarter - another busy period where our team worked seamlessly to coordinate the many moving parts involved in the redevelopment of the high-grade Reward mine and associated processing facilities. During the quarter, Vertex delivered on another round of key operational milestones for both mine optimisation and improvements to the processing plant. With the completion of these initiatives, Vertex is now positioned to execute on our stated objective to recommence underground mining in August, underpinning our transition to high-grade gold production."

"Reflecting investor confidence in our development strategy, we were also pleased to complete a successful $11m capital raise during the quarter, which leaves the Company well funded to finalise all pre-development works for mining and processing, and fully unlock the value of this asset. As we head into the September quarter, I'm thrilled to be working as part of a really strong team, all of whom are committed to the execution of our stated development strategy. We look forward to providing more updates in the coming months and mining and production gets underway."

*To view the full Quarterly Report, please visit:
https://abnnewswire.net/lnk/YA65USAA



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Vertex Minerals Limited  Capital Raising Update

Vertex Minerals Limited Capital Raising Update

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) (OTCMKTS:VTXXF) confirms that on 28 July 2025 it received A$3.9 million (before costs) through the issuance of new ordinary Shares as part of the A$11 million capital raising ("Capital Raising") announced by the Company on 12 May 2025 and approved at the General Meeting which took place on 21 July 2025.

The Capital Raising had also included the earlier issuance of A$3.5 million in Convertible Loans, bringing total proceeds received to date from the financing initiative to approximately A$7.5 million.

With respect to the A$3.9 million secured on 28 July 2025, 18,377,562 fully paid ordinary shares were issued by the Company ("Shares") at A$0.21 per Share.

At the commencement of the Capital Raising, associates of the Company's cornerstone investor and largest shareholder with 17% of the shares on issue (Gleneden Nominees Pty Ltd) committed to subscribe for A$3.6 million of Shares. Timing for receipt of these funds has now been revised to on or before 15 September 2025, as is provided for in an agreement entered on 27 July 2025 between the Company and Gleneden Nominees Pty Ltd.

The Company has also retained its ability to place the remaining A$3.6 million to other interested investors (on the same terms as the Capital Raising).

Receipt of the A$3.9 million, along with the $3.5 million Convertible Loan component of the Capital Raising, has provided the Company with financial liquidity for the near-term restart of the high-grade Hill End Gold Project, at a time of an historically strong A$ gold price.



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Questcorp Mining Completes 25 Percent of Maiden Drilling Program at the La Union Gold & Silver Project in Mexico

Questcorp Mining Completes 25 Percent of Maiden Drilling Program at the La Union Gold & Silver Project in Mexico

Questcorp Mining Inc. (CSE: QQQ,OTC:QQCMF) (OTCQB: QQCMF) (FSE: D910) (the "Company" or "Questcorp") is pleased to announce they have completed 25% of the planned drilling program on its La Union Project in northwest Sonora, Mexico. This work is being carried out by property vendor and operator Riverside Resources Inc. (TSXV: RRI).

Highlights

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Noble Reports Updates on Homeland Nickel

Noble Reports Updates on Homeland Nickel

(TheNewswire)

TORONTO TheNewswire - August 18, 2025 Noble Mineral Exploration Inc. (" Noble " or the " Company ") (TSXV: NOB,OTC:NLPXF) (OTCQB: NLPXF) is pleased to report that t he News Release issued today giving an Exploration and Corporate Update for Homeland Nickel in which Noble has a significant shareholding was issued today the contents of which are below. This all relates to the White House announcing immediate measures to be introduced to significantly increase the US production of lithium, nickel, copper, and rare earths, with an eye to increased production, the creation of jobs and, significantly, the reduction of US reliance on foreign nations.

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Bold Ventures Announces Results of A and B Horizon Soil Sampling Program on Its Burchell Property

Bold Ventures Announces Results of A and B Horizon Soil Sampling Program on Its Burchell Property

Bold Ventures Inc. (TSXV: BOL,OTC:BVLDF) (the "Company" or "Bold") is pleased to announce the results of an A and B Horizon Soil Sampling Program on its Burchell Gold and Copper Property ("the Property"), located approximately 100 km west of Thunder Bay, Ontario. 474 samples in total were collected on a flagged 800 m by 1 km grid centered on the 111 Zone, where grab samples returned from 10 ppb Au up to 68 gt Au last Fall (see Bold news release dated January 9, 2025).

Highlights from the survey include:

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Prismo Engages Windfall Geotek for Data Analysis at Hot Breccia

Prismo Engages Windfall Geotek for Data Analysis at Hot Breccia

(TheNewswire)

Vancouver, British Columbia TheNewswire - August 18th, 2025 Prismo Metals Inc. (the " Company ") (CSE: PRIZ,OTC:PMOMF) (OTCQB: PMOMF) is pleased to announce that its has engaged Windfall Geotek Inc. to apply its proprietary Windfall AI System to integrate and analyze geophysical data, topography data and drill hole data at Prismo's Hot Breccia copper project located in Arizona.

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
400% Increase in Gecko Resource to 18.4Mt @2.32% CuEq

400% Increase in Gecko Resource to 18.4Mt @2.32% CuEq

CuFe Limited (CUF:AU) has announced 400% Increase in Gecko Resource to 18.4Mt @2.32% CuEq

Download the PDF here.

Vertex Minerals

Vertex Minerals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×