Vertex Minerals Limited  Reward Gold Mine and Company Update

Vertex Minerals Limited Reward Gold Mine and Company Update

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX) (OTCMKTS:VTXXF) is pleased to announce a further update on the Reward Gold mine start up.

HIGHLIGHTS

- All major components are now installed and fitted at the Reward Gold Mine Gravity Plant.

- Electrical fit out is well underway.

- Piping and water reticulation is ongoing.

- Tails lines are being laid to the dry sand stack location.

- Plant power up is planned for mid-December.

- General Manager and other key personnel have commenced employment.

- Ore Sorter structure is under construction and will be installed in January

- The plant will be commissioned on stockpiles located at the plant prior to the Ore Sorter installation.

- Road infrastructure upgraded.

- Portal entry and ore handling area refurbished and expanded.

- Vertex on track for January commissioning of the plant.

Mobilisation of the Gravity Plant from Ballart to site commenced earlier this month (as announced 13 November 2024), with all major components now onsite, installed and fitted at the Gravity Plant. Fitout of ancillary services (including electrical and water) is well underway, with completion and initial powering-up scheduled for mid-December 2024.

All Civil Works for this stage, including the upgrading and refurbishment of Road Infrastructure, portal entry and the ore handling area are also complete.

Ore Sorter and Forward Plan

Compelling results from Ore Sorting testwork (including a 337% increase in grade and 79% mass reduction) as announced on 25th July 2024, resulted in a decision to incorporate pre-concentration into the flow sheet and design for the Hill End project (as announced 11 September 2024). Construction of the Ore Sorter structure has commenced, with installation expected in January 2025. Installation of the Ore Sorter is not expected to delay plant commissioning, with initial processing of existing stockpiles located at the plant location to commence prior to installation and commissioning of the Ore Sorter.

Corporate and Financial

On 7 November 2024, Shareholders voted to approve the second tranche of the Company's 2-tranche share placement announced in mid-August 2024. All funds for the second tranche have been received and allotment is expected shortly.

The Company's Annual General Meeting (AGM) is scheduled for 29 November 2024 and resolutions include approval for the conversion of loan funds received under the capital-raising announced in October 2024. Various option issue approvals were granted in the 7 November Meeting and are being sought at the AGM and a prospectus for the issue of those options is being prepared.

On 27 May 2024 the Company announced that it had signed a terms sheet with Ocean Partners for a US$10M Prepayment Facility, subject to conditions precedent. Following on from the revised mine design and Gravity plant flow sheet, because of the decision to utilise an ore sorter, the capital expenditure required to develop the mine was significantly lowered. A facility of this size is no longer expected to be required by the Company and the parties have agreed that the proposed arrangement will not be completed, with no penalty to the Company. The Company is in negotiations with several parties in relation to a significantly smaller debt or prepayment facility.

Commenting on the progress, Vertex Executive Chairman Roger Jackson said: "We are very excited by the progress that has been made with the Gravity Gold plant installation at our mine ready Gold project.

The installation is well ahead of the time we had scheduled, which has helped recover the time lost due to weather with the civil construction. We are hopeful we can now power the plant up for testing in just a few weeks. We then can commission the plant with the gold ore stockpiles we have sitting at the plant.

I would commend Gekko and our Hill End team for their efforts with this installation."

*To view photgraphs, please visit:
https://abnnewswire.net/lnk/BSH85XZW



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited



Contact:
Roger Jackson
Executive Chairman
roger@vertexminerals.com.au

Tully Richards
Technical Director
tully@vertexminerals.com.au

News Provided by ABN Newswire via QuoteMedia

VTX:AU
Vertex Minerals

Vertex Minerals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Vertex Minerals

Vertex Minerals


Keep reading...Show less

Australia’s next high-grade, green gold producer

Vertex Minerals Limited  Reward Gold Mine Production Update

Vertex Minerals Limited Reward Gold Mine Production Update

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) (OTCMKTS:VTXXF) is pleased to announce the commencement of development of the first two stope blocks at the Reward Mine. Since commissioning the ventilation fan on Thursday 21 August, a total of 500 tonnes of ore has been blasted and bogged to the Amalgamated portal for processing.

Operational Milestones

- Vertex is today pleased to announce first freshly blasted ore sourced from the first two stoping blocks at the Reward Underground Mine.

- Ore is from development stripping (making ore drives larger for machine access) in preparation for mechanised stoping operations.

- Reward ore will be processed via the Gravity Only gold processing plant located at the entry to the mine.

- The material will start replacing feed from the low-grade surface ore stockpile, with the aim of achieving 100% feed from higher grade underground ore sources over the next few weeks.

- The underground electrical transformer is energised and 1,000 Volt power reticulated underground.

- The Primary Ventilation Fan was commissioned on Thursday 21 August, giving excitement to the Vertex Mining Team. Powered ventilation in the mine means mining can start in earnest.

- 1550 Decline is dewatered, with first ore blasted.

- Vertex aims to have developed multiple mining fronts, with over around 400m of strike, to achieve continuous feed to the plant.

Underground broken stocks include 200 tonnes at 5.4g/t from the 1325 strip, while the remaining 300 tonnes is pending assay grades but from 1438 stope area and 1555 decline strip.

The Company is spreading initial production areas around 400 metres of strike length to provide operational flexibility. Significant effort is underway setting up the 1720 stopes to the northern end of the mine, primarily accessed from the 1555 Decline. The Company is focussed on initially mining high grade ore, primarily from the Mica 1 and Mica 2 Veins. M1 and M2 are parallel veins and around 2m apart.

The Company is employing multiple mining methods to diversify risk and maximise head grade These include airleg gallery and shrink stoping, jumbo cut and fill stoping and narrow vein longhole open stoping.

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/0CUE41IB



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Vertex Minerals Limited  Underground Production Commences at the Reward Gold Mine Project

Vertex Minerals Limited Underground Production Commences at the Reward Gold Mine Project

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) (OTCMKTS:VTXXF) commences underground production at the Reward Gold Mine, moving to high grade gold production.

Operational Milestones

- First blasting of gold producing ore on the Lady Belmore Reef was undertaken over the weekend.

- The material will start complementing the low-grade gold stockpile feed to the Gravity Processing Plant, until all mining fronts are enabled.

- In forthcoming weeks, VTX remains firmly on track to commence processing of high-grade stope ore from the underground mine.

- The Reward Underground 11kva to 1000v Transformer Substation is installed and powered up. Cabling to the Primary Fan is completed.

- Access Drives to the two Starter Stopes are being cleaned, ready for the Production Rig to commence drilling the High-Grade Stopes.

- Decline 3 developed on the Mica Vein is fully dewatered, ready to be flatback mined for providing further gold feed to the Gravity Plant.

- Vertex aims to have developed at least 4 mining fronts and maintain continuous feed to the plant, which will involve various mining methods.

- Mining the Reward Gold Mine - Resource 225kozs at 16.7g/t

As previously announced, the startup mine schedule includes mining 2,075 tonnes at 17.8 g/t Au from a developed airleg stope block. The planned stope width is the same as the interpretation of the mineralisation. Refer to VTX ASX announcement 4th June 2025

Given the stope will take some time to extract, additionally, the Vertex Geology and Mining Team have brought forward a very high-grade long hole stope to commence mining in August 2025. The high-grade long hole stope isto be mined with a long hole stope method, using the Epiroc Production Rig.

*To view photographs, please visit:
https://abnnewswire.net/lnk/2U10401V



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Underground Production Commences Reward Gold Mine Project

Underground Production Commences Reward Gold Mine Project

Vertex Minerals (VTX:AU) has announced Underground Production Commences Reward Gold Mine Project

Download the PDF here.

Vertex Minerals Limited  Quarterly Activities Report

Vertex Minerals Limited Quarterly Activities Report

Perth, Australia (ABN Newswire) - Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) (OTCMKTS:VTXXF), is pleased to provide a summary of its activities for the quarter ended 30 June 2025.

HIGHLIGHTS FOR QUARTER

- Commencement of operations at the Reward Gold Mine Gravity plant, with processing of low-grade stockpiled gold ore through the gravity gold plant undertaken throughout the quarter, producing saleable gold.

- During the quarter, Vertex remained focused on moving the business to be operationally ready for underground mining at the Reward gold mine.

- VTX remainsfirmly on track to deliver first underground high grade gold ore to the Gravity Gold plant in Q3 2025, with commissioning and underground mine readiness ramp-up activities progressing as planned.

- VTX's Technical Services team has identified a fully developed stope block to include in the mine production start-up.

o Stopes are suitable for airleg mining which will augment jumbo production.

o Stope blocks contain an Inferred Resource of 2,075 tonnes at 17.8 g/t Au and forms part of the 2023 Mineral Resource Estimate. With the lower block having over 700 tonnes at 42.5 g/t. The planned stope width is the same as the interpretation of the mineralisation

- Key management hires, with staff procurement complete for on-site field team:

o Appointment of Mr Vince Fayad and Mr Kurt Laney as Joint CFOs

o Appointment of Mr Ian Morgan as Company Secretary

o Specialist on-site technical services team now fully onboarded

- Firm commitments received to raise approximately A$11 million via a combination of share placement and convertible note issuance to institutional and sophisticated investors.

- Vertex registered office and principal place of business changed to the following address: 6 Bowen St, Hill End, NSW, 2850.

- Vertex will run the mine, drill equipment and the processing plant as an owner operator. Gold Underground Mining Readiness

- First phase of underground specialist miners onboarded under owner operator model

o TD1 Jumbo Drill fully operational and operating underground

o Primary ventilation installed

o First stope development dewatering completed

o Explosive Magazine constructed

o Water feed installed

o Air lines installed and operational -

o 11kva power installation underway

o Jumbo boxes on site

- Revised mine plan and schedule completed and ready to implement.

- Pulse Mining System installed and implemented.

- Underground Ore trialled through gravity plant

o The underground miners have trialled a batch of 90 ton of development material with some reef quartz through the gravity plant with throughput exceeding expectation and beyond the nameplate plant flow sheet value.

- INX Software Installed and Implemented

o INX Software and site access kiosks to go live at mine site in August.

o INX will improve safety framework with real time incident and injury reporting system.

o Strengthens site access controls for employees, contractors and visitors to site.

- Sand Stack facility fully operational

o Facility fully functioning with return water pump station installed and operational (water recycling)

o 57 Megalitre Turon River water licence purchased for back up water supply

- Environmental & Compliance Implementation

o Multiple real-time monitoring systems installed (dust, noise, vibration)

- Underground Drilling site being established

o Drill Cuddy (room for drill rig) drilled and fired for Vertex Diamond Rig readiness

Improvements to plant

- DSM screen installed

- Gemini table improvements with new top and gearbox

- Process water pump upgrade

- Treating of underground rock has shown higher plant throughput

Vertex Minerals Executive Chairman, Roger Jackson, commented:

"We are pleased to present our Activities Report for the June quarter - another busy period where our team worked seamlessly to coordinate the many moving parts involved in the redevelopment of the high-grade Reward mine and associated processing facilities. During the quarter, Vertex delivered on another round of key operational milestones for both mine optimisation and improvements to the processing plant. With the completion of these initiatives, Vertex is now positioned to execute on our stated objective to recommence underground mining in August, underpinning our transition to high-grade gold production."

"Reflecting investor confidence in our development strategy, we were also pleased to complete a successful $11m capital raise during the quarter, which leaves the Company well funded to finalise all pre-development works for mining and processing, and fully unlock the value of this asset. As we head into the September quarter, I'm thrilled to be working as part of a really strong team, all of whom are committed to the execution of our stated development strategy. We look forward to providing more updates in the coming months and mining and production gets underway."

*To view the full Quarterly Report, please visit:
https://abnnewswire.net/lnk/YA65USAA



About Vertex Minerals Limited:

Vertex Minerals Limited (ASX:VTX,OTC:VTXXF) is an Australian based gold exploration company developing its advanced Hargraves and Hill End gold projects located in the highly prospective Eastern Lachlan Fold Belt of Central West NSW. Other Company assets include the Pride of Elvire gold project and Taylors Rock gold/nickel/lithium project both located in the Eastern Goldfields of WA. The focus of Vertex Minerals is to advance the commercial production of gold from its NSW projects embracing an ethical and environmentally sustainable approach.



Source:
Vertex Minerals Limited

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Silver47 Announces Closing of $23 Million Brokered LIFE Financing, Including Full Exercise of the Over-Allotment Option

Silver47 Announces Closing of $23 Million Brokered LIFE Financing, Including Full Exercise of the Over-Allotment Option

Silver47 Exploration Corp. (TSXV: AGA,OTC:AAGAF) (OTCQB: AAGAF) ("Silver47" or the "Company") is pleased to announce the closing of its previously announced brokered private placement (the "Offering") of units (each, a "Unit") at a price of $0.70 per Unit for aggregate gross proceeds of $23,000,460, including the full exercise of the over-allotment option.

The Offering was led by Research Capital Corporation, as lead agent and sole bookrunner, on behalf of a syndicate of agents, including Eventus Capital Corp. and Haywood Securities Inc. (collectively, the "Agents").

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
GlobeTrotters Resource Group Inc. Announces Filing of Updated Early Warning Report

GlobeTrotters Resource Group Inc. Announces Filing of Updated Early Warning Report

GlobeTrotters Resource Group Inc. ("GlobeTrotters" or the "Acquiror") announces that, on September 15, 2025, GlobeTrotters disposed of ownership of an aggregate of 1,428,000 common shares (the "Shares") of Forte Minerals Corp. ("Forte" or the "Issuer") at an approximate price of $0.75 per Share pursuant to certain market sales over the facilities of the TSX Venture Exchange (the "Disposition").

Immediately prior to the completion of the Disposition, the Acquiror owned a total of 6,298,333 Shares, representing approximately 9.59% of the issued and outstanding Shares on a non-diluted basis.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Heritage Mining Confirms New Gold Mineralization at the Scattergood Project

Heritage Mining Confirms New Gold Mineralization at the Scattergood Project

(TheNewswire)

VANCOUVER, BC TheNewswire - September 16, 2025 - Heritage Mining Ltd. (CSE: HML FRA: Y66) (" Heritage " or the " Company ") is pleased to announce the results from its 2025 prospecting program at its Scattergood Project ("Scattergood") (Figure 1, 2). The Company has confirmed surface gold mineralization in close proximity (~4.5km) to Dynasty Gold's Pelham Deposit (Figure 2).

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Prismo Metals Identifies Porphyry Style Mineralization at Silver King

Prismo Metals Identifies Porphyry Style Mineralization at Silver King

(TheNewswire)

Vancouver, British Columbia TheNewswire - September 15th, 2025 Prismo Metals Inc. (the " Company " ) (CSE: PRIZ,OTC:PMOMF) (OTCQB: PMOMF) is pleased to report that its exploration team has identified porphyry style mineralization at its Silver King project located outside the town of Superior in Arizona. Given the proximity of the nearby Resolution Copper deposit (a joint venture between Rio Tinto and BHP), the team is excited about the potential of this same style of mineralization identified at surface within the eastern portion of our claim.

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Bold Ventures Announces Prospecting and Sampling Results and Mobilizes Crew to Burchell Gold and Copper Project

Bold Ventures Announces Prospecting and Sampling Results and Mobilizes Crew to Burchell Gold and Copper Project

Bold Ventures Inc. (TSXV: BOL,OTC:BVLDF) (the "Company" or "Bold") is pleased to announce the results of a prospecting and sampling program on its Burchell Gold and Copper Property (the "Property"), located within the Shebandowan Greenstone Belt, approximately 100 km west of Thunder Bay, Ontario. 209 grab samples and 42 channel samples were collected in total. The goal of this phase of work was preparation for a mechanical stripping, sampling and geological mapping program at the 111 Zone gold showing and surroundings. A crew has been mobilized for the mechanical stripping program which will commence immediately.

Highlights from the program include:

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Vertex Minerals

Vertex Minerals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×