Galena Mining

Galena Successfully Raises $17 Million

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce it has accepted binding commitments for a placement of 136,000,000 new shares at an issue price of $0.125 per share (“Placement Shares”), to raise $17 million before costs (“Placement”).


HIGHLIGHTS

  • Placement was well oversubscribed
  • Strong support from existing key stakeholders:
    • Existing largest strategic investor, Tim Roberts subscribed for ~$4.4M
    • Project financing debt provider, Taurus subscribed for ~$3.8M
    • Directors subscribed for ~$0.6M
  • Galena to use placement proceeds to provide Abra a funding buffer during the critical initial commissioning and ramp-up stages of the project
  • Abra remains on-target for Q1 2023 production and for total Project capital expenditure to be on budget as per regular monthly updates
Managing Director, Tony James commented, “With first concentrate production coming in early 2023, we felt it critical to ensure our Abra Project has an adequate funding buffer to deal with any unforeseen circumstances during the commissioning and ramp- up phase of the mine. It’s very pleasing to see the ongoing strong support from our key stakeholders who continue to support us in the development of our world-class lead- silver mine.”

The Placement was significantly oversubscribed and well supported mainly by existing stakeholders. The Company’s largest shareholder and strategic investor Mr Timothy Andrew Roberts, subscribed for 35,318,665 Placement Shares for ~A$4.41 million.

Taurus Mining Finance Fund No 2 LP (“Taurus”), the provider of the Taurus Debt Facilities to the Abra Base Metals Mine and a key stakeholder in the ongoing success of the Project, subscribed for 30,007,862 Placement Shares for ~A$3,75 million (see Galena ASX announcements of 12 November 2020 and 15 June 2021 for more information on the Taurus Debt Facilities).

The Company’s Directors subscribed for 4,880,000 Placement shares for ~A$0.61 million, subject to shareholder approval.

Proceeds from the Placement (net of expenses) will be used to provide Abra Mining Pty. Ltd. (“AMPL”, the Abra Project joint-venture entity) a temporary unsecured reserve facility (“URF”). The URF will be $30 million, contributed $18 million by Galena and $12 million by the Company’s joint-venture partner Toho Zinc Co., Ltd. (“Toho Zinc”). The URF will be made available during the critical commissioning and initial ramp-up stages of the Abra Base Metals Mine (“Abra” or the “Project”), up until the Project Completion tests are satisfied under the Taurus Debt Facilities (anticipated to be 2H CY2023). Its purpose will be to provide a working capital and cost buffer for AMPL to draw in the event of unforeseen circumstances and costs such as weather-related road or port closures or other events. Any drawn amounts will become unsecured shareholder loans to AMPL whilst undrawn amounts will be returned to each of Galena and Toho in their respective 60:40 share.

Euroz Hartleys Limited and Petra Capital Pty Ltd acted as Joint Lead Managers and Joint Bookrunners to the Placement and will receive 6.0% capital raising fees on funds raised.

FURTHER PLACEMENT DETAILS

71,400,000 of the shares issued under the Placement will fall within the Company’s 15% placement capacity under ASX Listing Rule 7.1, with settlement scheduled to occur on Tuesday, 2 August 2022. The remaining 64,600,000 shares to be issued under the Placement are subject to shareholder approval with the general meeting anticipated to be held mid- September. All subscriptions by the Company’s Directors require shareholder approval and will be included in the second tranche of the Placement Shares for approval at the mid- September general meeting.

The Board of Directors of Galena authorised this announcement for release to the market.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (seeASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Rapid Successfully Undertakes $10.5M Capital Raising to Fund Acquisition of the Webbs and Conrads NSW Silver Projects

Rapid Successfully Undertakes $10.5M Capital Raising to Fund Acquisition of the Webbs and Conrads NSW Silver Projects

Rapid Critical Metals Limited (‘Rapid,’ ‘RCM’ or ‘Company’) is pleased to announce that the Company has received firm commitments from institutional, sophisticated and professional investors for the placement of 437,500,000New Fully Paid Ordinary Shares (New Shares) at an issue price of A$0.024 per new share (post 12-for-1 consolidation) to raise gross proceeds of A$10.5 million (Placement). The Placement comprises two tranches:

Keep reading...Show less
Silver bars with rising chart, "Weekly Editor's Picks" text overlay.

Editor's Picks: Silver Price Hits 13 Year High, Gold Takes a Breather

Gold was on the decline this week, closing just below US$3,370 per ounce, after tensions in the Middle East pushed it past the US$3,430 level toward the end of last week.

All eyes were on the US Federal Reserve, which in a widely expected move left interest rates unchanged on Wednesday (June 18) following its two day meeting. The central bank cut rates in December 2024, but has kept them steady for its last four gatherings.

US President Donald Trump wasn't pleased, calling Powell "too late" in a Thursday (June 19) post on Truth Social. While speculation that Trump will fire Powell has died down, the president did recently say he intends to announce his next pick for the Fed leader position "very soon."

Keep reading...Show less
Silver metallic dice spelling "ETF" against stock chart background.

10 Silver ETFs for Every Investing Style in 2025

Investors looking for exposure to the silver price and silver-mining companies should consider silver exchange-traded funds (ETFs).

Spurred by moves in the gold market, safe-haven buying as well as increasing demand from industrial sectors, silver saw strong price movements in the first half of 2025, breaching US$37 per ounce for the first time since 2011.

While silver has often been seen as a more approachable precious metal owing to its lower per ounce price, its performance has lagged gains seen in the gold price over the past few years. However, silver stole some of the spotlight in the second quarter of 2025 as it saw significant gains on the back of geopolitical tension and economic uncertainty from the US trade and tariff policy.

Keep reading...Show less
Silver bars and US$100 bills with a rising chart overlay.

Silver Price Surges to US$37, Highest Value Since May 2011

After being overshadowed by gold early in the year, silver has been in the spotlight in recent weeks.

The white metal broke through the US$37 per ounce mark on Tuesday (June 17) for the first time since May 2011.

Recent economic and geopolitical events have raised analysts’ expectations of a September rate cut from the US Federal Reserve, helping to fuel safe-haven buying of silver and gold.

Keep reading...Show less

Latest Press Releases

Related News

×