Galena Mining

Activities Report For The Quarter Ended 30 June 2023

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 June 2023 (the “Quarter”), primarily focused on the ongoing production ramp-up of both the underground mine and the processing plant to achieve steady-state production in the second half of 2023, at its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS

  • Strong recovery achieved with May and June physicals following limited activities in April due to rainfall events. Ore mined of 194,644t at 5.4% Pb grade and 16.9g/t Ag grade and processed 190,258t at 5.1% Pb grade and 19.0g/t Ag grade for the Quarter.
  • Second and third in-specification lead concentrate shipments of ~5kt each completed in the Quarter, doubling revenue from the previous quarter to ~A$20.4 million.
  • July month to date on track to achieve first positive monthly operating cash flows with over 90% of the next ~9-10kt concentrate shipment produced and committed shipment set for loading between 28 July and 4 August.
  • Underground development achieved 1,583m advance during the Quarter with the decline reaching 1,234mRL (312m vertically below the surface). Underground stope production achieved 81,592t at 6.3% Pb grade. Pb grade is slowly improving and will continue to do so in the coming months as new work areas are established and the ratio of stoping ore to development ore increases to required production levels.
  • Cash balance at Quarter-end of A$19.3 million.
  • Galena completed an oversubscribed placement to provide additional working capital funding for the Abra ramp-up.
  • September quarter mining plans set to achieve over 2,000m development and over 250,000t stope production expecting to process over 300,000t of ore as next quarter ramp-up milestones. Targeting ~25-30kt of lead concentrate shipments expected to generate positive operating cash flows.

Managing Director, Tony James commented, “We made a strong recovery from no production in April to set new project highs in both May and June, and we expect to achieve first positive operating cash flows in July. The plant is showing its capacity to process everything put in front of it so far and the focus remains on increasing mine production levels. The key to the mine reaching the levels required is good planning and execution. With the mine plans at 90% grade control status through to January 2024 we see the pathway well laid out to achieve our targets. Some very strong technical work has been completed to increase our confidence in hitting our targets.”

ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena and 40% owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment achieved in March 2023.

Review of operations

Notes:

1. Total Recordable Injury Frequency Rate (“TRIFR”) and Notifiable Incident Frequency Rate (“NIFR”) are the 12-month moving average at the end of each quarter calculated per million work hours.

2. Concentrate sales and average lead price received initially based on provisional invoices and subsequently updated with final invoices, including final assays and quotational period adjustments.

3. Payable lead and silver based on 95% metal payability subject to standard deductions (i.e., 3 units for lead and 50g/t for silver).

4. C1 costs include mining costs, processing costs, site general and administration costs, transport, logistics and shipping costs, and treatment and refining charges, adjusted for inventory movements and net of silver by-product credits.

5. All-in sustaining costs include C1 Costs plus royalties, corporate general and administration costs, sustaining capital and capitalised mine development costs. All-in sustaining costs exclude growth capital and exploration costs.

6. Abra Project construction works were completed by the end of the December 2022 quarter (see Galena ASX announcements of 10 January 2023 and 13 January 2023).

During the Quarter, new quarter high mining and processing production levels were achieved. This achievement also takes into account the limited activities in April 2023 due to the rainfall issues affecting access to the Abra mine site.

In June, a mine development record was set with 646m of lateral and vertical development achieved during the month. A third Jumbo commenced in the mine in June with the aim of increasing the mine’s monthly development rates to 800m per month during the September quarter.

The mine delivered 194,644t (April: 31,915t, May: 81,014t and June: 81,715t) at 5.4% Pb grade to the plant during the Quarter, including stope production ore of 81,592t at 6.3% Pb grade. The higher development ore during the Quarter is consistent with the ramp-up of mine production as new stoping areas are established. In general, mine production in the Quarter was also affected by congestion in the available work areas, production delays associated with upgrading secondary ventilation networks and loader availability. These impediments were continually rectified during the quarter.

The plant effectively processed all the ore delivered from the mine during the Quarter with 190,258t processed (April: Nil, May: 102,719t and June: 87,539t). 12,468t of concentrate was produced containing 8,070t Pb and 63,122oz Ag. Plant availability in May was 99% and in June 86%. A flotation blower (compressor) breakdown caused the lower availability in June. The plant was able to operate consistently at the 150dmt/hr level during the Quarter.

The mine call grade for ore processed during the Quarter was estimated at 5.4% Pb, which is approximately 0.3% Pb higher than the reconciled processing grade of 5.1% Pb.

Considerable technical improvements were achieved during the Quarter with detailed resource modelling and mine planning work completed. A new Mineral Resource Estimate (“MRE”) is expected to be finalised in the coming weeks which will include all the recent underground drilling and revised geological modelling. This work will lead into a new Ore Reserve estimate and 2024 budget completion in the December quarter. Three month rolling mine plans have been established and the mine planning for the remainder of 2023 is well advanced with 90% of that plan built on grade control drilling down to a 12.5x12.5m spacing.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Two silver bars weighing 1000 grams in front of price charts.

Should You Invest in Silver Bullion?

Investing in silver bullion has pros and cons, and what’s right for one investor may not work for another.

Interest in the silver market tends to flourish whenever the silver price increases, with investors beginning to wonder if it is the right time to add physical silver to their investment portfolios. While silver can be volatile, the precious metal is also seen as a safe-haven asset, similar to its sister metal gold. Safe-haven investments can offer protection in times of uncertainty, and with tensions running high, they could be a good choice for those looking to preserve their wealth in difficult times.

With those factors in mind, let’s look at the pros and cons of buying silver bullion.

Keep reading...Show less

Pan American Silver Announces the Sale of La Arena for US$245 Million Cash Upfront and US$50 Million Contingent Payment

  • retains a 1.5% gold net smelter return royalty for the La Arena II project

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) (" Pan American ") announces that it has agreed to sell its 100% interest in La Arena S.A. ("La Arena"), which owns the La Arena gold mine as well as the La Arena II project in Peru, to Jinteng (Singapore) Mining Pte. Ltd., a subsidiary of Zijin Mining Group Co., Ltd. (collectively, "Zijin") for US$245 million cash upfront and a US$50 million contingent payment.

"With the sale of La Arena, we continue to deliver on our strategy to optimize our portfolio, following the Yamana transaction, while maintaining future upside through the retention of royalties," said Michael Steinmann, President and Chief Executive Officer of Pan American. "Proceeds from the transaction will further strengthen our financial position and allow us to deliver on our capital allocation priorities of investing in high-quality assets, debt reduction and returning capital to our shareholders."

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Silver bar and metal.

Top 5 Canadian Silver Stocks of 2024

Silver demand is forecast to reach its second highest level ever in 2024 at 1.2 billion ounces, driven by industrial market segments such as photovoltaics and electric vehicles.

This high demand is coming alongside flat production growth, and is creating a situation that would seemingly be ripe for a price breakout. However, the first months of the year saw the metal trade in the US$22 to US$24 per ounce range.

The beginning of March brought a shift in the market, and silver started to make gains. Following its sister metal gold higher, silver hit a quarterly high of US$25.71 on March 20 before reaching an 11 year high of US$28.85 on April 14.

Keep reading...Show less

MAG Announces First Quarter 2024 Production From Juanicipio

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG" or "MAG Silver") reports production from Juanicipio (56% 44% Fresnillo plc ("Fresnillo") and MAG, respectively) for the first quarter ("Q1") ended March 31, 2024.

Q1 Highlights

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bars and coins.

Silver Price Update: Q1 2024 in Review

2023 was a relatively lackluster year, silver largely traded on volatility between US$22 and US$25 per ounce.

The white metal started 2024 with less volatility and remained rangebound for the first eight weeks. Silver dropped to US$22.08 per ounce on January 21, marking its quarterly low.

Silver started seeing gains in March with the expectation that the US Federal Reserve was getting closer to lowering interest rates. Improving sentiment gave the precious metals markets momentum, causing silver to reach its quarterly high of US$25.62 on March 20, before continuing on to an 11 year high of US$29.26 on April 12.

Keep reading...Show less

Endeavour Silver Provides Q1 2024 Construction Progress Update on Terronera; Construction Progress Reaches 53% Completion

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q1 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos . All dollar ($) references in this news release are United States dollars.

The Terronera project made significant progress in the first quarter, as concrete work was nearly complete on the Upper Plant Platform and erection of structural steel advanced for areas including crushing, coarse-ore storage, grinding, flotation, and thickening. Mechanical installation of major equipment continued to advance on schedule and the project remains on track for commissioning in Q4 2024.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×