Galena Mining

Activities Report for Quarter Ended 31 March 2022

GALENA MINING LTDLTD. (“Galena” or the “Company”) ( ASX: G1A) reports on its activities for the quarter ending 31 March 2022 (the “Quarter”), primarily focused on construction of its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project 58% complete at end of the March Quarter (19% of Abra construction works were completed during the March Quarter). Project focus remains on underground access to the Abra orebody and completion of the processing plant and power station.
  • Underground development achieved 694m advance during the Quarter remaining ahead of schedule with the decline reaching 1,395mRL. The decline is 82m above the orebody and 155m below the surface.
  • Overall processing plant construction has reached 61% complete. Plant engineering and drafting work is 95% complete and site construction work is 35% complete.
  • Contracts have been awarded for the remaining non-processing surface infrastructure work representing only 10% of the remaining project capex of $97.8M.
  • Power supply company Contract Power have commenced site works associated with the Abra power station (build, own, operate contract).
  • US$35M additional debt drawdown was completed under the Taurus Debt Facilities, leaving US$45M remaining undrawn.
  • Cash balance at Quarter-end A$60.0M.

ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL”), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.

Project construction / development

During the Quarter Abra Project construction works continued, passing the half-way to completion mark as the Quarter progressed.


Abra construction works conducted during the Quarter were comprised of site civil and earthworks, underground mine development, processing plant construction and ongoing front- end engineering design and procurement, including:

  • Underground mining – During the Quarter, underground development continued to progress ahead of schedule, with a further 694 metres of development being completed. As at Quarter-end, total development reached 1,134 metres consisting of 885 metres of decline development and 249 metres of other lateral development. The decline reached 1,395mRL, 82 metres above the Abra orebody and 155 metres below the surface. During the Quarter the first raise bore hole (4.5m) was successfully completed for development of the mine’s primary ventilation infrastructure. The ventilation shaft is one of 3 surface holes that will be completed to provide underground ventilation as the mine progresses.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD. , licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Silver nuggets.

Endeavour Silver Hits Updated 2024 Production Guidance After Disruption at Guanaceví Mine

Endeavour Silver (TSX:EDR,NYSE:EXK) shared its 2024 production results, reporting output for the period of 4,471,824 ounces of silver and 39,047 ounces of gold, or 7.6 million silver equivalent ounces.

The company met its updated annual production guidance, which it adjusted following operational challenges.

"After operating at reduced capacity due to the Guanaceví trunnion failure in August, and subsequently resuming full capacity in December, we are satisfied with our production performance in Q4 and producing at the top range of our updated production guidance," CEO Dan Dickson said in Thursday's (January 9) press release.

Keep reading...Show less
Stack of silver bars.

Royalty Investments: A Strategic Approach to Silver Exposure

In the dynamic world of precious metals investing, royalties have emerged as a compelling strategy, offering unique advantages over traditional mining or commodity investments.

This approach, particularly in the silver sector, provides investors with an opportunity to capitalize on the potential of precious metals while mitigating many of the risks associated with direct mining operations.

Royalty and streaming agreements form the backbone of this investment model in the precious metals industry. These arrangements allow royalty companies to generate revenue from mining projects without directly engaging in the operational aspects of mineral extraction. Unlike typical mining companies, royalty firms provide upfront capital to miners in exchange for a percentage of future production or revenue, effectively creating a win-win situation for both parties.

Keep reading...Show less
Boab Metals Limited

Boab Metals Limited


Keep reading...Show less

Endeavour Silver Produces 4,471,824 Oz Silver and 39,047 Oz Gold in 2024; Improved Fourth Quarter Production Delivers on Updated Annual Guidance

 Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) reports full year 2024 production of 4,471,824 silver ounces ("oz") and 39,047 gold oz, for silver equivalent ( 1) ("AgEq") production of 7.6 million oz. Fourth quarter production was 824,529 silver oz and 9,075 gold oz for 1.6 million AgEq oz.

"After operating at reduced capacity due to the Guanaceví trunnion failure in August, and subsequently resuming full capacity in December, we are satisfied with our production performance in Q4 and producing at the top range of our updated production guidance," said Dan Dickson, Chief Executive Officer. "The team demonstrated exceptional diligence and commitment throughout the 15 week recovery period, ensuring the timely fabrication and installation of the trunnion while maintaining seamless operations and bringing Guanaceví's plant back to its historical levels of 1,200 tonnes per day."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Endeavour Silver Produces 4,471,824 Oz Silver and 39,047 Oz Gold in 2024; Improved Fourth Quarter Production Delivers on Updated Annual Guidance

 Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) reports full year 2024 production of 4,471,824 silver ounces ("oz") and 39,047 gold oz, for silver equivalent ( 1) ("AgEq") production of 7.6 million oz. Fourth quarter production was 824,529 silver oz and 9,075 gold oz for 1.6 million AgEq oz.

"After operating at reduced capacity due to the Guanaceví trunnion failure in August, and subsequently resuming full capacity in December, we are satisfied with our production performance in Q4 and producing at the top range of our updated production guidance," said Dan Dickson, Chief Executive Officer. "The team demonstrated exceptional diligence and commitment throughout the 15 week recovery period, ensuring the timely fabrication and installation of the trunnion while maintaining seamless operations and bringing Guanaceví's plant back to its historical levels of 1,200 tonnes per day."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×