Galena Mining

Activities Report for Quarter Ended 31 March 2022

GALENA MINING LTDLTD. (“Galena” or the “Company”) ( ASX: G1A) reports on its activities for the quarter ending 31 March 2022 (the “Quarter”), primarily focused on construction of its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project 58% complete at end of the March Quarter (19% of Abra construction works were completed during the March Quarter). Project focus remains on underground access to the Abra orebody and completion of the processing plant and power station.
  • Underground development achieved 694m advance during the Quarter remaining ahead of schedule with the decline reaching 1,395mRL. The decline is 82m above the orebody and 155m below the surface.
  • Overall processing plant construction has reached 61% complete. Plant engineering and drafting work is 95% complete and site construction work is 35% complete.
  • Contracts have been awarded for the remaining non-processing surface infrastructure work representing only 10% of the remaining project capex of $97.8M.
  • Power supply company Contract Power have commenced site works associated with the Abra power station (build, own, operate contract).
  • US$35M additional debt drawdown was completed under the Taurus Debt Facilities, leaving US$45M remaining undrawn.
  • Cash balance at Quarter-end A$60.0M.

ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL”), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.

Project construction / development

During the Quarter Abra Project construction works continued, passing the half-way to completion mark as the Quarter progressed.


Abra construction works conducted during the Quarter were comprised of site civil and earthworks, underground mine development, processing plant construction and ongoing front- end engineering design and procurement, including:

  • Underground mining – During the Quarter, underground development continued to progress ahead of schedule, with a further 694 metres of development being completed. As at Quarter-end, total development reached 1,134 metres consisting of 885 metres of decline development and 249 metres of other lateral development. The decline reached 1,395mRL, 82 metres above the Abra orebody and 155 metres below the surface. During the Quarter the first raise bore hole (4.5m) was successfully completed for development of the mine’s primary ventilation infrastructure. The ventilation shaft is one of 3 surface holes that will be completed to provide underground ventilation as the mine progresses.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD. , licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining Director & CEO Tony James

Galena Mining

Galena Mining CEO Tony James: On Track for Commercial Production in 2023youtu.be

Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Silver bars in a pile on the left on top of a blue grid with a stock price chart in white.

How to Invest in Silver (Updated 2024)

How to best invest in silver is a thought on many investors’ minds.

Silver has long been an attractive vehicle not only for storing wealth, but for generating it too. Silver bugs rave about the growth opportunities to be had in a price rally.

However, what goes up must come down, and the silver market is prone to deep dives. This has much to do with the silver’s dual role as both a precious and industrial metal.

Keep reading...Show less
Silver metallic dice spelling "ETF" against stock chart background.

7 Biggest Silver ETFs in 2024

Spurred by moves in the gold market as well as increasing demand from industrial sectors, silver saw strong price movements in the first half of 2024, breaching US$30 per ounce for the first time in more than a decade.

While silver has often been seen as a more approachable precious metal owing to its lower per ounce price, its performance has lagged gains seen in the gold price over the past few years. However, silver did join gold in its rally earlier this year, climbing above US$32 in May, and pulled above US$30 again in July.

Like gold, investors can gain exposure to silver in several ways that each offer their own pros and cons, along with differing costs and risks. For example, investors can purchase physical silver bars or coins, or invest in silver futures.

Keep reading...Show less

Pan American Silver Reports Mineral Reserves and Mineral Resources as at June 30, 2024

  • Significant increase in estimated mineral resources for the La Colorada Skarn project
  • Mineral reserve replacement and 1.2 million ounce increase in gold inferred mineral resources at Jacobina demonstrates exploration potential

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") reports its estimated mineral reserves and mineral resources as at June 30, 2024. Proven and probable mineral reserves are estimated to contain approximately 468.0 million ounces of silver and 6.9 million ounces of gold. Measured and indicated ("M&I") mineral resources (excluding proven and probable ("P&P") reserves) are estimated to total approximately 1,148.0 million ounces of silver and 15.5 million ounces of gold. Inferred mineral resources are estimated to total approximately 366.0 million ounces of silver and 9.4 million ounces of gold. The updated mineral reserves and mineral resources estimates are reported net of the sales of the MARA, Agua de la Falda and Morococha properties, as announced in the Company's news release dated July 31, 2023. The divestment of these non-core, non-producing assets is largely responsible for a decrease in mineral reserves and mineral resources compared to 2023.

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Raw silver.

Andean Boosts Cerro Bayo's Silver Equivalent Ounces by 80 Percent in New Resource Estimate

Andean Silver (ASX:ASL) published an updated resource estimate for its Chile-based Cerro Bayo silver-gold project on Tuesday (September 10), saying silver equivalent ounces have increased by 80 percent.

The resource now stands at 8.3 million tonnes at 342 grams per tonne silver equivalent, which equates to 91 million silver equivalent ounces. In addition to the 80 percent boost in silver equivalent ounces, that's a 64 percent increase in tonnes compared to the previous estimate, which was published in March of this year.

“The updated Resource establishes Cerro Bayo as an outstanding silver asset with genuine scale and high grades,” said CEO Tim Laneyrie, noting that Andean has nearly quadrupled the asset's resource since acquiring it.

Keep reading...Show less

First Majestic Announces Share Repurchase Program

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") announces that the Toronto Stock Exchange ("TSX") has accepted for filing First Majestic's Notice of Intention to Make a Normal Course Issuer Bid (the "Share Repurchase Program") to be transacted through the facilities of the TSX andor through Canadian alternative trading systems.

Pursuant to the NCIB, First Majestic may, during the 12-month period commencing September 12, 2024, and ending on or before September 11, 2025, purchase up to 10,000,000 of its common shares ("Shares"), being approximately 3.32% of the 301,616,350 issued and outstanding Shares as of September 4, 2024. All purchases under the Share Repurchase Program will be made at prevailing market prices.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

BRODSKY & SMITH SHAREHOLDER UPDATE: Notifying Investors of the Following Investigations: Iteris, Inc. , Forza X1, Inc. , Titan Pharmaceuticals, Inc. , Gatos Silver, Inc.

Brodsky & Smith reminds investors of the following investigations. If you own shares and wish to discuss the investigation, contact Jason Brodsky ( jbrodsky@brodskysmith.com ) or Marc Ackerman ( mackerman@brodskysmith.com ) at 855-576-4847. There is no cost or financial obligation to you.

Iteris, Inc. (Nasdaq - ITI)

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×