Galena Mining

Activities Report for Quarter Ended 31 March 2022

GALENA MINING LTDLTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ending 31 March 2022 (the “Quarter”), primarily focused on construction of its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project 58% complete at end of the March Quarter (19% of Abra construction works were completed during the March Quarter). Project focus remains on underground access to the Abra orebody and completion of the processing plant and power station.
  • Underground development achieved 694m advance during the Quarter remaining ahead of schedule with the decline reaching 1,395mRL. The decline is 82m above the orebody and 155m below the surface.
  • Overall processing plant construction has reached 61% complete. Plant engineering and drafting work is 95% complete and site construction work is 35% complete.
  • Contracts have been awarded for the remaining non-processing surface infrastructure work representing only 10% of the remaining project capex of $97.8M.
  • Power supply company Contract Power have commenced site works associated with the Abra power station (build, own, operate contract).
  • US$35M additional debt drawdown was completed under the Taurus Debt Facilities, leaving US$45M remaining undrawn.
  • Cash balance at Quarter-end A$60.0M.

ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL”), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.

Project construction / development

During the Quarter Abra Project construction works continued, passing the half-way to completion mark as the Quarter progressed.


Abra construction works conducted during the Quarter were comprised of site civil and earthworks, underground mine development, processing plant construction and ongoing front- end engineering design and procurement, including:

  • Underground mining – During the Quarter, underground development continued to progress ahead of schedule, with a further 694 metres of development being completed. As at Quarter-end, total development reached 1,134 metres consisting of 885 metres of decline development and 249 metres of other lateral development. The decline reached 1,395mRL, 82 metres above the Abra orebody and 155 metres below the surface. During the Quarter the first raise bore hole (4.5m) was successfully completed for development of the mine’s primary ventilation infrastructure. The ventilation shaft is one of 3 surface holes that will be completed to provide underground ventilation as the mine progresses.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD. , licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)

Galena Mining

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion... Keep Reading...
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November... Keep Reading...
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station... Keep Reading...
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western... Keep Reading...
Silver bars on shiny metallic surface.

Silver Stocks: 5 Biggest Companies in 2025

Silver mining companies are being supported by a silver price bull run in 2025. After climbing through 2025, silver broke its all-time high set in 1980 this October, reaching a new high of US$54.47 per ounce on October 17.The factors driving the metal's rise remain, most notably tightening... Keep Reading...
Closeup of a handshake over a desk with charts and a notebook.

Americas Gold & Silver to Acquire Crescent Silver in US$65 Million Deal

Mid-tier precious metals producer Americas Gold and Silver (TSX:USA,NYSEAMERICAN:USAS) continues to grow its North American footprint with its intended acquisition of privately owned Crescent Silver. The two companies inked a US$65 million binding purchase agreement on Thursday (November 13). It... Keep Reading...
Stacks of shiny silver bars labeled "FINE SILVER" and "999" purity.

ASX Silver Stocks: 5 Biggest Companies in 2025

The silver price rose to new highs this year, breaking above its previous record set in 1980, as strong safe-haven demand for precious metals aligned with tightening supply.Over the years, silver has seen a broadening of industrial use, particularly in electronics and for the energy transition.... Keep Reading...
Chris Marcus, silver bars.

Chris Marcus: Silver Supply Crunch Not Over, Price Path Clear Long Term

Chris Marcus, founder of Arcadia Economics, shares his thoughts on silver and gold. While it's impossible to know exactly how precious metals prices will move in the short term, he's confident they will maintain an upward trajectory in the long term.Don't forget to follow us @INN_Resource for... Keep Reading...
Silver bars in front of newspaper showing high price performance.

What Was the Highest Price for Silver?

Like its sister metal gold, silver has been attracting renewed attention as a safe-haven asset due to high levels of uncertainty. Although silver continues to exhibit its hallmark volatility, a silver bull market is well underway in 2025. Experts are optimistic about the future, and as the... Keep Reading...
Steve Penny, gold and silver bars.

Steve Penny: Silver, Gold, Uranium — Price Targets and My Strategy

Steve Penny, founder of SilverChartist.com, explains why he currently has a bullish outlook for gold, silver and platinum, as well as uranium. “The reaction to the next deflationary impulse is what I believe ultimately sends silver up towards triple digits, gold up towards north of US$10,000... Keep Reading...

Latest Press Releases

Related News