Galena Mining Limited

Abra Initial Production Guidance

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to provide initial production guidance for its 60% owned Abra Base Metals Mine (“Abra” or the “Project”) having achieved the construction milestone of 75% complete. The guidance for the CY2023 ramp-up year and future life of mine averages are based on the most recently updated mine plan incorporating updated mine designs and the latest cost information.


HIGHLIGHTS

  • Abra Project construction is now 75% complete – Galena confirms first concentrate production remains on-target for Q1 2023 and provides initial production targets based on latest mine plan
  • CY2023 mill throughput expected to be 0.8-1.0Mtpa resulting in ramp-up year lead production of 53-68kt
  • Following ramp-up, life of mine average annual production expected to average 93,000 tonnes of lead and 553,000 ounces of silver, with lead ‘C1’ direct cash cost of US$0.50/lb
  • Plant processing throughput and mine plan increased to 1.3Mtpa in the current mine plan (vs. 1.2Mtpa in 2019 Feasibility Study)1
Managing Director, Tony James commented, “With first concentrate production on target for the March 2023 quarter, we provide this update on near-term and life of mine plan and targets. During the construction period of the project, we have worked very closely with our partner Toho Zinc and our key service providers to reach the 75% build mark. For the remainder of 2022 we plan to safely complete the mine construction and commission Abra as a world-class lead-silver mine.”

The guidance provided today is based on the knowledge and confidence gained from additional drilling, Mineral Resource estimation, and advancing construction at Abra, and preparation for commissioning ahead of a planned safe and efficient start-up.

Grade control drilling commenced in June 2022 and ongoing drilling and evaluation over the next 3 months will likely offer further opportunity for additional optimisation of the mine plan.

The forecast life of mine production now averages 93,000tpa lead metal production and 553,000ozpa silver. An 8% increase in mine and mill production is offset by a 6% reduction in lead grade to produce slightly less metal in direct comparison to the 2019 Feasibility Study (“FS”)1. A suitable ramp up profile has been adopted for the CY2023 prior to reaching steady state production which is anticipated to occur in the December quarter 2023.

Table 1 below outlines the current expected production forecast for CY2023 and the Updated Life of Mine outcomes in direct comparison the FS completed in 2019.

Table Notes
1. Key outcomes and metrics shown reference 100% of Project. Abra Project is owned 60% by Galena & 40% by Toho Zinc.
2. Includes a by-product credit for net silver revenue of US$0.04/lb (A$0.06/lb).
3. Current lead metal price and exchange rate.

Table 1 - Updated Abra key operating and financial metrics.

The Abra mine construction is progressing as planned. Progress reached 73% complete as of 30 June 2022 and has since past 75% complete. Processing plant construction activities reached 79% complete with concrete civils passing 95% complete and structural steel passing 42% complete. During June and early July several key equipment items arrived on site and the only remaining items coming from overseas are the flotation cells and the regrind mill. These items are currently in shipping with the flotation cells expected to arrive on 12 August and the regrind mill expected to arrive on 1 September. Figures 1 to 4 included in this announcement provide additional photographs of the Abra work completed to date.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)

Galena Mining

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion... Keep Reading...
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November... Keep Reading...
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station... Keep Reading...
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western... Keep Reading...
Stock market graphic showing "Silver" with green and red arrows.

Silver’s 2025 Rally Lifts Miners to Record Q3 Results

The rally in silver that began earlier this year has translated into a wave of strong third quarter results for leading industry firms. The silver market erupted in 2025, breaking the US$30 barrier at the start of the year before accelerating into the spring with a February 20 print of US$32.94... Keep Reading...
Stacks of silver bars and coins on financial charts.

Sun Silver Begins Trading on OTCQX as Part of US Expansion

Sun Silver (ASX:SS1) will commence trading on the US OTCQX market following strong US investor interest, the company said earlier this week.The OTCQX trading allows US investors to trade the company’s shares in US dollars and during the US market hours.According to Sun Silver, US investor... Keep Reading...
Prince Silver (CSE:PRNC)

Prince Silver Corp Announces Closing of First Tranche of Private Placement Financing

Prince Silver Corp. ("Prince" or the "Company") (CSE:PRNC)(OTCQB:PRNCF) is pleased to announce that further to its news release dated September 24, 2025, the Company has closed the first tranche (the "First Tranche") of its previously announced non-brokered private placement financing for gross... Keep Reading...
Ed Steer, silver bars.

Ed Steer: Silver Rally Now Unstoppable, Price to Hit Triple Digits

Ed Steer of Ed Steer's Gold and Silver Digest shares his thoughts on silver's run past US$50 per ounce, saying that in his view the bull market is just getting started. "One way or another we're going to run into a supply/demand brick wall, and when that day happens we could see triple-digit... Keep Reading...
Gianni Kovacevic, lithium-ion battery.

Gianni Kovacevic: Silver, Oil to Break US$100, but This is the Real Speculation

Investor and author Gianni Kovacevic discusses silver's price pullback, saying that in the long term he sees the white metal reaching triple digits. He expects oil prices to reach that level too, but emphasized that he sees lithium as the truly contrarian play for the rest of 2025 and into next... Keep Reading...

Latest Press Releases

Related News