Ur-Energy Provides Operations, Construction and 2024 Guidance Updates

Ur-Energy Inc. (NYSE American:URG)(TSX:URE) (the "Company" or "Ur-Energy") provides the following updates on Lost Creek Mine operations and Shirley Basin construction, as well as updated production guidance

Lost Creek Production Operations
Ramp up continues at Lost Creek with five header houses coming online in 2024. Most recently, Header House (HH) 2-10 came online in mid-August, as scheduled, and HH2-11 is expected to come online this month. Average production solution headgrade in August was 67.1 mg/L. Our fifth shipment of yellowcake this year arrived at the conversion facility on September 11, and we are planning our next shipment of dried product for late September. Deep disposal well #5 was recently placed into operation and is satisfying wastewater needs.

We now have 15 drill rigs on site with additional drill rigs pending (not including three rigs at our Shirley Basin Project). As we are able to grow the space between wellfield construction and drilling, we plan to ultimately redirect some of the drill rigs to exploration projects within the Great Divide Basin with the goal of replacing mined pounds with new uranium resources.

We continue to focus on employee training and retention as these are currently our most notable challenges because many of our employees have little experience with uranium production. Our quality workforce is, however, stabilizing.

Every month of 2024, except for June, we have steadily increased the pounds captured in the processing plant. The Lost Creek wellfield is performing as expected and the issues which have slowed ramp-up are temporary in nature. While ramp up continues to move in the right direction, it has been slower than anticipated largely due to manpower matters. Therefore, we are revising our 2024 production guidance to a range of 325,000 to 475,000 pounds of U3O8 captured. We expect to satisfy our contractual commitments to our customers with Lost Creek production and available alternatives.

Shirley Basin Development
Installation of the monitor wells for the first mine unit at Shirley Basin is on schedule with 120 of the 120 planned wells piloted and cased. We expect to finalize well completions in the coming days. We currently have three drill rigs working at Shirley Basin, which will redeploy to Lost Creek when the completion work concludes.

Plans are being finalized to collect baseline water quality and perform hydrologic aquifer tests this fall. Power supply to the satellite plant construction area has been completed and the line is energized. The access road upgrades are complete, and the septic system is being installed. Construction of fifteen IX columns is on target with delivery expected in Q3 2025. Our purchasing program for equipment continues, with an emphasis on continually reviewing the timing for long lead-time purchases such as electronic components.

We continue to expect construction at Shirley Basin to be complete in late 2025 with a pre-operations inspection by the State of Wyoming following soon after.

About Ur-Energy
Ur-Energy is a uranium mining company operating the Lost Creek in situ recovery uranium facility in south-central Wyoming. We have produced and packaged approximately 2.7 million pounds U3O8 from Lost Creek since the commencement of operations. Ur-Energy has all major permits and authorizations to begin construction at Shirley Basin, the Company's second in situ recovery uranium facility in Wyoming and is advancing Shirley Basin construction and development following the March 2024 ‘go' decision for the mine. We await the remaining regulatory authorization for the expansion of Lost Creek. Ur‑Energy is engaged in uranium mining, recovery and processing activities, including the acquisition, exploration, development, and operation of uranium mineral properties in the United States. The primary trading market for Ur‑Energy's common shares is on the NYSE American under the symbol "URG." Ur‑Energy's common shares also trade on the Toronto Stock Exchange under the symbol "URE." Ur-Energy's corporate office is in Littleton, Colorado and its registered office is in Ottawa, Ontario.

FOR FURTHER INFORMATION, PLEASE CONTACT
John W. Cash, Chairman, CEO & President
20-981-4588, ext. 303
John.Cash@Ur-Energy.com

Cautionary Note Regarding Forward-Looking Information
This release may contain "forward-looking statements" within the meaning of applicable securities laws regarding events or conditions that may occur in the future (e.g., the timing of upcoming shipments from Lost Creek; our ability to satisfy contractual commitments to our customers; our planned future use of drill rigs; 2024 Lost Creek production guidance; the timing and ability to complete the build out of Shirley Basin as currently projected). Forward-looking statements are based on current expectations that, while considered reasonable by management at this time, inherently involve a number of significant business, economic and competitive risks, uncertainties and contingencies. Generally, forward-looking statements can be identified by the use of forward-looking terminology such as "plans," "expects," "does not expect," "is expected," "is likely," "estimates," "intends," "anticipates," "does not anticipate," or "believes," or variations of the foregoing, or statements that certain actions, events or results "may," "could," "might" or "will be taken," "occur," "be achieved" or "have the potential to." All statements, other than statements of historical fact, are considered to be forward-looking statements. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements express or implied by the forward-looking statements. Factors that could cause actual results to differ materially from any forward-looking statements include, but are not limited to, capital and other costs varying significantly from estimates due to inflation or otherwise; staffing challenges; failure to establish estimated resources and reserves; the grade and recovery of ore which is mined varying from estimates; production rates, methods and amounts varying from estimates; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; supply chain constraints; changes in exchange rates; fluctuations in commodity prices; delays in development and other factors described in the public filings made by the Company at www.sedarplus.ca and www.sec.gov. Readers should not place undue reliance on forward-looking statements. The forward-looking statements contained herein are based on the beliefs, expectations and opinions of management as of the date hereof and Ur-Energy disclaims any intent or obligation to update them or revise them to reflect any change in circumstances or in management's beliefs, expectations or opinions that occur in the future.

SOURCE: Ur-Energy Inc.



View the original press release on accesswire.com

News Provided by ACCESSWIRE via QuoteMedia

URE:CA,URG
The Conversation (0)

Laramide Releases Final Results from 2024 Drill Campaign at Westmoreland; Updated Resource Estimate on Track for Q1 Delivery

Highlights:

  • Laramide's largest program ever with 106 holes completed
  • Multiple targets tested including infill and extensional drilling of known zones and greenfield targets in both Queensland and the Northern Territory
  • Consistent observation from results demonstrates the potential and scope for broad mineralisation styles enveloping narrow high-grade intercepts
  • The consistency and scalability underscore economic viability and reinforce Westmoreland's position as a potentially important future source of global uranium supply
  • Resource expansion potential is largely wide open with many follow-up targets warranting large-scale future exploration campaigns

Laramide Resources Ltd. ( "Laramide" or the "Company" ) (TSX: LAM) (ASX: LAM) (OTCQX: LMRXF), a uranium mine development and exploration company with globally significant projects in the United States Australia and Kazakhstan is pleased to report a summary of the 2024 drilling campaign completed at the Westmoreland Uranium Project in Queensland, Australia ( "Westmoreland" ). The 2024 drill program has concluded with successful results confirming the high-quality of the Westmoreland uranium deposit and supporting a Global Mineral Resource Estimate Update expected by the end of Q1 2025.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Cameco Announces 2024 Results; Strong Performance Across All Segments; Westinghouse Distribution; Strategy Centered on Marketing, Production, Financial Discipline Expected to Generate Full-Cycle Value; Positive Outlook for Nuclear Energy

Cameco( TSX: CCO; NYSE: CCJ) today reported its consolidated financial and operating results for the fourth quarter and year ended December 31, 2024, in accordance with International Financial Reporting Standards (IFRS).

�Our 2024 full-year financial performance benefitted from strong fourth quarter results delivered by our uranium and Westinghouse segments," said Tim Gitzel, Cameco's president and CEO. "Although both net earnings and adjusted net earnings in 2024 were lower than in 2023 primarily due to the impact of purchase accounting related to the Westinghouse acquisition, our other key financial metrics improved significantly. We expect our strong financial performance to continue in 2025, driven by the supportive market conditions we are seeing throughout the fuel cycle and across the nuclear sector, and through the continued benefits flowing from our investment in Westinghouse. Over the coming year, we expect to continue investing to help ensure reliability and sustainability of our existing operations, while positioning ourselves for future production flexibility and growth growth that will be strategic, deliberate, disciplined, and with a focus on generating full-cycle value.

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
High-Grade Mineralisation Identified at North Sweden Project

High-Grade Mineralisation Identified at North Sweden Project

Basin Energy (BSN:AU) has announced High-Grade Mineralisation Identified at North Sweden Project

Download the PDF here.

Global Atomic Provides Corporate Update

Global Atomic Corporation (" Global Atomic " or the " Company ") (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) is pleased to provide an update on recent activities at the Company and the Dasa Uranium Project in the Republic of Niger .

Global Atomic Corporation Logo (CNW Group/Global Atomic Corporation)

NIGER UPDATE

At the African Mining Indaba Conference held in Cape Town last week, the Company held several important meetings with Niger's Mines Minister Abarchi, who was present at the largest mining conference in Africa , promoting his Country to attract potential investors interested in the mining sector. The Minister emphasized the Government's strong support for Global Atomic and the Dasa Project, and confirmed his government has no intention to nationalize the Dasa Project.

In various meetings attended by Minister Abarchi at the Conference, he stated that Niger welcomes and encourages investment by foreign mining companies specifically including those from Canada , the United States and Australia.  Further, at the end of last week the Niger government announced plans to hold a major conference in mid-February to establish a process that will govern the transition to a democratic election.

The Company held additional meetings in Cape Town , including with new groups interested in financing the Dasa Project, as well as suppliers and contractors who are currently working with Global Atomic and SOMIDA.

PROJECT DEVELOPMENT

The advancement of the Dasa underground has progressed on the first two levels along the footwall of the ore body.  Five-meter diameter ventilation raises have been completed and commissioned enabling continued underground development while maintaining safe working conditions and efficiency.

Plant construction is proceeding on schedule with earthworks nearing completion and civil works underway and the concrete batch plant now under construction.  Large pieces of processing equipment such as the SAG mill shell, crusher and acid plant are now on site.  The camp that will house the plant construction crew is well underway with a large percentage of housing now ready for occupation.

FINANCING

Since the inauguration of President Trump in the United States of America , the market reaction has been that debt funding for the Dasa Project is unlikely to come from the USA .  However, these discussions continue as well as the advancement of the Joint Venture final documentation. It is important to remember that the Company has entered into off-take agreements for 8.8 million pounds U 3 O 8 over the first 7 years of the Mine; 90% of which has been sold to US utilities.  As a result of the many successful meetings at the Indaba Conference, new parties have indicated a willingness to participate in the final funding solution for Dasa. Management is confident that these initiatives will continue to progress, and we reiterate our belief that prior to the end of Q1, 2025, further clarity can be shared with the market.

Stephen Roman , President & CEO of Global Atomic, stated, " By advancing the development of the mine, processing plant and infrastructure, we have significantly moved the Dasa Project closer to production while continuously adding to the intrinsic value of the Dasa Project.  This is the basis of appraisal for all our financing discussions and not the current value of our shares."

A recent video of our progress in Niger is available at https://www.youtube.com/watch?v=ITl8r104-MA .

About Global Atomic

Global Atomic Corporation ( www.globalatomiccorp.com ) is a publicly listed company that provides a unique combination of high-grade uranium mine development and cash-flowing zinc concentrate production.

The Company's Uranium Division is currently developing the fully permitted, large, high grade Dasa Deposit, discovered in 2010 by Global Atomic geologists through grassroots field exploration.  The "First Blast Ceremony" occurred on November 5, 2022 , and commissioning of the processing plant is scheduled for Q1, 2026.  Global Atomic has also identified 3 additional uranium deposits in Niger that can be advanced with further assessment work.

Global Atomic's Base Metals Division holds a 49% interest in the Befesa Silvermet Turkey, S.L. (BST) Joint Venture, which operates a modern zinc recycling plant, located in Iskenderun, Türkiye. The plant recovers zinc from Electric Arc Furnace Dust (EAFD) to produce a high-grade zinc oxide concentrate which is sold to zinc smelters around the world. The Company's joint venture partner, Befesa Zinc S.A.U. (Befesa) holds a 51% interest in and is the operator of the BST Joint Venture.  Befesa is a market leader in EAFD recycling, with approximately 50% of the European EAFD market and facilities located throughout Europe , Asia and the United States of America .

CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS:

The information in this release may contain forward-looking information under applicable securities laws.  Forward-looking information includes, but is not limited to, statements with respect to completion of any financings; Global Atomics' development potential and timetable of its operations, development and exploration assets; Global Atomics' ability to raise additional funds necessary; the future price of uranium; the estimation of mineral reserves and resources; conclusions of economic evaluation; the realization of mineral reserve estimates; the timing and amount of estimated future production, development and exploration; cost of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; currency exchange rates; government regulation of mining operations; and environmental and permitting risks.   Generally, forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "is expected", "estimates", variations of such words and phrases or statements that certain actions, events or results "could", "would", "might", "will be taken", "will begin", "will include", "are expected", "occur" or "be achieved".  All information contained in this news release, other than statements of current or historical fact, is forward-looking information.   Statements of forward-looking information are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Global Atomic to be materially different from those expressed or implied by such forward-looking statements, including but not limited to those risks described in the annual information form of Global Atomic and in its public documents filed on SEDAR from time to time.

Forward-looking statements are based on the opinions and estimates of management at the date such statements are made.  Although management of Global Atomic has attempted to identify important factors that could cause actual results to be materially different from those forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended.  There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.  Accordingly, readers should not place undue reliance upon forward-looking statements.  Global Atomic does not undertake to update any forward-looking statements, except in accordance with applicable securities law.  Readers should also review the risks and uncertainties sections of Global Atomics' annual and interim MD&As.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy and accuracy of this news release.

Global Atomic - TSX 30 - OTX 50 (CNW Group/Global Atomic Corporation)

SOURCE Global Atomic Corporation

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/February2025/12/c0271.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Global Atomic Provides Corporate Update

Global Atomic Corporation (" Global Atomic " or the " Company ") (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) is pleased to provide an update on recent activities at the Company and the Dasa Uranium Project in the Republic of Niger .

Global Atomic Corporation Logo (CNW Group/Global Atomic Corporation)

NIGER UPDATE

At the African Mining Indaba Conference held in Cape Town last week, the Company held several important meetings with Niger's Mines Minister Abarchi, who was present at the largest mining conference in Africa , promoting his Country to attract potential investors interested in the mining sector. The Minister emphasized the Government's strong support for Global Atomic and the Dasa Project, and confirmed his government has no intention to nationalize the Dasa Project.

In various meetings attended by Minister Abarchi at the Conference, he stated that Niger welcomes and encourages investment by foreign mining companies specifically including those from Canada , the United States and Australia.  Further, at the end of last week the Niger government announced plans to hold a major conference in mid-February to establish a process that will govern the transition to a democratic election.

The Company held additional meetings in Cape Town , including with new groups interested in financing the Dasa Project, as well as suppliers and contractors who are currently working with Global Atomic and SOMIDA.

PROJECT DEVELOPMENT

The advancement of the Dasa underground has progressed on the first two levels along the footwall of the ore body.  Five-meter diameter ventilation raises have been completed and commissioned enabling continued underground development while maintaining safe working conditions and efficiency.

Plant construction is proceeding on schedule with earthworks nearing completion and civil works underway and the concrete batch plant now under construction.  Large pieces of processing equipment such as the SAG mill shell, crusher and acid plant are now on site.  The camp that will house the plant construction crew is well underway with a large percentage of housing now ready for occupation.

FINANCING

Since the inauguration of President Trump in the United States of America , the market reaction has been that debt funding for the Dasa Project is unlikely to come from the USA .  However, these discussions continue as well as the advancement of the Joint Venture final documentation. It is important to remember that the Company has entered into off-take agreements for 8.8 million pounds U 3 O 8 over the first 7 years of the Mine; 90% of which has been sold to US utilities.  As a result of the many successful meetings at the Indaba Conference, new parties have indicated a willingness to participate in the final funding solution for Dasa. Management is confident that these initiatives will continue to progress, and we reiterate our belief that prior to the end of Q1, 2025, further clarity can be shared with the market.

Stephen Roman , President & CEO of Global Atomic, stated, " By advancing the development of the mine, processing plant and infrastructure, we have significantly moved the Dasa Project closer to production while continuously adding to the intrinsic value of the Dasa Project.  This is the basis of appraisal for all our financing discussions and not the current value of our shares."

A recent video of our progress in Niger is available at https://www.youtube.com/watch?v=ITl8r104-MA .

About Global Atomic

Global Atomic Corporation ( www.globalatomiccorp.com ) is a publicly listed company that provides a unique combination of high-grade uranium mine development and cash-flowing zinc concentrate production.

The Company's Uranium Division is currently developing the fully permitted, large, high grade Dasa Deposit, discovered in 2010 by Global Atomic geologists through grassroots field exploration.  The "First Blast Ceremony" occurred on November 5, 2022 , and commissioning of the processing plant is scheduled for Q1, 2026.  Global Atomic has also identified 3 additional uranium deposits in Niger that can be advanced with further assessment work.

Global Atomic's Base Metals Division holds a 49% interest in the Befesa Silvermet Turkey, S.L. (BST) Joint Venture, which operates a modern zinc recycling plant, located in Iskenderun, Türkiye. The plant recovers zinc from Electric Arc Furnace Dust (EAFD) to produce a high-grade zinc oxide concentrate which is sold to zinc smelters around the world. The Company's joint venture partner, Befesa Zinc S.A.U. (Befesa) holds a 51% interest in and is the operator of the BST Joint Venture.  Befesa is a market leader in EAFD recycling, with approximately 50% of the European EAFD market and facilities located throughout Europe , Asia and the United States of America .

CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS:

The information in this release may contain forward-looking information under applicable securities laws.  Forward-looking information includes, but is not limited to, statements with respect to completion of any financings; Global Atomics' development potential and timetable of its operations, development and exploration assets; Global Atomics' ability to raise additional funds necessary; the future price of uranium; the estimation of mineral reserves and resources; conclusions of economic evaluation; the realization of mineral reserve estimates; the timing and amount of estimated future production, development and exploration; cost of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; currency exchange rates; government regulation of mining operations; and environmental and permitting risks.   Generally, forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "is expected", "estimates", variations of such words and phrases or statements that certain actions, events or results "could", "would", "might", "will be taken", "will begin", "will include", "are expected", "occur" or "be achieved".  All information contained in this news release, other than statements of current or historical fact, is forward-looking information.   Statements of forward-looking information are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Global Atomic to be materially different from those expressed or implied by such forward-looking statements, including but not limited to those risks described in the annual information form of Global Atomic and in its public documents filed on SEDAR from time to time.

Forward-looking statements are based on the opinions and estimates of management at the date such statements are made.  Although management of Global Atomic has attempted to identify important factors that could cause actual results to be materially different from those forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended.  There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.  Accordingly, readers should not place undue reliance upon forward-looking statements.  Global Atomic does not undertake to update any forward-looking statements, except in accordance with applicable securities law.  Readers should also review the risks and uncertainties sections of Global Atomics' annual and interim MD&As.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy and accuracy of this news release.

Global Atomic - TSX 30 - OTX 50 (CNW Group/Global Atomic Corporation)

SOURCE Global Atomic Corporation

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/February2025/12/c0271.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Positive Uranium Leach Test Results at Lo Herma

Positive Uranium Leach Test Results at Lo Herma

GTI Energy (GTR:AU) has announced Positive Uranium Leach Test Results at Lo Herma

Download the PDF here.

Latest Press Releases

Related News

×