Santacruz Silver Reports Q1 2021 Production of 706,978 Silver Equivalent Ounces

Santacruz Silver Mining Ltd. (TSXV: SCZ) (the "Company" or "Santacruz") reports its operating results from the Zimapan Mine located in Zimapan, Hidalgo, Mexico and the Rosario Project located in Charcas, San Luis Potosi, Mexico, for the first quarter 2021 ("Q1"). The Company is not including production from the Veta Grande Project in this report as operations at Veta Grande were suspended during Q1 2020.

Production Highlights:

  • Silver equivalent ounces produced 706,978
  • Silver head grades increase 9.4 % at Zimapan Mine as compared to Q1 and Q4 2020
  • Increased tonnage throughput from Lomo del Toro zone of the Zimapan Mine from 4,000 during January and February to 6,000 tonnes for the month of March
  • New mining method introduced in late March at Rosario that is expected to significantly reduce costs by less handling of waste material

Carlos Silva, Santacruz's COO, stated, "As we keep advancing our workings deeper into the higher-grade Lomo del Toro manto and increase the tonnage mined from this zone, we are seeing a corresponding increase in head grades at our Zimapan Mine. We are progressing well towards our objective of reaching 15,000 tonnes per month of mill feed from this higher-grade area by the end of the second quarter." Mr. Silva continued, "We expect further efficiencies at our Rosario Project during Q2 as a result of a revised mining plan which results in less waste material being handled. These very encouraging improvements were unfortunately partially offset by an unstable power supply from Mexico's Comision Federal de Electricidad (Mexico's power supply Company). The unstable power supply impacted the mill throughput at both mines in February as motors for the ball mills were damaged. The matter was resolved in early March but mill throughput was materially reduced for eight days."

COVID-19 Update

The Company continues to take all appropriate measures to prevent COVID-19 among the work force and local communities and to monitor the effectiveness of these measures in mitigating any potential impact on business activities. The Company's actions have been successful to date and the pandemic has not had any material impact on the business.

CONSOLIDATED PRODUCTION RESULTS

2021 Q12020 Q42020 Q1
Material Processed (tonnes milled)176,239191,043157,400
Silver eqv. ounce production706,978943,103902,765
Silver production (ounces)325,376318,764274,678
Gold production (ounces)727183
Lead production (tonnes)945970965
Zinc production (tonnes)2,2852,8382,674
Copper production (tonnes)354365438
Average Head Grade (g/t Ag Eqv.)176221241
Development (metres)2,2122,8912,170

 

ZIMAPAN MINE PRODUCTION RESULTS

2021 Q12020 Q42020 Q1
Material Processed (tonnes milled)156,433171,313139,903
Silver eqv. ounce production646,085858,362829,514
Silver production (ounces)294,099277,154245,344
Silver head grade (g/t)857777
Gold head grade (g/t)---
Lead head grade (%/t)0.630.630.73
Zinc head grade (%/t)1.992.252.41
Copper head grade (%/t)0.310.320.43
Silver recovery (%)69.065.571.2
Gold production (ounces)---
Lead production (tonnes)892900913
Zinc production (tonnes)2,0672,6202,443
Copper production (tonnes)354365438
Average Head Grade (g/t Ag Eqv.)182228250
Development (metres)1,7242,0951,418

 

ROSARIO MINE PRODUCTION RESULTS

2021 Q12020 Q42020 Q1
Material Processed (tonnes milled)19,80619,73017,497
Silver eqv. ounce production60,89384,74173,251
Silver production (ounces)31,27741,61029,334
Silver head grade (g/t)617463
Gold head grade (g/t)0.190.180.22
Lead head grade (%/t)0.340.400.36
Zinc head grade (%/t)1.511.381.78
Copper head grade (%/t)---
Silver recovery (%)80.388.382.4
Gold production (ounces)59.461.668.7
Lead production (tonnes)78.089.682.0
Zinc production (tonnes)73.079.873.9
Copper production (tonnes)---
Average Head Grade (g/t Ag Eqv.)727184
Development (metres)4887052

 

* In the above tables Ag Eq has been calculated as follows:

2021 Ag Eq was calculated using metal prices of: Ag $25.00/oz, Au $1,925/oz, Pb $0.85/lb, Zn $1.05/lb and Cu $3.00/lb.
2020 Ag Eq was calculated using metal prices of: Ag $17.85/oz, Au $1,480/oz, Pb $0.92/lb, Zn $1.09/lb and Cu $2.80/lb.

Silver Equivalent Comparative Production

As noted in the tables above, there is a significant reduction in silver equivalent ounces produced in Q1 2021 as compared to that produced in Q1 and Q4 2020. This negative change in production is due in large part to the metal prices used for this calculation in 2021 as compared to 2020. For example, had the Company used the 2020 metal price deck for its silver equivalent production calculation at the Zimapan Mine in Q1 2021, the reported silver equivalent ounces produced would have been 868,750, an increase of 9.1% over the current reported balance. On a comparative basis within any particular fiscal year or between periods in different fiscal years where the metal price decks are relatively equivalent, this computation is useful for comparing production from one period to another. When the price decks are not relatively equivalent, the usefulness of this production indicator is diminished.

About Santacruz Silver Mining Ltd.

Santacruz is a Mexican focused silver company with two producing silver projects (Zimapan and Rosario) and two exploration properties, the La Pechuga property and Santa Gorgonia prospect. The Company is managed by a technical team of professionals with proven track records in developing, operating and discovering silver mines in Mexico. Our corporate objective is to become a mid-tier silver producer.

'signed'

Arturo Préstamo Elizondo,
Executive Chairman

For further information please contact:

Mars Investor Relations
Telephone: (778) 999 4653
scz@marsinvestorrelations.com

Arturo Prestamo
Santacruz Silver Mining Ltd.
Email: info@santacruzsilver.com
Telephone: (528) 183 785707

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-looking information

Certain statements contained in this news release constitute "forward-looking information" as such term is used in applicable Canadian securities laws, including statements relating to production at the Zimapan Mine and Rosario Project and the Company's plans to grow it. Forward-looking information is based on plans, expectations and estimates of management at the date the information is provided and is subject to certain factors and assumptions. In making the forward-looking statements included in this news release, the Company has applied several material assumptions., including, but not limited to, assumptions as the Company's financial condition and development plans do not change as a result of unforeseen events, that the Company will receive all required regulatory approvals, and that future metal prices and the demand and market outlook for metals will remain stable or improve. Forward-looking information is subject to a variety of risks and uncertainties and other factors that could cause plans, estimates and actual results to vary materially from those projected in such forward-looking information. Factors that could cause the forward-looking information in this news release to change or to be inaccurate include, but are not limited to, the risk that any of the assumptions referred to above prove not to be valid or reliable; market conditions and volatility and global economic conditions, including increased volatility and potentially negative capital raising conditions resulting from the continued COVID-19 pandemic and risks relating to the extent and duration of such pandemic and its impact on global markets; risk of delay and/or cessation in planned work or changes in the Company's financial condition and development plans; risks associated with the interpretation of data (including in respect of third party mineralized material) regarding the geology, grade and continuity of mineral deposits; the uncertainty of the geology, grade and continuity of mineral deposits and the risk of unexpected variations in mineral resources, grade and/or recovery rates; risks related to gold, silver, base metal and other commodity price fluctuations; risks relating to environmental regulation and liability; the possibility that results will not be consistent with the Company's expectations, as well as the other risks and uncertainties applicable to mineral exploration and development activities and to the Company as set forth in the Company's continuous disclosure filings filed under the Company's profile at www.sedar.com. There can be no assurance that any forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, the reader should not place any undue reliance on forward-looking information or statements. The Company undertakes no obligation to update forward-looking information or statements, other than as required by applicable law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/83902

News Provided by Newsfile via QuoteMedia

The Conversation (0)

Pan American Silver Provides Annual Exploration Update

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") provides an annual exploration update and releases new exploration drill results for its Jacobina, El Peñon, La Colorada, Huaron, Minera Florida and Timmins mines, as well as its La Colorada Skarn project.

"The success of our exploration program highlights the potential for long-term organic growth at many of our assets," said Christopher Emerson, Vice President of Exploration and Geology at Pan American. "Based on the results we were achieving in exploration this year, we increased our drill budget to over 450,000 metres for 2024. This exploration update highlights these results, and showcases the ongoing discovery of new mineralized structures in and around our existing mining operations."

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Boab Metals

Boab Metals Limited (ASX: BML) – Trading Halt

Boab Metals Limited (ASX:BML) (the “Company”) hereby requests a trading halt of its securities be granted by the ASX effective immediately, pending a release of an announcement regarding an Offtake and Project Finance Agreement. The trading halt will last until the earlier of commencement of trading on Wednesday, 11 December 2024 or the release to the market of an announcement as specified above. The Company is not aware of any reason why the trading halt should not be granted or of any other information necessary to inform the market about the trading halt. This request was authorised for release by the Board of the Company.

Keep reading...Show less
Open-pit mine.

What Makes VMS Deposits Attractive Targets?

As investors well know, there is no such thing as a sure bet with the stock market. Against a backdrop of fluctuating metals prices, volcanogenic massive sulfide (VMS) deposits may look more attractive than ever.

That’s thanks to their polymetallic content. Often containing copper, zinc, lead, silver and gold, VMS deposits can offer resource investors some cushion regarding the rise and fall of individual metals. If it’s a rough year for copper prices, for example, profits off zinc or gold might still help a VMS deposit company’s stock soar.

Furthermore, VMS deposits are an opportunity to buy into both the precious and base metals markets — two very different landscapes. The latter tends to be driven by commodities markets, while precious metals like gold and silver are often seen as safe-haven investments. The principle of diversification, then, seems built into a VMS deposit itself.

Keep reading...Show less

Pan American Silver Completes the Sale of La Arena

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ( "Pan American" ) yesterday completed the previously announced divestment of its 100% interest in La Arena S.A. ("La Arena"), which owns the La Arena gold mine as well as the La Arena II project in Peru, to Jinteng (Singapore) Mining Pte. Ltd., a subsidiary of Zijin Mining Group Co., Ltd. (collectively, "Zijin").

Under the terms of the agreement, Zijin paid US$245 million in cash consideration and granted Pan American a life-of-mine gold net smelter return royalty of 1.5% for the La Arena II project. Upon commencement of commercial production from the La Arena II project, the agreement provides for an additional contingent payment from Zijin of US$50 million in cash.

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Rows of silver bars with two bars lying on top.

ASX Silver Stocks: 5 Biggest Companies in 2024

The precious metal silver is often compared to gold due to its importance in jewellery and as a safe haven investment.

However, silver has many industrial applications too, including in electronics, automobiles, medicine and photography, and, of course, silverware.

Energy transition applications are a growing demand sector for silver — the metal is valued for its conductive capacity, which makes it particularly useful in the production of photovoltaic panels.

Silver supply has tightened in recent years as industrial demand rises. This was one of several factors that helped the silver price break through the US$30 per ounce mark in May for the first time since 2013. At that time, it also broke AU$48, setting a new all time high in Australian dollars.

Keep reading...Show less

Latest Press Releases

Related News

×